Weekend Sale Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

Scrum PSM-I Professional Scrum Master level I Exam Practice Test

Page: 1 / 25
Total 250 questions

Professional Scrum Master level I Questions and Answers

Question 1

Who is responsible for collaboration with stakeholders?

(choose the best answer)

Options:

A.

The Business Analyst.

B.

The Scrum Team.

C.

The Team Manager.

D.

The Project Manager.

E.

The Developers.

Question 2

The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.

Options:

A.

False.

B.

True, accordingly to what was committed to the stakeholders.

C.

True, but only after confirmation by the resource manager that the Team has enough capacity.

D.

True.

E.

False, the Scrum Master does that.

F.

False, capacity and commitment are the Project manager’s responsibility.

Question 3

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

Options:

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

Yes, otherwise the Product Owners (and stakeholders) may not be able to accurately inspect what is done.

C.

No, each Scrum Team stands alone.

D.

No, that is far too hard and must be done in a hardening Sprint.

Question 4

Currently, your Development Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams? (Choose three.)

Options:

A.

You cannot do Scrum without feature teams.

B.

Productivity may suffer when making this kind of move.

C.

Getting support from the business side first helps.

D.

Feature teams have less communication overhead.

E.

With feature teams, it is easier to calculate the productivity per team.

Question 5

A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help. What would be good advice to give the Product Owner?

Options:

A.

Remind the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog.

B.

Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.

C.

Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.

Question 6

A new developer is having continuing conflicts with existing Development Team members and creating the hostile environment. If necessary, who is responsible for removing the team member?

Options:

A.

The hiring manager is responsible, because he/she hired the developer.

B.

The Scrum Manager is responsible, because he/she removes Impediments.

C.

The Development Team is responsible, and may need help from the Scrum Master.

D.

The Product Owner is responsible, because he/she controls the return on investment (ROI).

Question 7

As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

Options:

A.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

B.

Find another Scrum Team to give the excess work to.

C.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

D.

Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

Question 8

Which statement best describes a Product Owner’s responsibility?

Options:

A.

Optimizing the value of the work the Development Team does.

B.

Managing the project and ensuring that the work meets the commitments to the stakeholders.

C.

Directing the Development Team.

D.

Keep stakeholders from distracting the Development Team.

Question 9

Why should the Product Owner be present at the Daily Scrum?

Options:

A.

He/She doesn’t need to be there.

B.

To hear about impediments in functionality.

C.

To represent the stakeholders’ point of view.

D.

To participate as a Scrum Team member.

Question 10

When does the second Sprint start?

Options:

A.

Once the architectural changes for the second Sprint have been approved by the senior architect.

B.

After the Product Backlog for the second Sprint has been selected.

C.

Immediately after the first Sprint.

D.

After the customer completes acceptance testing of the first Sprint.

Question 11

What is the role of management in Scrum?

Options:

A.

To facilitate the Scrum Teams with insights and resources that help them improve.

B.

To monitor the Development Team’s productivity.

C.

To identify and remove people that aren’t working hard enough.

D.

To continually monitor staffing levels of the Development Team.

Question 12

What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose two.)

Options:

A.

Involve the complete Development Team.

B.

Use coaching techniques; such as open questions and active listening.

C.

Ask an external technical specialist to make the decision.

D.

Send every team member to the company’s HR department to express their concerns.

Question 13

Who is responsible for engaging the stakeholders?

Options:

A.

The Business Analyst.

B.

The Development Team.

C.

The Team Manager.

D.

The Project Manager.

E.

The Product Owner.

Question 14

The time-box for a Daily Scrum?

Options:

A.

Two minutes per person.

B.

15 minutes.

C.

15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.

D.

4 hours.

E.

The same time of day every day.

Question 15

Which two ways of creating Scrum Teams are consistent with Scrum's values?

(choose the best two answers)

Options:

A.

Bring all the people together and let them organize into Scrum Teams

B.

Managers personally re-assign current subordinates to new teams.

C.

Existing teams propose how they would like to go about organizing into the new

structure.

D.

Managers collaborate to assign individuals to specific teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Question 16

For which is the Scrum Master responsible?

Options:

A.

Managing the performance of the Scrum Team.

B.

The meetings and the objectives that a Scrum Team sets for itself.

C.

The Scrum framework being adopted and used properly.

D.

Keeping track of resource allocation.

Question 17

When might a Sprint be abnormally cancelled?

