iSQI CTAL-TAE_V2 ISTQB Certified Tester Advanced Level - Test Automation Engineering CTAL-TAE (Syllabus v2.0) Exam Practice Test
ISTQB Certified Tester Advanced Level - Test Automation Engineering CTAL-TAE (Syllabus v2.0) Questions and Answers
You are employed as a TAE on a project to build a purchasing system. The main requirements for the system are:
1) Allow users to enter details of items that they wish to have purchased and, from these details, create a purchase request.
2) Take each purchase request through a workflow that will allow the requestor’s line manager to approve the request, reject it, or return it for clarification/modification.
3) Forward approved requests to the Purchasing Department.
4) Allow purchasers to find the best available supplier and place the request on that supplier as a purchase order.
Requirement 1 has now been delivered and has been satisfactorily tested manually. In parallel, you have developed a TAS so that functional suitability testing can be automated.
The functional suitability testing of Requirement 1 has now been automated as fully as possible. A change to add audit logging of user activity is planned but has not yet been made. After a small change to the UI code, the last regression run contained a significant number of unexplained test failures. At the point each test stopped, the actual and expected results showed no discrepancies. In each case, the run was able to continue with the next test in the suite. Preliminary investigation showed that the points at which these tests stopped had nothing obvious in common.
Which option below contains the BEST next steps to investigate this?
What would be a goal of test automation in a local development environment?
Which of the following statements about contract testing is TRUE?
You are evaluating the best approach to implement automated tests at the UI level for a web app. Specifically, your goal is to allow test analysts to write automated tests in tabular format, within files that encapsulate logical test steps related to how a user interacts with the web UI, along with the corresponding test data. These steps must be expressed using natural language words that represent the actions performed by the user on the web UI. These files will then be interpreted and executed by a test execution tool. Which of the following approaches to test automation is BEST suited to achieve your goal?
When is automated API testing BEST performed?
(Which of the following statements refers to a typical advantage of test automation?)
You are a TAE responsible for a TAS that is used on several products, all of which have complex UIs. A substantial proportion of the automated tests break on a regular basis, usually for reasons associated with the UI. The investigation and maintenance this requires is significantly reducing the productivity of the teams and the return on investment.
You are looking for ways to improve the test cases in this TAS. Which of the following approaches would be MOST appropriate?
a) Artificial intelligence
b) Test histograms
c) Reliability growth modelling
d) Schema validation
e) Operational profiles
You are employed as a TAE on a project to build a purchasing system. The main requirements for the system are:
1) Allow users to enter details of items that they wish to have purchased and, from these details, create a purchase request.
2) Take each purchase request through a workflow that will allow the requestor's line manager to approve the request, reject it, or return it for clarification/modification.
3) Forward approved requests to the Purchasing Department.
4) Allow purchasers to find the best available supplier and place the request on that supplier as a purchase order.
Requirement 1 has now been delivered and has been satisfactorily tested manually. In parallel, you have developed a TAS so that functional suitability testing can be automated.
You intended to use the implementation of Requirement 1 as a pilot for the TAS. Which TWO of these objectives are MOST appropriate for this pilot?
a) Generate prototypes for the implementation options of the TAS
b) Demonstrate the suitability of at least one TAS implementation option
c) Expose any risks to further deployment of this TAS
d) Assess the quality of the implementation of Requirement 1
e) Enable a calculation of the likely return on investment for this TAS
Which of the following recommendations can help improve the maintainability of test automation code?
A CI/CD pipeline consists of two phases: build and deployment. The build phase, among other activities, runs automated test cases at the following test levels: Component Testing (CT) and Component Integration Testing (CIT). If the build phase is successful, the deployment phase is started. The deployment phase first provisions the test environment infrastructure needed to deploy the SUT, then deploys the SUT to this environment, and finally triggers another separate pipeline that runs automated test cases at the following test levels: System Testing (ST) and Acceptance Testing (AT). Which of the following statements is TRUE?
Which of the following descriptions of what some test automation tools can be used to do is TRUE?
