Summer Sale- Special Discount Limited Time 65% Offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

VMware 3V0-21.23 VMware vSphere 8.x Advanced Design Exam Practice Test

Page: 1 / 9
Total 92 questions

VMware vSphere 8.x Advanced Design Questions and Answers

Question 1

An architect is designing a new hosting platform for a healthcare provider with proposed locations in three regional areas.

The following set of requirements have been provided by key stakeholders:

REQ001 - The hosting platform must support long distance vMotion between the primary and secondary site.

REQ002 - The maximum RTT (round-trip time) latency between the primary site and the secondary site must be less than 150 milliseconds.

REQ003 - The hosting platform must be manageable from assets located in the third site.

REQ004 - Each location must scale to support a minimum of 35TB storage.

Which requirement would be classified as a technical (formerly non-functional) requirement for the new hosting platform?

Options:

A.

Each location must scale to support a minimum of 35TB storaqe.

B.

The maximum RTT (round-trip time) latency between the primary and secondary site must be less than 150 milliseconds.

C.

The hosting platform must be manageable from assets located in the third site.

D.

The hosting platform must support long distance vMotion between the primary and secondary site.

Question 2

A company has a requirement that all production applications must have a maximum tolerable downtime (MTD) of one hour per month.

Which statement would be included in the physical design to support this requirement?

Options:

A.

vSphere HA will be enabled on all clusters.

B.

vSphere HA Host Failure Response will be set to Restart VMs.

C.

vSphere Fault Tolerance (FT) will not be enabled for the production applications.

D.

Server hardware has already been purchased for the production applications.

Question 3

What is an example of a performance design quality?

Options:

A.

The solution must scale to meet spikes in CPU demand.

B.

The solution must provide 40 physical CPU cores and 20 TB of physical memory.

C.

The solution must support applications with a maximum tolerable downtime (MTD) of four hours.

D.

The solution must support applications with 1,000 transactions per second (TPS).

Question 4

An architect is responsible for designing a vSphere-based solution for a customer. The customer has the following requirements:

The solution must provide redundancy and load balancing for storage traffic

The solution must tolerate at least one failure

There must be no single point of failure in the solution

Which three considerations regarding physical host design should the architect analyze when making storage related design decisions? (Choose three.)

Options:

A.

Configure the fixed multi-pathing policy on the ESXi hosts

B.

Use four single port storage host bus adapters (HBAs) in each ESXi host

C.

Use an active-active array for Fibre Channel storage-based VMFS datastores

D.

Configure a minimum of two paths to every LUN or datastore

E.

Configure a minimum of four paths to every LUN or datastore

F.

Use one quad-port storage host bus adapter (HBA) in each ESXi host

Question 5

An architect is designing a vSphere-based application hosting solution in a brownfield site.

The following information has been provided during the requirements gathering workshop:

The solution should support 5,000 compute workloads across two physical sites.

The CFO has approved budget for the purchase of new server and network hardware only.

The existing storage array is currently Fibre Channel connected with 2 x 8 Gbps interfaces to a dedicated Storage Area Network (SAN) fabric.

The existing storage array does not support integration with vSphere API for Storage Awareness.

The existing storage array can be configured to support NFS storage.

The existing vSphere administration team will responsible for operational management of the new solution.

Which storage technology should the architect recommend based on these requirements?

Options:

A.

vSphere Virtual Volumes (vVols)

B.

iSCSI

C.

Fibre Channel

D.

VMware vSAN

Question 6

An architect is reviewing the security and compliance requirements for a new application that will be hosted on a vSphere 8 environment.

The following information has been noted about the new application:

The application stores and processes confidential data

The supporting virtual infrastructure is shared with other departments

No other application stores or processes confidential data

The application virtual machines must be able to run on any ESXi host in the cluster

The storage layer is a iSCSI attached SAN

Data at Rest Encryption is in place for each presented LUN validated to FIPS 140-2

No budget is available for additional infrastructure components or software

Application data must not be accessible outside of the application's virtual machines

The architect has been tasked with providing a secure virtual machine design to host the application.

Which three design elements must the architect include to meet the requirements? (Choose three.)

Options:

A.

Virtual Machine Encryption

B.

