Labour Day Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PRINCE2 Prince2-Foundation PRINCE2 Foundation Exam Exam Practice Test

Page: 1 / 46
Total 461 questions

PRINCE2 Foundation Exam Questions and Answers

Question 1

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Question 2

Which is an objective of the ‘directing a project’ process?

Options:

A.

To tailor the project’s products and roles so that the project suits the circumstances

B.

To respond to the project mandate by starting up a project

C.

To provide an interface between the project and corporate management

D.

To ensure the stage products are delivered to the stated quality standards

Question 3

Which is a minimum requirement for applying the 'change' theme?

Options:

A.

Specify in the change control approach the means by which project products will be protected

B.

Document the format and contents of the issue register

C.

Produce issue reports to document the impact assessment for requests for change

D.

Delegate the change authority to the senior supplier(s) for supplier off-specifications

Question 4

What is established during the 'initiating a project' process?

Options:

A.

The agreed protect acceptance criteria

B.

The need for a configuration library

C.

A plan for the work or project initiation

D.

An understanding of the project's funding

Question 5

Why is it necessary to apply the 'defined roles and responsibilities' principle?

Options:

A.

Because the people involved in a project should know what is expected of them

B.

Because the project management team should be cross-functional

C.

Because the user and supplier interests should be involved on a need-to-know basis

D.

Because the project manager should represent all the stakeholders of the project

Question 6

According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?

Options:

A.

One

B.

Two

C.

Three

D.

Six

Question 7

Which statement about the length of management stages in a project is CORRECT?

Options:

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Question 8

Which is a minimum requirement for applying the quality theme?

Options:

A.

To define the project’s approach to quality assurance

B.

To appoint external reviewers for quality reviews

C.

To define quality criteria in product descriptions

D.

To provide administrative support for quality controls

Question 9

How can the risk culture of 3n organization make decision-making less effective?

Options:

A.

By using statistical modelling be understand the Impact of risks and their likelihood

B.

By establishing a risk budget to make funding risk responses actions easier

C.

By Individuals adopting an attitude that leads them to ignore threats to objectives

D.

By Involving stakeholders in assessing the likelihood and impact of each risk

Question 10

Which is a purpose of the quality theme?

Options:

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Question 11

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 12

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Question 13

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

Options:

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Question 14

What should be recorded in a quality register?

1. Activities to ensure the products are fit for purpose

2. Identified threats and opportunities

3. Problems and concerns to be managed informally

4. Roles responsible for reviewing the project's products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 15

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options:

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Question 16

What should be implemented using a risk budget?

1. A request for change

2. A contingent plan

3. Actions to avoid a risk from occurring

4. Responses to dis-benefits

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 17

Which is a responsibility of the project board?

Options:

A.

To manage the team managers and project support

B.

To ensure production of the project's outputs

C.

To ensure effective communication with external stakeholders

D.

To implement the change control approach

Question 18

Whitt is 3 purpose of the initiating a project’ process?

Options:

A.

To prepare the contract for the project to enable the project board to commit to delivery

B.

To provide the project board with Just Enough Information to decide whether to approve the Initiation stage

C.

To provide the opportunity for the senior user in confirm that they find the project product acceptable

D.

To enable the project board to empower the project manager to work within delegated authority limits

Question 19

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

Options:

A.

delivery step

B.

benefit

C.

delivery stage

D.

team plan

Question 20

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Question 21

What is an advantage of applying the 'manage by stages' principle?

Options:

A.

The PRINCE2 method can be used for any type of project

B.

The project delivers benefits that are aligned with strategic objectives

C.

The project has decision points so that it does not run on in an uncontrolled manner

D.

Tolerances can be defined for delegated authority

Question 22

Which is a minimum requirement for applying the change theme?

Options:

A.

To identify whether an issue affects the continuation of the project

B.

To ensure each change is managed as an exception

C.

To produce a breakdown of the products to be produced

D.