Options:

A.

When the Development Team feels that the work is too hard.

B.

When the Sprint Goal becomes obsolete.

C.

When the sales department has an important new opportunity.

D.

When it becomes clear that not everything will be finished by the end of the Sprint.

Question 18

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

Options:

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Development Team's plan for the Sprint.

E.

It is ordered by the Product Owner.

Question 19

Which three behaviors demonstrate that a team is self-organizing? (Choose three.)

Options:

A.

Stakeholders walking in at the Daily Scrum to check progress and work with the Scrum Master to optimize the functional scope for the Sprint.

B.

The Development Team members are working within the boundaries of their functional description and nicely handing off work from analyst to developer to tester to integration.

C.

The Product Owner doesn’t need to be at Sprint Retrospectives.

D.

The Development Team creating their own sprint backlog, reflecting all work that is part of the definition of “Done”.

E.

The Development Team has all the skills needed to create a releasable Increment.

F.

Development Team members collaboratively selecting their own work during the Sprint.

G.

The Development Team inviting external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.

Question 20

Which two of the following are true about the Scrum Master role? (Choose two.)

Options:

A.

At the Sprint Review, the Scrum Master identifies what has been “done” and what has not been “done”.

B.

The Scrum Master teaches the Development Team to keep the Scrum meetings to their time-box.

C.

The Scrum Master helps those outside the team interact with the Scrum Team.

D.

The Scrum Master assigns tasks to Development Team members when they need work.

E.

The Scrum Master is responsible for updating the Sprint Burndown.

Question 21

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Question 22

Who creates a Product Backlog Item’s estimate?

Options:

A.

The Development Team after clarifying requirements with the Product Owner.

B.

The Product Owner with input from the Development Team.

C.

The most senior people in the organization, including architects and subject matter experts.

D.

The Scrum Master.

E.

The Development Team, alone.

Question 23

When should a Sprint Goal be created?

Options:

A.

It should have been created in the previous Sprint during Product Backlog refinement.

B.

It must be established before Sprint Planning in order to begin planning.

C.

A Sprint Goal is not mandatory in Scrum.

D.

At any time during the Sprint.

E.

During Sprint Planning.

Question 24

When must the Product Owner participate in the Dairy Scrum? (choose the best answer)

Options:

A.

When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer

B.

When the Product Owner needs to represent the stakeholders point of view to the Developers

C.

When there are impediments to discuss

D.

When the Scrum Master asks the Product Owner to attend

Question 25

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario. (Choose two.)

Options:

A.

There should be six Product Owners, one for each Scrum Team.

B.

There should be six Product Owners, reporting to a chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Question 26

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog tor a Sprint to satisfy the stakeholders.

Options:

A.

True

B.

False

Question 27

When many Scrum Teams are working on a single product, what best describes the Definition of Done?

(Choose the best answer.)

Options:

A.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a

hardening Sprint.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

D.

All Scrum Teams must have a Definition of Done that makes their combined work potentially releasable.

Question 28

Who is accountable for managing the progress ot work during a Sprint?

(choose the best answer)

Options:

A.

The Product Owner.

B.

The Developers.

C.

The Scrum Master.

D.

The most junior member ot the team.

Question 29

What factor should be considered when establishing the Sprint length?

(choose the best answer)

Options:

A.

The organization has mandated similar length sprints.

B.

The need for the team to learn based on doing work and measuring results.

C.

The frequency at which team formation can be changed.

D.

The organization's release schedule.

Question 30

What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)

Options:

A.

There is no such thing as Sprint 0.

B.

Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.

C.

Make the complete project plan to commit date, budget, and scope to the stakeholders.

D.

Determine the composition of the Development Teams so they have the capacity to deliver the completed

forecast.

E.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

Question 31

When must a scrum Team release each increment? (choose the best answer)

Options:

A.

when the Scrum Team finishes their work

B.

Alter every Sprint. without exception

C.

Whenever the product s tree of detects

D.

When it makes sense to release It.

Question 32

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

Options:

A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Question 33

Which topics should be discussed in the Sprint Review?

Options:

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

Sprint results.

D.

All of the above.

Question 34

A Scrum Team is a cohesive unit of professionals that consists of which of the following? (Choose all that

apply.)

Options:

A.

Users.

B.

One Scrum Master.

C.

Developers.

D.

Customers.

E.

One Product Owner.