The vSphere Native Key Provider

C.

A new encrypted iSCSI LUN

D.

External Key Management Service (KMS) provider

E.

A new local VMFS volume

F.

VMware vSAN

Question 7

An architect is designing a vSphere-based private cloud solution to support the following customer requirements:

The solution should support running 5,000 concurrent production compute workloads across the primary and secondary sites.

The solution should support running 1,000 development compute workloads within the secondary site.

The solution should support up to 50 management workloads across the primary and secondary site.

The solution must ensure the isolation of virtual infrastructure management operations between management and compute workloads.

The solution must ensure that the hosting of any virtual infrastructure management workloads does not impact the amount of capacity available for compute workloads.

The solution must ensure that all production compute workloads are physically isolated from development compute workloads.

The solution must ensure that the operational management of compute workloads in the secondary site is possible in the event of a disaster affecting the primary site.

How many VMware vCenter instances will the architect need to include in the design to meet these requirements?

Options:

A.

5

B.

3

C.

2

D.

4

Question 8

An architect is tasked with designing a repeatable edge hosting solution using VMware technologies that can be deployed to existing hotels across the world and operate independently of other locations.

During interviews with stakeholders, the architect notes the following information:

There are 123 hotels in total.

All hotels have a minimum of two 1 Gbps connections for guest Internet access.

The company operates hotels in four countries: Canada, USA, Cuba and Mexico.

The company is rebranding the hotels located in Mexico.

Which of these is a business factor that will impact this design?

Options:

A.

The company is rebranding the hotels located in Mexico.

B.

The company operates hotels in four countries: Canada, USA, Cuba and Mexico.

C.

There are 123 hotels in total

D.

All hotels have a minimum of two 1 Gbps connections for guest Internet access.

Question 9

An architect is documenting the design for a new multi-site vSphere solution. The customer has informed the architect that the workloads hosted on the solution are managed by application teams who must perform a number of steps to return the application to service following a failover of the workloads to the secondary site. These steps are defined as the Work Recovery Time (WRT). The customer has provided the architect with the following information about the workloads, including the recovery time objective (RTO) and recovery point objective (RPO):

Critical workloads have a WRT of 12 hours

Production workloads have a WRT of 24 hours

Development workloads have a WRT of 24 hours

All workloads have an RPO of 4 hours

Critical workloads have an RTO of 1 hour

Production workloads have an RTO of 12 hours

Development workloads have an RTO of 24 hours

The customer has also confirmed that production and development workloads are managed by the same team and the disaster recovery solution will not begin the recovery of the development workloads until all critical and production workloads have been recovered at the secondary site.

Which three statements would the architect document as the maximum tolerable downtime (MTD) for workloads within the design? (Choose three.)

Options:

A.

Critical Workloads: 12 hours

B.

Development Workloads: 24 hours

C.

Production Workloads: 36 hours

D.

Critical Workloads: 13 hours

E.

Development Workloads: 60 hours

F.

Production Workloads: 24 hours

Question 10

A company will be replacing the external storage array that is currently providing storage to the vSphere environment. The architect must design a storage architecture for existing and future workloads. Company policy required storage separation of workloads by departments.

Which design decision should the architect make to satisfy the requirement and scale for additional departments?

Options:

A.

Use storage volumes based on applications.

B.

Use one storage volume per department and create new volumes for new departments.

C.

Use one storage volume per existing department and extend current volumes for new departments.

D.

Use N + 1 storage volumes for current and future workloads.

Question 11

An architect is designing the datastore configuration of a new vSphere-based solution.

The following information was obtained during the initial meeting with the customer:

There is currently 500 production and DMZ virtual machine workloads spread evenly across the primary and secondary site.

The profile of the workloads (per site) is as follows:

- DMZ:

-- 75 x Small: 1 vCPU, 2GB RAM, 200 GB disk

- Production:

-- 50 x Small: 1 vCPU, 2 GB RAM, 200 GB disk

-- 100 x Medium: 2 vCPU, 4 GB RAM, 200 GB disk

-- 25 x Large: 4 vCPU, 8 GB RAM, 500 GB disk

The average IO Profile per workload is 70/30 read/write.

The solution should cater to 10% storage growth in the first year.