To tailor all changes to improve the quality of the project

Question 23

Which statement about project roles is CORRECT?

Options:

A.

The project organization must be defined using the roles and responsibilities in PRINCE2

B.

The project team structure defined in PRINCE2 must be used, but other roles may be added

C.

The project board roles defined in PRINCE2 must be used, but other roles can be defined as required

D.

Any role can be defined as required the responsibilities defined in PRINCE2 are fulfilled

Question 24

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Question 25

Which are purposes of the 'directing a project' process?

1. To enable the project board to be accountable for a project's success by making key decisions

2. To enable the project board to authorize work packages

3. To enable the project board to prepare the communication management approach

4. To enable the project board to exercise overall control of a project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 26

Which activity is part of the recommended risk management procedure?

Options:

A.

Allocating a budget to investigate issues

B.

Reviewing risk management practices to ensure that they are performing effectively

C.

Sending information to stakeholders about risks to the projects

D.

Resolving conflicts between the project and the programme board

Question 27

Which is an assumption about the PRINCE2 customer/supplier environment?

Options:

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Question 28

The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.

In which step of ‘business case management technique should this be considered?

Options:

A.

Develop

B.

Check

C.

Maintain

D.

Confirm

Question 29

How are team managers involved in tailoring PRINCE2 suit the project?

Options:

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Question 30

What is a risk actionee responsible for?

Options:

A.

Identifying risks to the project that might occur in their department

B.

Owning and authorizing the use of the risk budget to fund risk responses

C.

Managing, monitoring and controlling of all aspects of an assigned risk

D.

Carrying out a risk response action to respond to a particular risk

Question 31

Which is a purpose of the 'directing a project' process?

Options:

A.

To create and authorize the project mandate

B.

To ensure that work on products allocated to the team is authorized and agreed

C.

To control the day-to-day running of the project

D.

To delegate day-to-day management of the project to the project manager

Question 32

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

Options:

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Question 33

Which is a purpose of the 'initiating a project' process?

Options:

A.

To ensure the project has a sound basis before asking the project board to authorize the project

B.

To authorize the stage plan for the next management stage of the project

C.

To establish a contract between the project management team and the commissioning organization

D.

To ensure that prerequisites are in place before starting the project

Question 34

How does the ‘managing product delivery’ process ensure that the team manager’s perspective is provided in a work package?

Options:

A.

The work packages are defined by the team manager and supported by a team plan

B.

the work packages provided by the project manager are agreed by the team manager

C.

The team plans are checked by project assurance against the work packages

D.

The stage plan covering the work packages is created with input from the team manager

Question 35

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

Options:

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

Question 36

Which statement describes a purpose of the 'starting up a project’ process?

Options:

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers

Question 37

Which feature of a stage plan suggests that a project is in danger of scope creep?

Options:

A.

Stage plans are prepared by the project manager as the stage comes to an end

B.

Products identified in a stage plan cannot be traced back to the project plan

C.

The team delivering the stage plan includes staff from different parts of an organization

D.

it is not possible to implement remedial actions for an exception by updating a stage plan

Question 38

Which describes user's quality expectations?

Options:

A.

They are documented in the project product description

B.

They are documented in the quality management approach

C.

They are documented in the stage plan

D.

They are documented in the product descriptions

Question 39

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

Options:

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Question 40

What is a description of a purpose of the ‘quality’ practice?

Options:

A.

To enable the project products to meet the documented expectations of the user

B.

To document fundamental information to make rational sneer (Wert commissioning the project

C.

To establish the basis for the project, to enable the work to deliver the project product to be understood

D.

To monitor the allocated work, deal with issues, and allocate additional work if required

Question 41

Which team is defined as motivating people to achieve a project’s objectives?

Options:

A.

Leadership

B.

Management

C.

Quality assurance

D.

Co-creation

Question 42

Which statement about capability and competency within a project is CORRECT?