Question 35

How do you know that a Scrum Team is cross-functional? (Choose the best answer.)

Options:

A.

Scrum Team has all the skills to create an increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Scrum Team.

D.

Every member of the Scrum Team is able to perform every task.

Question 36

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?

Options:

A.

There are no such activities. The next Sprint starts immediately after the current Sprint.

B.

Refine the Product Backlog.

C.

Work with the Quality Assurance departments on the Increment of the current Sprint.

D.

Update the project plan with stakeholders.

Question 37

Which answer best describes the topics covered in Sprint Planning? (Choose the best answer.)

Options:

A.

What to do and who will do it.

B.

How conditions have changed and how the Product Backlog should evolve.

C.

What can be done and how to do it, and why to do it.

D.

What went wrong in the last Sprint and what to do differently this Sprint.

E.

Who is on the team and what team member roles will be.

Question 38

When is implementation of a Product Backlog item considered complete?

Options:

A.

At the end of the Sprint.

B.

When the item has no work remaining in order to be potentially released.

C.

When QA reports that the item passes all acceptance criteria.

D.

When all work in the Sprint Backlog related to the item is finished.

Question 39

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

Options:

A.

True

B.

False

Question 40

Why is the Daily Scrum held at the same time and same place?

Options:

A.

The consistency reduces complexity.

B.

The place can be named.

C.

The Product Owner demands it.

D.

Rooms are hard to book and this lets it be booked in advance.

Question 41

The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.

Options:

A.

True

B.

False

Question 42

What is the function or purpose of management in Scrum?

(choose the best answer)

Options:

A.

To identify and remove people that are not working hard enough.

B.

To monitor the productivity of the Developers.

C.

To present the Scrum Teams with insights and resources that help them improve.

D.

To continually monitor staffing levels of the Scrum Team.

Question 43

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

Options:

A.

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Question 44

What are two ways that regulatory compliance issues are dealt with in Scrum?

(choose the best two answers)

Options:

A.

They are addressed by a separate team who is responsible for compliance

issues.

B.

They are addressed along with functional development of the product.

C.

They are discussed, determined, and documented before the actual feature

development Sprints.

D.

They are added to the Product Backlog and addressed in early Sprints, while

always requiring at least some business functionality, no matter how small.

Question 45

What happens if the Development Team cannot complete its work by the end of the Sprint?

Options:

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Question 46

What is the recommended size for a Development Team?

Options:

A.

7 plus or minus 3.

B.

At least 7.

C.

9.

D.

3 to 9.

Question 47

When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint'

(choose the best answer)

Options:

A.

Never The entire Scrum Team is accountable for creating value every Sprint.

B.

At the Sprint Planning Evented

C.

Whenever a team member can accommodate more worn.

D.

During the Daily scrum

Question 48

What is the recommended size for a Scrum Team? (Choose the best answer.)

Options:

A.

At least 7.

B.

9

C.

10 or fewer.

D.

7 plus or minus 3.

Question 49

What is the best suited structure for Development Teams in order to produce integrated Increments?

Options:

A.

Each Development Team works only one technical layer of the system (e.g. GUI, database, middle tier, interfaces).

B.

Each Development Team develops functionality from beginning to end throughout all technical layers.

Question 50

Which three of the following are true about Scrum? (Choose the best three answers.)

Options:

A.

Scrum implements self-management by replacing Project Managers with Scrum Masters.

B.

Each component of Scrum serves a specific purpose and is essential to Scrum’s success and your usage

of Scrum to develop complex products.

C.

Scrum is a methodology where you can pick and choose which parts of Scrum you think will work for your

environment.

D.

Scrum is a framework for developing and sustaining complex products.

E.

Scrum is based on empiricism and lean thinking.

Question 51

Who is accountable for clearly expressing Product Backlog items? (Choose the best answer.)

Options:

A.

The business analyst who represents the Product Owner.

B.

The Product Owner.

C.

The Scrum Master, or the Scrum Master may have the Developers do it.

D.

The Scrum Master.

Question 52

When is a Product Backlog item considered complete? (choose the best answer)

Options:

A.

When the item passes ail acceptance criteria

B.

When the item has gamed product sponsor approval

C.

At the end of the Sprint

D.

When the item meets the Definition of Done

Question 53

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.

A good way to continue is:

Options:

A.

The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn’t mess up the Product Backlog.

B.

Add enough people to the Development Team for the deadline to be made.