The solution should cater to 15% virtual machine snapshot overhead.

The storage team has confirmed:

- A scalable external storage array has been deployed per site to support the storage requirements.

- The storage array will connect to all hosts using a dedicated Fibre Channel storage area network fabric.

- Usable storage capacity is available in 10 TB LUNs.

- As many LUNs as required can be provided.

- Every effort should be made to ensure the number of required LUNs is minimized.

The security team has stated that all DMZ and production workloads must remain logically isolated from each other.

Given the information provided, which three design decisions should the architect make to meet the requirements? (Choose three.)

Options:

A.

Six 10TB VMFS datastores will be configured on each site for all production workloads.

B.

Four 10TB VMFS datastores will be configured on each site for all production workloads.

C.

Each 10TB LUN will be configured as a VMFS datastore.

D.

Two 10TB VMFS datastores will be configured on each site for all DMZ workloads.

E.

Each 10TB LUN will be configured as an NFS datastore.

F.

Seven 10TB VMFS datastores will be configured on each site for all workloads.

Question 12

A company is expanding and will be deploying new vSphere environments in multiple new locations. All environments use datastores backed by multiple storage technologies and vendors.

How can the architect create a design to efficiently and repeatedly distribute existing company virtual machine (VM) templates to multiple new locations?

Options:

A.

Use storage array replication tools to replicate the storage volume holding the company VM templates to each remote site.

B.

Upload company templates to a cloud provider and download to each new location.

C.

Create a published content library and have the new locations subscribe to it.

D.

Create a local content library at each site and manually copy only needed templates.

Question 13

An architect is tasked with helping a customer develop a design that meets the following requirements:

Must have no single point of failure

Must include thorough standard operating procedure documentation

Must use VMXNET3 virtual network interface card

Must have 99.9% uptime Service Level Agreement

Must use the latest version of VMware vSphere

Which two are considered constraints? (Choose two.)

Options:

A.

Must use the latest version of VMware

B.

Must have no single point of failure

C.

Must use VMXNET3 virtual network interface card

D.

Must include thorough standard operating procedure documentation

E.

Must have 99.9% uptime Service Level Aqreement

Question 14

As part of designing a greenfield vSphere-based hosting solution, an architect is responsible for defining a patch management solution for the virtual infrastructure.

During initial meetings with the customer, the following information is provided:

There are two geographically dispersed physical sites (primary and secondary) in scope for the solution.

The inter-site connectivity has been classified as low bandwidth and high latency.

The customer has the following requirements:

REQ001 - Only IT Security Team-approved versions of VMware Tools should be installed across all workloads within the infrastructure.

REQ002 - The solution should minimize traffic across the inter-site link.

REQ003 - Upgrades to the virtual infrastructure should continue in the event of a failure with either site.

A combination of which three design decisions could the architect make to ensure the requirements are met? (Choose three.)

Options:

A.

The solution will set the UserVars.ToolsRamdisk advanced system setting on each VMware ESXi host to "1" (enabled).

B.

The solution will ensure that all VMware ESXi hosts within a site have access to the local VMFS datastore containing the shared VMware Tools repository.

C.

The solution will use VMware Autodeploy to ensure the latest version of VMware Tools is deployed to each workload.

D.

The solution will set the UserVars.ProductLockerLocation advanced system setting on each VMware ESXi host to point to the local site shared Repository

E.

The solution will create a shared repository on a VMFS datastore within each site that contains all approved versions of VMware Tools.

F.

The solution will create a shared repository on a VMFS datastore within the primary site that contains all approved versions of VMwareTools.

Question 15

An architect is responsible for the lifecycle management design for a brownfield vSphere-based solution.

The following information has been provided during initial meetings around the new solution:

Existing heterogeneous server hardware will be used to provide the hosting platform.

The available hardware is:

-- 10 servers that contain 2 x 20-Core Intel Xeon processors and 512 GB RAM from Vendor A

-- 10 servers that contain 2 x 24-Core Intel Xeon processors and 768 GB RAM from Vendor A

-- 20 servers that contain 2 x 16-Core AMD EPYC processors and 512 GB RAM from Vendor B

-- 10 servers that contain 1 x 24-Core AMD EPYC processors and 256 GB RAM from Vendor C

All of the hardware is currently listed on the VMware Hardware Compatibility List (HCL).