Options:

A.

People who appear to have the same skills and experience will probably undertake the same tasks in different ways

B.

People within a team will perform equally when working with different people

C.

People who have participated in developing ways of working are more willing to be managed

D.

People working as team members often have conflicting priorities contrary to the project's needs

Question 43

What is a temporary organization that is treated for the purpose of delivering Business Products according an-agrees business casa?

Options:

A.

A project

B.

A baselined product

C.

The project scope

D.

The business

Question 44

Which is a feature of an effective project team?

Options:

A.

It should rely on the team sitting together in order to easily build effective working relationships

B.

It should consist of people with a wide range of skills, abilities and viewpoints

C.

It should plan and control effective communications with the project's stakeholders

D.

It should consist of full-time team members who can focus attention on the project's needs

Question 45

Which member of the project management team should secure funding for the project before the project stars?

Options:

A.

Project executive

B.

Project manager

C.

Senior user

D.

senior supplier

Question 46

Which is a definition of management?

Options:

A.

Instructing the execution of tasks in line with agreed ways of working

B.

Translating stakeholder requirements into quality criteria

C.

Assigning people with specific skills and capabilities to work on multiple projects

D.

Defining, assuring, and accepting products back into the business

Question 47

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

Options:

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Question 48

When is a work breakdown structure MOST useful?

Options:

A.

When there are multiple work packages with a mix of internal and external resources

B.

in a simple project with one work package for the work of a small team

C.

When establishing a change authority aligned to project tolerances

D.

When assuring business, user and supplier aspects of project performance

Question 49

Which principle should ensure that a project remains aligned with the objectives of the investing organizations?

Options:

A.

Focus on products

B.

Manage by exception

C.

Tailor to suit the project

D.

Ensure continued business justification

Question 50

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Directing a project

D.

Managing a stage boundary

Question 51

In which step of the Issue management’ technique should Superseded versions be archives?

Options:

A.

Implementing changes

B.

Assessing issues

C.

capturing issues

D.

Deciding on changes

Question 52

Which management product Soul guide the Project management team on how to manage multiple aspects of the project?

Options:

A.

Project initiation documentation

B.

Project plan

C.

Business case

D.

Exception plan

Question 53

Which common project context relates to the need to engage with external suppliers to deliver part of the project?

Options:

A.

Commercial

B.

Delivery method

C.

Organizational

D.

Scale

Question 54

The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.

Which principle is being applied by the team manager as part of the 'people’ element when holding this workshop?

Options:

A.

Focus on products

B.

Tailor to suit the project

C.

Define roles, responsibilities and relationships

D.

Ensure continued business justification

Question 55

Which term is defined as a product that will not meet is quality specifications?

Options:

A.

Off-specification

B.

Request for change

C.

Concern

D.

Problem

Question 56

Which TWO are objectives of the 'managing a stage boundary" process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 57

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

Options:

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Question 58

Which is a definition of management?

Options:

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Question 59

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a team manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Question 60

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

Options:

A.

In stage of team plans to allow mare accurate scheduling

B.

As quality tolerances in product descriptions

C.

As acceptance criteria in the project product description

D.

In the quality management approach to plan the testing

Question 61

As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.

In which step of 'business case management' technique should the project manager assess this?

Options:

A.

Develop

B.

Check ay

C.

Maintain

D.

Confirm

Question 62

What should set the expected success level for benefits, time, cost, quality, scope, sustainability and risk?

Options:

A.

Performance target

B.

Project baseline

C.

Integrated elements

D.

Project context

Question 63

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

Options:

A.

Managing product delivery

B.

controlling a stage

C.

Managing a stage boundary

D.

closing a project

Question 64

The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

Options:

A.

issue register

B.

issue report

C.

Issue management approach

D.

Risk management approach

Question 65

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

Options:

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Question 66

Which is the definition of a requirement?

Options:

A.

A need or expectation that has been documented in an approved management product

B.