Automated tests at the UI level for a web app adopt an asynchronous waiting mechanism that allows them to synchronize test steps with the app, so that they are executed correctly and at the right time, only when the app is ready and has processed the previous step: this is done when there are no timeouts or pending asynchronous requests. In this way, the tests automatically synchronize with the app's web pages. The same initialization tasks to set test preconditions are implemented as test steps for all tests. Regarding the pre-processing (Setup) features defined at the test suite level, the TAS provides both a Suite Setup (which runs exactly once when the suite starts) and a Test Setup (which runs at the start of each test case in the suite). Which of the following recommendations would you provide for improving the TAS (assuming it is possible to perform all of them)?
When a continuous integration/continuous deployment (CI/CD) pipeline is split between build and deployment phases, which statements are TRUE?
a) Component and component integration tests are part of the deployment phase.
b) System and higher-level tests may be part of the build phase.
c) Component and component integration tests are part of the build phase.
d) System and acceptance tests may be executed in a separate pipeline.
e) System integration tests cannot be run in this kind of pipeline.
You are employed as a TAE on a project to build a purchasing system. The main requirements for the system are:
1) Allow users to enter details of items that they wish to have purchased and, from these details, create a purchase request.
2) Take each purchase request through a workflow that will allow the requestor’s line manager to approve the request, reject it, or return it for clarification/modification.
3) Forward approved requests to the Purchasing Department.
4) Allow purchasers to find the best available supplier and place the request on that supplier as a purchase order.
Requirement 1 has now been delivered and has been satisfactorily tested manually. In parallel, you have developed a TAS so that functional suitability testing can be automated.
You have just conducted a pilot of the TAS on the implementation of Requirement 1 and several things went wrong:
• One test failed because some reference data that it needed was missing. This and several other failures were difficult to diagnose.
• Another test failed unexpectedly because an old version of the script was used.
Which three measures could mitigate these risks during deployment?
a) Full test logging down to and including trace level
b) Identification and correct configuration of all firewalls
c) Automated creation and loading of all data to meet test preconditions
d) Provision of proper device configuration plans
e) Careful packaging with thorough configuration management
As a TA-E, you have successfully verified that a test automation environment and all other components of the TAS are working as expected. Now your goal is to verify the correct behavior for a given automated test suite that will be run by the TAS. Which of the following should NOT be part of the verifications aimed at achieving your goal?
A SUT (SUT1) is a client-server system based on a thin client. The client is primarily a display and input interface, while the server provides almost all the resources and functionality of the system. Another SUT (SUT2) is a client-server system based on a fat client that relies little on the server and provides most of the resources and functionality of the system. A given TAS is used to implement automated tests on both SUT1 and SUT2. The main objective of the TAS is to cover as many system functionalities as possible through automated tests executed as fast as possible. Which of the following statements about the automation solution is BEST in this scenario?
(In User Acceptance Testing (UAT) for a new SUT, in addition to the manual tests performed by the end-users, automated tests are performed that focus on the execution of repetitive and routine test scenarios. In which of the following environments are all these tests typically performed?)
You are currently conducting a Proof of Concept (PoC) aimed at selecting a tool that will be used for the development of a TAS. This TAS will exclusively be used by one team within your organization to implement automated UI-level test scripts for two web apps. The two tools selected for the PoC use JavaScript/TypeScript to implement the automated test scripts and offer capture and playback capabilities. Three test cases for each of the two web apps were selected to be automated during the PoC. The PoC will compare these two tools in terms of their effectiveness in recognizing and interacting with UI widgets exercised by the test cases, to quickly determine whether test automation is possible and which tool is better. Which of the following TAFs is BEST suited for conducting the PoC?
Which of the following practices can be used to specify the active (i.e., actually available) features for each release of the SUT and determine the corresponding automated tests that must be executed for a given release?
As a TAE, you are evaluating a test automation tool to automate some UI tests for a web app. The automated tests will first locate the required HTML elements on the web page using their corresponding identifiers (locators), then perform actions on those elements, and finally check the presence of any expected text for an HTML element. These tests are independent of each other and are organized into a test suite that must be run every night against the most recent build of the web app. There is a high risk that the web app will crash while running some automated tests. Based only on the given information, which of the following is your MOST important concern related to the evaluation of the test automation tool?
When looking for the cause of an intermittent failure, which action is MOST likely to help?
Which statement correctly describes what a Test Automation Architecture should do?
What is considered to be an ADVANTAGE of test automation?
Which part of the SUT can be changed to better support test automation?