All existing server hardware has 36 months vendor support remaining.

The requirements from the customer are:

REQ001 - The solution must support the hosting of 5,000 workloads across two physical sites.

REQ002 - The solution should minimize the number of clusters.

REQ003 - The solution must ensure that there is no impact to service when completing upgrades.

Given the resource requirements needed for the solution, the architect has calculated that all of the existing servers will be required to provide sufficient resources for the new environment. The Intel-based servers will be deployed to the primary site and the AMD-based servers will be

deployed to the secondary site.

Which four additional design decisions should the architect make to ensure all requirements can be met? (Choose four.)

Options:

A.

The solution will create an Intel-based 20-node vSphere cluster in the primary site and an AMD-based 30-node vSphere cluster in the secondary site.

B.

The solution will use VMware SDDC Manager to perform lifecycle management of the solution.

C.

The solution will ensure each vSphere cluster supports a minimum of N + 1 redundancy.

D.

The solution will use vSphere Lifecycle Manager images to update and upgrade vSphere ESXi hosts in the secondary site.

E.

The solution will use vSphere Lifecycle Manager baselines to perform patching and upgrading of vSphere ESXi hosts in the secondary site.

F.

The solution will use vSphere Lifecycle Manager images to update and upgrade vSphere ESXi hosts in the primary site.

G.

The solution will ensure each vSphere cluster is configured with Distributed Power Management (DPM).

Question 16

An architect is updating an existing design to include a new vSphere cluster to meet the following customer requirements:

The solution must provide automatic load redistribution of workloads across all resources in the cluster

The solution must consider the usage patterns of workloads when performing load redistribution

The solution must provide capacity to reserve resources equal to two ESXi hosts for failover in the event of a host failure

The architect has also collected the following assumptions and constraints during the design workshops:

A001 - Budget is available for additional hardware and software if required to meet the solution requirements

A002 - Capacity is available to allow the deployment of additional tooling to manage the solution

C001 - All management workloads must be deployed to the existing vSphere management cluster

Which three design decisions should the architect include to meet the documented requirements? (Choose three.)

Options:

A.

The solution will enable the Predictive DRS option to avoid host over-commitment.

B.

The solution will enable the Memory Metric for Load Balancing option to avoid host over-commitment.

C.

The solution will deploy VMware Aria Operations to monitor the vSphere environment.

D.

The solution will enable the VM Distribution option to avoid host over-commitment.

E.

The solution will deploy a Distributed Resource Scheduler (DRS) enabled cluster with sufficient capacity to meet the workload demands.

F.

The solution will deploy a vSphere Distributed Power Management (DPM) enabled cluster with sufficient capacity to meet the workload demands.

Question 17

What is a benefit of using workload domains in VMware Cloud Foundation?

Options:

A.

Workload domains require separate instances of vCenter, decreasinq complexity and manaqement overhead.

B.

Workload domains allow for manual provisioninq of vSphere clusters usinq the SDDC Manaqer.

C.

Workload domains are pre-configured and automatically deployed according to industry best practices for SDDC implementation.

D.

Each workload domain can only support a maximum of three ESXi hosts, makinq it easy to manaqe small workloads.

Question 18

A company is expanding an existing vSphere deployment to meet new demands from the business. The following requirements have been identified for the expanded infrastructure:

REQ001- It must support enhanced vMotion compatibility (EVC) mode for Intel "Nehalem" Generation (Intel Xeon Core i7) processors.

REQ002- It must be accessible via an API.

REQ003- It must support a variety of operating systems.

REQ004- It must notify administrators whenever a virtual machine is connected to more than one network.

Which requirement would be classified as a technical (formerly non-functional) requirement?

Options:

A.

It must be accessible via an API.

B.

It must notify administrators whenever a virtual machine is connected to more than one network.

C.

It must support enhanced vMotion compatibility (EVC) mode for Intel "Nehalem" Generation (Intel Xeon Core i7) processors.

D.

It must support a variety of operating systems.

Question 19

An architect is documenting the design decisions for a new vSphere solution. The following design decision has been made:

Create a separate vSphere cluster for the management workloads

What could the architect include as justification for this design decision?