An event relevant to the project that requires project management consideration

C.

A prediction about future performance made by studying historical data and past patterns

D.

An uncertain event that, should it occur, will have an effect on the project.

Question 67

What is a purpose of the ‘organizing practice?

Options:

A.

To define who is responsible for which project activities

B.

To compare the team's actual achievements against the team plan

C.

Ta understand what the users require of the project

D.

To assess modifications raised by team members

Question 68

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Question 69

The project manager needs to know whether the response to a threat to the project has been actioned.

Which should the project manager review?

Options:

A.

Risk register

B.

Product register

C.

Risk management approach

D.

Checkpoint report

Question 70

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

Options:

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Question 71

How many roles make up the Project Board?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Question 72

Which is a difference between management and technical stages?

Options:

A.

Management stages require planning and technical stages do not

B.

Technical stages can overlap and management stages cannot

C.

Management stages deliver products and technical stages do not

D.

Technical stages require resources and management stages do not

Question 73

How many tasks does the product-based planning technique describe?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Question 74

Which is an objective of the Managing Product Delivery process?

Options:

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Question 75

Which is a purpose of a Project Product Description?

Options:

A.

Records the costs and timescales for delivery of the project's final product

B.

Shows the dependencies between the project's products to aid planning

C.

Provides a list of all the products to be delivered by the project

D.

Defines what the project must deliver in order to gain acceptance

Question 76

What theme estimates the cost of delivering the project?

Options:

A.

Business Case

B.

Change

C.

Plans

D.

Progress

Question 77

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Question 78

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

Options:

A.

Closing a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Question 79

Which of the following statements about quality assurance and Project Assurance is true?

Options:

A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Question 80

Which should be funded by a change budget?

Options:

A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Question 81

Who carries out audits that are independent of the project?

Options:

A.

Quality assurance

B.

Project Assurance

C.

Project Support

D.

Project Manager

Question 82

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Options:

A.

Configuration Item Record

B.

Quality Register

C.

Highlight Report

D.

Checkpoint Report

Question 83

Which statement about stages is true?

Options:

A.

Management stages should be of the same duration

B.

The use of technical stages is mandatory

C.

The use of management stages is mandatory

D.

Management stages are driven by specialist teams

Question 84

What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options:

A.

Directing a Project

B.

Managing a Stage Boundary

C.

Controlling a Stage

D.

Starting up a Project

Question 85

Which is a purpose of the Quality theme?

Options:

A.

Establish how the project will ensure that all products created meet their requirements

B.

Establish quality assurance to maintain the quality management system

C.

Identify all the products of the project to ensure the scope has been adequately defined

D.

Determine the communication needs of the organization's quality assurance function

Question 86

Which is a typical core activity within configuration management?

Options:

A.

Issue management

B.

Quality inspection

C.

Identification

D.

Preparation

Question 87

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Chair

D.

Producer

Question 88

Which is NOT a purpose of a Benefits Review Plan?

Options:

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Question 89

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

Options:

A.

Executive

B.

Senior User

C.

Senior Supplier

D.

Project Manager

Question 90

In what process is the authorization to deliver the project's products given?

Options:

A.

Starting up a Project

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Directing a Project

Question 91

From whom does a Team Manager obtain approval for a completed product?

Options:

A.

Project Manager

B.

Project Support

C.

The authority defined in the Product Description

D.

Senior Supplier

Question 92

Which is a purpose of the Directing a Project process?

Options:

A.

Create and authorize the project mandate

B.

Ensure that work on products allocated to the team is authorized and agreed

C.

Control the day-to-day running of the project

D.

Delegate day-to-day management of the project to the Project Manager

Question 93

Which is NOT one of the PRINCE2 integrated elements?

Options:

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Question 94

Which is a purpose of the Controlling a Stage process?

Options:

A.

Assign work to be done and take corrective action to ensure that the stage remains within tolerance

B.