C.

The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master’s duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.

D.

The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.

Question 54

A Scrum Team is experiencing a growing list of impediments. Which techniques would be most

helpful in this situation?

(choose the best two answers)

Options:

A.

As a Scrum Team, prioritize the list and work on them in order.

B.

The Scrum Master discusses the impediments with the Scrum Team.

C.

The Product Owner should add the open impediments to the Product Backlog.

D.

Arrange a triage meeting with management.

Question 55

Which of the following is an example of an Increment? (Choose the best answer.)

Options:

A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of products featured.

F.

All of the above.

Question 56

What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)

Options:

A.

Put them on a separate list on the Scrum board, available for all to see.

B.

Add them to the Product Backlog and keep the Product Owner posted on the expected effort.

C.

Run the integration and regression tests before the end of the Sprint, and capture the open work for the Sprint Backlog of the next Sprint.

D.

Add them to the definition of “Done” so the work is taken care of every Sprint.

Question 57

What is included in the Sprint Backlog?

Options:

A.

User Stories.

B.

Tasks.

C.

Use Cases.

D.

Tests.

E.

Any of the above (or others) which are a decomposition of the selected Product Backlog items.

Question 58

Every Scrum Team should nave:

(choose the best answer)

Options:

A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint

C.

At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.

Question 59

The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take?

Options:

A.

Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.

B.

Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.

C.

Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.

D.

Present the Product Owner with an ordered Product Backlog to use.

E.

Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.

Question 60

What is the timebox for the sprint Review? (choose the best answer)

Options:

A.

1 day

B.

4 hours for a one-month Sprint.

C.

As long as needed

D.

2 hours for a one-month Sprint.

Question 61

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

Options:

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Question 62

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Options:

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.

Question 63

Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

Options:

A.

Economic Value Added.

B.

Respect.

C.

Focus.

D.

Earned Value.

E.

Courage.

Question 64

When is the Sprint Backlog created?

Options:

A.

At the beginning of the project.

B.

During the Sprint Planning meeting.

C.

Prior to the Sprint Planning meeting.

D.

During the Sprint.

Question 65

True or False: Multiple scrum Teams working on the same product must have the same Sprint start date.

Options:

A.

True

B.

False

Question 66

A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?

Options:

A.

Call a meeting between the Development Team and senior management.

B.

Comply with the decision of the self-organizing team.

C.

Consult with the Product Owner to see how he/she feels about the situation.

D.

Begin facilitating productive and useful Sprint Retrospectives.

Question 67

During the Sprint. Me Scrum Master's role is to do which two of the following: (choose the best two answers)

Options:

A.

Facilitate inspection and adaptation opportunities as requested or needed

B.

Coaching the team members in self-management

C.

Ensure the Product Owner attends all scrum events.

D.

Escalate team conflicts to functional line managers

E.

Monitor the progress of the Developers

F.

Assign tasks with the Scrum team.

Question 68

The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

Options:

A.

True

B.

False

Question 69

You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (Choose two.)

Options:

A.

The desire to maintain a stable velocity.

B.

The benefit of Development Teams figuring out a solution for themselves.

C.

The need to have enough work to keep all Development Team members busy.

D.

The ability of the Development Teams to produce integrated Increments.

Question 70

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

Options:

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Question 71

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

Options:

A.

There should be six Product Owners, one tor each Scrum Team.

B.

There should be six Product Owners, reporting to a Chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Question 72

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

Options:

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Question 73

Which are characteristics of the Daily Scrum?

(choose the best two answers)

Options:

A.

Its location and time remain constant

B.

Its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint

Backlog.

C.

It is tree form and designed to promote conversatiom

D.

It is facilitated by the team lead.

E.

It is held first thing in the morning.

F.

It consists of the Scrum Master asking the team tor status.

Question 74

When multiple Scrum Teams are working on a single product, what best describes the

Definition of Done?

(choose the best answer)

Options:

A.

Each Scrum Team uses its own, but must make their definition clear to all other

teams so the differences are known.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

D.

Each Scrum Team defines and uses its own. The differences are discussed and

reconciled during a hardening Sprint.

Question 75

When must a Product Owner release each Increment? (Choose the best answer.)

Options:

A.

When it makes sense.

B.

When the Scrum Team finishes their work.

C.

Whenever the product is free of defects.

D.

After every Sprint, Without exception.

Page: 1 / 25
Total 250 questions