Options:

A.

This increases operational overhead as multiple clusters are required for management and compute workloads.

B.

This increases capital expenditure as hardware must be purchased for multiple clusters.

C.

This ensures that compute workloads have no impact on the management workloads.

D.

This ensures that compute workloads have no impact on the management workloads.

Question 20

Which is a benefit of using vSAN stretched clusters in VMware Cloud Foundation?

Options:

A.

To enable high availability of virtual machines across different availability zones

B.

To reduce the cost by eliminating the need for additional hardware and software components

C.

To simplify physical network configurations by automatically configuring the required network components

D.

To improve application performance by reducing network latency between availability zones

Question 21

An architect is working on a new VMware vSphere design and notes the following information during interviews with stakeholders:

The company has previously worked with multiple VMware partners

The company has an internal security policy that is referenced in long running contracts

The company has an Enterprise License Agreement (ELA) with VMware

The company has a multi-year cloud subscription agreement

Which of these is a business factor that will impact this design?

Options:

A.

The company has previously worked with multiple VMware partners.

B.

The company has an Enterprise License Agreement (ELA) with VMware.

C.

The company has an internal security policy that is referenced in long running contracts.

D.

The company has a multi-year cloud subscription agreement.

Question 22

What is an example of an availability design quality?

Options:

A.

A vSphere cluster is configured to support an N + 1 level of redundancy.

B.

A vSphere cluster is configured to support a maximum tolerated downtime of one hour.

C.

A vSphere cluster is configured to stage patches on ESXi hosts before applying them.

D.

A vSphere cluster is configured to use a dedicated network adapter for vMotion traffic.

Question 23

An architect is creating the design for a vSphere platform that will be used as the target for a migration from multiple legacy vSphere platforms that are being decommissioned. The customer has provided the following information:

Each legacy platform has its own set of virtual machine templates stored in OVF format.

All of the templates need to be migrated to the new platform.

After migration, the templates should be centralized into a single location.

The templates must be accessible to all clusters in the new platform vCenter instance.

Any new templates added to the central location must be automatically available to all clusters.

Administrators must be able to deploy new virtual machines directly from the template instances.

The customer also confirmed that after the migrations are complete, the new platform will be the only vSphere solution available.

Which design choice should the architect evaluate in the logical design for the storage and management of virtual machine templates?

Options:

A.

Use a dedicated datastore on each vSphere cluster

B.

Use a shared datastore on each vSphere cluster

C.

Use a subscribed content library

D.

Use a local content library

Question 24

An architect is designing a new vSphere solution. The solution will be used to host workloads that have multiple dependencies. The customer provides the following information regarding the workloads:

Workload 1: Self-Service Portal

Workload 2: Database

Workload 3: Identity Broker

Workload 4: Reporting Tool

Workload 5: Management Tool

Application A is formed of workloads 1 and 2 and has a dependency on workload 3

Application B is formed of workloads 2 and 4 and has a dependency on workload 3

Application C is formed of workload 5 and has a dependency on workload 4

How should the architect document the vSphere HA requirements to ensure that all of the applications can be recovered in the event of a host failure while observing the dependencies?

Options:

A.

Set vSphere HA to Restart VMs in response to a Host FailureSet the Restart Priority of workload 3 to HighSet the Restart Priority of workload 4 to MediumSet the Restart Priority of workloads 1, 2 and 5 to Low

B.

Set vSphere HA to Shut Down and Restart VMs in response to a Host IsolationSet the Restart Priority of workloads 3 and 4 to HighSet the Restart Priority of workload 5 to MediumSet the Restart Priority of workloads 1 and 2 to Low

C.

Set vSphere HA to Restart VMs in response to a Host FailureSet the Restart Priority of workloads 3 and 4 to HighSet the Restart Priority of workload 5 to MediumSet the Restart Priority of workloads 1 and 2 to Low

D.