Provide a fixed reference point at which acceptance for the project product is confirmed

C.

Enable the Project Board to be provided with sufficient information to authorize the next stage

D.

Enable the organization to understand the work that needs to be done to deliver the project's products

Question 95

Which of the following statements about stakeholders are true?

1. Someone who thinks they will be affected by a project is a stakeholder on that project.

2. Stakeholders may be internal or external to the corporate organization.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Question 96

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

Options:

A.

Capture

B.

Examine

C.

Propose

D.

Decide

Question 97

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Question 98

How many management stages should a PRINCE2 project consist of?

Options:

A.

Start up stage, initiation stage and at least one other management stage to cover the remainder of the project

B.

Start up stage, at least one other management stage to cover the remainder of the project and a closing stage

C.

Initiation stage and at least one other management stage to cover the remainder of the project

D.

Start up stage, initiation stage and a closing stage

Question 99

Which is one of the six aspects of project performance that needs to be managed?

Options:

A.

Progress

B.

Change

C.

Risk

D.

Security

Question 100

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Question 101

Which is a purpose of the Initiating a Project process?

Options:

A.

Decide if it is worthwhile to initiate a project

B.

Decide on the project approach

C.

Establish solid foundations for a project

D.

Identify the number of Work Packages required

Question 102

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

Options:

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Pay for the project

D.

Specify the benefits of the project

Question 103

Which is an objective of the Closing a Project process?

Options:

A.

Prepare the plan for the next stage

B.

Assess any benefits that have already been realized

C.

Produce a Benefits Review Plan to identify what benefits are expected

D.

Check that all benefits are realized before closing a project

Question 104

Which is the Issue Register NOT used for?

Options:

A.

Capture external events that are impacting a stage

B.

Record information about a deviation in stage tolerance

C.

Capture any threats or opportunities that might have an impact on a stage

D.

Record any problems identified when authorizing a Work Package

Question 105

Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

Options:

A.

define a coding system to provide a unique identifier for the products within

B.

summarize the results of the quality activities performed on

C.

provide a framework to design, develop and maintain

D.

define the project benefits to be achieved by each of

Question 106

What may be funded from a risk budget?

Options:

A.

Corrections required due to off-specifications

B.

Impact analysis of requests for change

C.

Implementation of a fallback plan

D.

Preparation of the risk management approach

Question 107

Which is a purpose of a Project Brief?

Options:

A.

Enable the assembly of the project mandate

B.

Describe the reporting requirements of the various layers of management involved with the project

C.

Describe how changes to products will be controlled

D.

Provide a solid basis for the initiation of the project

Question 108

How does the project board use the 'manage by stages' principle to control the project?

Options:

A.

By approving the project management team

B.

By reviewing project viability at defined intervals

C.

By ensuring that the benefits are managed and controlled

D.

By reviewing previous project closure documentation

Question 109

Which should be provided by corporate or programme management before the Starting up a Project process commences?

Options:

A.

A Project Brief

B.

Sufficient information to identify the prospective Executive

C.

The Project Initiation Documentation

D.

Authority to initiate a project

Question 110

Within which integrated element does PRINCE2 set minimum requirements?

Options:

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Question 111

What is described as an organization's unique attitude towards risk taking

Options:

A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Question 112

Which is a purpose of the Starting up a Project process?

Options:

A.

Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

B.

Define the means of communication between the project and corporate or programme management

C.

Define the project controls

D.

Record any identified risks in the Risk Register

Question 113

Which is a minimum requirement for applying the organization theme?

Options:

A.

To document the project management team structure

B.

To define the experience required for each project role

C.

To include external stakeholders on the project board

D.

To train project team members in the use of PRINCE2

Question 114

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

Options:

A.

Manage by stages

B.

Manage by exception

C.

Continued business justification

D.

Learn from experience

Question 115

The application of which principle helps to define what should be included in a project?

Options:

A.

Defined roles and responsibilities

B.

