Weekend Sale Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

SAP C_TPLM22_67 SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Exam Practice Test

Page: 1 / 17
Total 165 questions

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Question 1

Your customer uses Progress Tracking for network components and maintains dates of events manually. They need to implement scheduling of events. What is the prerequisite for scheduling of events? *

Options:

A.

Priority of Events must be set

B.

Event Scenarios must be defined

C.

Scheduling Paramaters for Material Scheduling must be set

D.

Events must be released manually

Question 2

Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?

There are 2 correct answers to this question.

Response:

Options:

A.

WBS elements

B.

Activities

C.

Milestones

D.

Structures

Question 3

In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?

Please choose the correct answer.

Response:

Options:

A.

Available to promise check

B.

Available on booking check

C.

Available on requirement check

D.

Immediate delivery check

Question 4

Which of the following information regarding cost activity is not relevant for the calculation of planned costs?

Please choose the correct answer.

Response:

Options:

A.

Control key

B.

The cost element is defaulted for cost activities based on the network profile

C.

A unit costing that enables detailed planning with multiple cost elements, or an invoicing plan

D.

Cost activities based on external services

Question 5

Which of the following helps you to adjust cost planning to changing circumstances during the execution phase of the project?

Please choose the correct answer.

Response:

Options:

A.

Progress analysis

B.

Cost forecasts

C.

Overhead costs

D.

Interest forecast

Question 6

An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?

Please choose the correct answer.

Response:

Options:

A.

Activity analysis tool

B.

Relationship analysis tool

C.

Cycle analysis tool

D.

Loop analysis tool

Question 7

Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response?

Please choose the correct answer.

Response:

Options:

A.

Budget plan

B.

Availability control

C.

Time horizon

D.

Tolerance limit

Question 8

What are the different options available for project stock?

There are 3 correct answers to this question.

Response:

Options:

A.

No project stock

B.

Valuated project stock

C.

Non-valuated project stock

D.

WBS project stock

Question 9

Where can you define that a network is a "header-account assigned" or "activity-account assigned"?

Options:

A.

Network profile

B.

Parameters for the network type

C.

Project profile

D.

Network type

Question 10

You have implemented automatic requirements grouping for projects. Once you check the materials turbine and fittings you realize that the requirements are grouped for turbine but not for fittings. What might be the reason?

Please choose the correct answer.

Response:

Options:

A.

The grouping indicator of the top WBS element is set to a single MRP Group.

B.

The network is set to no grouping for specific MRP Groups.

C.

The MRP Group for fittings is deactivated for grouping.

D.

The project definition is set to no project stock.

Question 11

What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?

Please choose the correct answer.

Response:

Options:

A.

Workflow indicator

B.

Workflow purchase order change indicator

C.

Workflow change indicator

D.

Purchase order change indicator

Question 12

In general the costs of internally processed activities and general cost activities can be distributed as required over the network duration and this distribution is controlled using a distribution key that can be stored in the activity.

How are costs distributed if a distribution key is not maintained in the activity for internally processed activities?

Please choose the correct answer.

Response:

Options:

A.

The costs are distributed evenly over the earliest dates in the activity

B.

The system uses the key from the work center

C.

System uses valuation variant

D.

Costing key is considered

Question 13

Which combination allows you to assign the material components in one WBS element to different grouping WBS element?

There are 2 correct answers to this question.

Response:

Options:

A.

Plant

B.

Material group

C.

MRP group

D.

WBS group

Question 14

Project System has its own Organizational structure, which can be a matrix structure.

Please choose the correct answer.

Response:

Options:

A.

True

B.

False

Question 15

Which SAP standard item category always leads to direct procurement and a purchase requisition generated by the network?

Please choose the correct answer.

Response:

Options:

A.

Non-stock item

B.

Stock item

C.

Billing item

D.

Non-billing item

Question 16

Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?

Please choose the correct answer.

Response:

Options:

A.

Individual confirmation

B.

Single confirmation

C.

Collective confirmation

D.

Group confirmation

Question 17

Can you specify in the application which status profile should be used the first time you set a user status where a status profile has not yet been defined in the project profile?

Please choose the correct answer.

Response:

Options:

A.

Yes

B.

No

C.

Yes using operative status

D.

Yes using status modes

Question 18

In which of the following ways Open PS allows you to exchange data directly with MS project?

There are 3 correct answers to this question.

Response:

Options:

A.

Create a project in MS project from an SAP PS project

B.

Transfer a project from MS project to SAP PS

C.

Download MS project and Upload to SAP PS

D.

Reconcile data from a project in Microsoft Project with a project in SAP PS

Question 19

Which variant defines the valuation procedure for materials, internal activities, external activities, and business processes?

Please choose the correct answer.

Response:

Options:

A.

Costing variant

B.

Valuation variant

C.

Planned cost variant

D.

Network variant

Question 20

With reference to WBS scheduling, which of the following statements are FALSE?

Please choose the correct answer.

Response:

Options:

A.

In WBS scheduling, the activities which are assigned to the selected WBS elements are scheduled. In network scheduling on the other hand, all activities which belong to the network are scheduled.

B.

If you selected scheduling type 'WBS determines dates', the earliest start date of the activities is defaulted from the respective WBS elements in case of forward scheduling (or the latest finish date of the activities in case of backward scheduling).

C.

The execution of WBS scheduling consists of 2 steps: 1. Determining the initial dates (start dates for forward scheduling or finish dates for backward scheduling). 2. Transferring the dates of the activities into respective network headers and WBS elements.

D.

Activities which are not scheduled, but have relationships to activities involved in scheduling, are viewed as external activities. In this case, the dates of the external activity are taken into account as restricting dates.

Question 21

Which of the following determines the item category assigned in the sales documents?

There are 2 correct answers to this question.

Response:

Options:

A.

Sales document type

B.

Schedule line items

C.

Material pricing group

D.

Material item category group

Question 22

How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities?

Please choose the correct answer.

Response:

Options:

A.

Reduction

B.

Scheduling breech

C.

Milestones

D.

Capacity breech

Question 23

Where else should you make manual changes; if you assign bill of materials (BOM) items to a network activity manually by exploding the BOM and then changed the BOM?

Please choose the correct answer.

Response:

Options:

A.

Network

B.

Assignments

C.

Cost object

D.

Material view

Question 24

Which type of reports allows you to choose the objects whose costs you want to analyze or call up an appropriate list and choose the period you want to evaluate?

Please choose the correct answer.

Response:

Options:

A.

Hierarchy reports

B.

Cost element reports

C.

Period analysis reports

D.

Structural reports

Page: 1 / 17
Total 165 questions