Set vSphere HA to Shut Down and Restart VMs in response to a Host IsolationSet the Restart Priority of workload 3 to HighSet the Restart Priority of workloads 4 and 5 to MediumSet the Restart Priority of workloads 1 and 2 to Low

Question 25

An architect is tasked with updating the design of an existing vSphere-based solution for a pharmaceuticals customer. The update will include upgrade to VMware vCenter 8 and VMware vSphere 8 and the creation of a new cluster that will be used for ongoing research projects. The research project that is driving the need for an update includes a number of applications that are latency-sensitive.

The customer has confirmed the following information during the initial workshop:

The customer recently completed a right sizing exercise using VMware Aria Operations that resulted in a number of ESXi hosts becoming available for use.

Each of the VMware ESXi host servers is configured with:

-- 2 x 20-core Intel Xeon CPU sockets

-- 1024 GB RAM divided evenly between sockets

There is no additional budget for purchasing hardware.

After confirming the existing hardware is still listed on the VMware Hardware Compatibility List (HCL), the architect makes the following design decisions with regard to the workload design:

The solution will support a maximum of 20 combined cores and sockets per virtual machine.

The solution will support a maximum of 512 GB RAM per virtual machine.

What should the architect document as justification for these design decisions?

Options:

A.

The maximum supported configuration will ensure efficient use of RAM by sharing memory pages between virtual machines.

B.

The maximum supported configuration will ensure the virtual machines will adhere to a single Non-Uniform Memory Access (NUMA) node boundary.

C.

The maximum supported configuration will ensure each virtual machine will exclusively consume a whole CPU socket.

D.

The maximum supported configuration will allow the creation of virtual machines that cross NUMA node boundaries resulting in improved overall performance.

Question 26

An architect is responsible for the lifecycle management design for a brownfield vSphere-based solution.

The following information has been provided during initial meetings around the new solution:

Existing heterogeneous server hardware will be used to provide the hosting platform.

The available hardware is:

- 10 servers that contain 2 x 20-Core Intel Xeon processors and 512 GB RAM from Vendor A

- 10 servers that contain 2 x 24-Core Intel Xeon processors and 768 GB RAM from Vendor A

- 20 servers that contain 2 x 16-Core AMD EPYC processors and 512 GB RAM from Vendor B

- 10 servers that contain 1 x 24-Core AMD EPYC processors and 256 GB RAM from Vendor B

All of the hardware is currently listed on the VMware Hardware Compatibility List (HCL).

All existing server hardware has 36 months vendor support remaining.

The requirements from the customer are:

REQ001 - The solution must support the hosting of 5,000 workloads spread across two physical sites.

REQ002 - The solution should minimize the number of clusters.

REQ003 - The solution must ensure that there is no impact to service when completing upgrades.

Given the resource requirements needed for the solution, the architect has calculated that all of the existing servers will be required to provide sufficient resources for the new environment. The Intel-based (Vendor A) servers will be deployed to the primary site and both the Intel-based and AMD-based servers (Vendor B) will be deployed to the secondary site.

Which assumption should the architect make to support the lifecycle management of vSphere 8?

Options:

A.

The different processor architectures across both sites will remediate against a shared vSphere Lifecycle Manager baseline.

B.

The different processor architectures will be located in the same cluster to support vSphere Lifecycle Manager image-based remediation.

C.

The different processor architecture within a single site will remediate against a single vSphere Lifecycle Manager image.

D.

The different processor architectures across both sites will remediate against a single vSphere Lifecycle Manager image.

Question 27

An architect is conducting interviews to gather requirements for a new vSphere-based private cloud solution.

The following information has been provided by the customer:

The customer, after 10 years within an outsourced managed service contract, has decided to bring application hosting back in-house but lacks the VMware skills to support this.

The customer currently has 5,000 workloads under contract and managed by their partner.

The customer would like to keep IT infrastructure costs at a minimum.

The customer would like to ensure that the solution supports the company's green IT agenda by reducing their carbon footprint.

Which statement is classified as a business factor that would impact the design?

Options:

A.

The customer would like to keep IT infrastructure costs at a minimum.

B.

The customer, after 10 years within an outsourced managed service contract, has decided to bring application hosting back in-house but lacks the VMware skills to support this.

C.

The customer would like to ensure that the solution supports the company's green IT agenda by reducing their carbon footprint.

D.

The customer currently has 5,000 workloads under contract and managed by their partner.

Page: 1 / 9
Total 92 questions