Focus on products

C.

Manage by stages

D.

Continued business justification

Question 116

Which is a responsibility of a risk owner?

Options:

A.

Identify risks to the project that might occur in their department

B.

Own and authorize the use of the risk budget to fund risk responses

C.

Manage, monitor and control all aspects of an assigned risk

D.

Determine project risk appetite

Question 117

Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

Options:

A.

when a stage plan has been prepared for

B.

at the beginning of

C.

when all the delivery steps have been completed within

D.

at, or close to the end of,

Question 118

What action is taken as part of the 'controlling a stage' process?

1. Create an exception plan

2. Authorize work to be done

3. Take corrective action

4. Obtain approvals for completed products

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question 119

Which describes a characteristic of a project?

Options:

A.

It maintains business as usual profitability

B.

It provides a quality service to customers

C.

It involves a team with different skills

D.

It enables established and proven best practices

Question 120

Which statement about time-driven controls is CORRECT?

Options:

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Question 121

According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

Options:

A.

Project board, project manager and project assurance roles

B.

Directing, managing and delivering levels

C.

Business, user and supplier interests

D.

Corporate, programme management or the customer parties

Question 122

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

Options:

A.

End Stage Report

B.

Team Plan

C.

Work Package

D.

Project Plan

Question 123

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Options:

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Question 124

Where should decisions regarding the tailoring of the project be recorded?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Question 125

Identify the missing words in the following sentence.

The role of [ ? ] is assigned to the project manager if it is not allocated to another person.

Options:

A.

change authority

B.

project assurance

C.

project support

D.

senior user

Question 126

Why is the 'initiating a project' process used?

Options:

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Question 127

Which product identifies how often stakeholders require information?

Options:

A.

Communication management approach

B.

Lessons report

C.

Configuration item record

D.

Benefits management approach

Question 128

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

Options:

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Question 129

What is performed as part of the recommended risk management procedure?

Options:

A.

A budget to investigate issues is allocated

B.

Risk management practices are reviewed to ensure that they are performed effectively

C.

Information about risks to the projects is sent to project stakeholders

D.

Conflicts between the project and the programme board are resolved

Question 130

What is a benefits management approach used to assess?

Options:

A.

How the project's products have performed when in operational use

B.

The effectiveness of the project strategies

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Question 131

When should the level of tailoring be defined?

Options:

A.

During the initiation stage

B.

When reviewing what has been learned to date

C.

As a response to issues and risks experienced

D.

Before the project is triggered by the project mandate

Question 132

Which process monitors work that has been assigned to a team manager?

Options:

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Question 133

Which is an objective of the 'directing a project' process?

Options:

A.

To review and approve a project mandate

B.

To ensure corporate or programme management has an interface to the project

C.

To define how risks, issues and changes will be managed

D.

To obtain approval for completed products

Question 134

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

Options:

A.

Risk category

B.

Risk description

C.

Risk response

D.

Risk status

Question 135

Which is a purpose of a Risk Register?

Options:

A.

Capture risks that may occur during the project

B.

Record how risk management activities will be undertaken on the project

C.

Record the risk tolerance for the project

D.

Capture issues which are impacting on the delivery of the project objectives

Question 136

Which theme verifies that a project's products are fit for purpose?

Options:

A.

Business case

B.

Organization

C.

Quality

D.

Progress

Question 137

Which is a minimum requirement for applying the plans theme?

Options:

A.

The project must have at least two management stages

B.

The team managers in the project must prepare team plans

C.

Scope tolerance must be prioritized using MoSCoW

D.

The project plan must be presented as a Gantt chart

Question 138

Which is a minimum requirement for applying the change theme?

Options:

A.

To establish a change budget to fund changes in scope

B.

To appoint the project manager as part of the change authority

C.

To define the project's approach to baselining products

D.

To record every issue that is raised in the issue register

Page: 1 / 46
Total 461 questions