Month End Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

SAP E_S4HCON2023 SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade Exam Practice Test

Page: 1 / 8
Total 80 questions

SAP Certified Technology Specialist - SAP S/4HANA Conversion and SAP System Upgrade Questions and Answers

Question 1

Which preparational steps must be performed for an SAP S/4HANA conversion?

There are 2 correct answers to this question.

Response:

Options:

A.

Uninstall industry extensions not supported by SAP S/4HANA

B.

Install add-on SAP Gateway 7.50

C.

Uninstall Fiori apps not released for SAP_UI 7.50

D.

Delete client 066 (Early Watch Client)

Question 2

You are planning to upgrade your SAP ECC 6.07 system running on a single codepage (SCP) to SAP ECC 6.08. What is the recommended option to perform this upgrade?

Please choose the correct answer.

Response:

Options:

A.

Perform the upgrade to SAP ECC 6.08 before the Unicode conversion.

B.

Combine the upgrade and the Unicode conversion using the Twin Upgrade &Unicode Conversion (TU &UC) procedure.

C.

Perform the Unicode conversion before the upgrade to SAP ECC 6.08.

D.

Combine the upgrade and the Unicode conversion using the Combined Upgrade &Unicode Conversion (CU &UC) procedure.

Question 3

What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.

Options:

A.

Standalone AS ABAP with SAP_BASIS 752 and above

B.

SAP ECC system from SAP ERP 6.0 EHP 8

C.

SAP Solution Manager 7.2

D.

SAP S/4HANA Server 1809 and above

Question 4

During the SUM procedure, the phase XPRAS_AIMMRG fails. Where can you most likely see the reason for the error?

There are 2 correct answers to this question.

Response:

Options:

A.

In the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp

B.

In the latest log files in the SUM directory, subdirectory ABAP, subdirectory log

C.

In the job log for the corresponding job in SM37 (Job Overview)

D.

In the corresponding R3trans log files of this phase

Question 5

You are running an SAP ECC system with SAP_BASIS 740, non-Unicode on SAP MaxDB. Which of the following are possible paths to perform an SAP S/4HANA conversion? Note: There are 3 correct answers to this question.

Options:

A.

Unicode conversion Upgrade to SAP ECC with SAP_BASIS 750 including database migrationSAP S/4HANA conversion without database migration

B.

Unicode conversion SAP S/4HANA conversion including database migration

C.

Unicode conversion SAP S/4HANA conversion without database migration Database migration

D.

SAP S/4HANA conversion including database migration and Unicode conversion

E.

Unicode conversion Database migration SAP S/4HANA conversion without database migration

Question 6

You are performing an SAP S/4HANA conversion with DMO as an inplace migration. How does SUM transfer the data by default from the source database to the target database during the migration?

Options:

A.

Using R3load and network socket connection

B.

Using R3load and memory pipes

C.

Using R3load and file transfer

D.

Using work processes and network socket connection

Question 7

During the configuration of the DMO for SUM, which Migration Parameter selection is NOT possible for an inplace migration?

Options:

A.

DMO with system move

B.

Migration repetition option

C.

Table count verification

D.

Table contents compare

Question 8

You are starting an SAP S/4HANA Conversion. The scenario strategy Downtime Optimized Conversion (DoC) is NOT selectable.What could be the reason?

Options:

A.

The SAP S/4HANA Conversion is without DMO.

B.

The SAP S/4HANA Conversion includes a DMO.

C.

The start release is too old for DOC.

D.

The source database is not supported

Question 9

Which maintenance events are possible with SUM for an SAP system based on AS ABAP 7.40 and above? There are 3 correct answers to this question.

Options:

A.

Dual Stack split

B.

Support Package Stack update

C.

Database migration

D.

Release upgrade

E.

Homogenous system copy

Question 10

You have chosen the "Advanced" option during the main configuration of the SUM tool. Which steps take place via the shadow instance?

There are 2 correct answers to this question.

Response:

Options:

A.

Conversion of application tables (PARCONV_UPG)

B.

Activation of dictionary objects (ACT_UPG)

C.

Switch to new repository (EU_SWITCH)

D.

Modification adjustment (SPDD)

Question 11

During a SUM run, you want to check if the PARCONV_UPG phase is still running properly. Where can you find information about this? Note: There are 2 correct answers to this question.

Options:

A.

Check the running batch job via Job Overview (SM37).

B.

Check for running R3trans processes on the host where SUM is running.

C.

Check for running R3load processes on the host where SUM is running.

D.

Check the latest log files in the SUM directory, subdirectory abap, subdirectory tmp.

Question 12

In which scenarios do you need to use SUM 2.0 instead of SUM 1.0?

There are 2 correct answers to this question.

Response:

Options:

A.

Upgrading to SAP ECC 6.08 without using DMO

B.

Using DMO when applying Support Packages to SAP ECC 6.07

C.

SAP S/4HANA conversion to SAP S/4HANA 1709

D.

Updating to SAP ECC 6.07 using DMO

Question 13

What do you need to know about the SAP S/4HANA Conversion Guide? Note: There are 2 correct answers to this question.

Options:

A.

It explains the database migration option (DMO) of SUM.

B.

It contains a section about the simplification item (SI) checks.

C.

It explains where to find information about the custom code analysis.

D.

It is a database-specific document.

Question 14

You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?

There are 2 correct answers to this question.

Response:

Options:

A.

Run the database migration to the SAP HANA database

B.

Perform the migration of data into the new data structure

C.

Check the compatibility of custom code with SAP S/4HANA

D.

Apply the recommendations of the simplification list

Question 15

During a SUM run you want to check if the phase SHADOW_IMPORT_INC is still running properly. Where can you find information about this?

There are 2 correct answers to this question.

Response:

Options:

A.

Check for running batch jobs in the shadow system via Job Overview (SM37)

B.

Check for running R3trans processes on the host of the primary application server

C.

Check for running R31oad processes on the host of the primary application server

D.

Check for the latest log files in the SUM directory, subdirectory ABAP, subdirectory tmp

Question 16

You are performing an upgrade of an SAP ECC development system with SUM. What is the earliest point when the upgrade is considered complete and you can allow all dialog users to log on to the system?

Please choose the correct answer.

Response:

Options:

A.

After the SUM roadmap step "Execution" is finished and before "Postprocessing"

B.

During the SUM roadmap step "Postprocessing", after the post procedure steps are complete

C.

During the SUM roadmap step "Postprocessing", in parallel with post procedure steps

D.

After the SUM roadmap step "Postprocessing" and post procedure steps are finished

Question 17

You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step "Configuration". For some software components you find entries in the "Calculated level" column.

What does the "Calculated level" indicate for those software components?

Please choose the correct answer.

Response:

Options:

A.

The SAP Support Packages that will be bound to the upgrade

B.

The SAP Support Packages contained in the upgrade media

C.

The SAP Support Packages found in the download directory

D.

The SAP Support packages of the Support Package Stack, calculated by the Maintenance Planner

Question 18

You are planning to use DMO of SUM to perform an "inplace-migration" to SAP HANA. What do you need to consider? Note: there are 2 correct answers to this question.

Options:

A.

The source system is non-Unicode and the target database is a scale-out system.

B.

The target database size increases temporarily because of the Shadow Repository.

C.

SAP HANA Landscape Reorganization required a manual step to edit a file.

D.

Network capacity between exporting and importing R3load processes must be.

E.

Unicode conversion is part of DMO only in case of target version AS ABAP 7.40 or 7.31.

Question 19

During a DMO procedure with SUM, after which phase is the repository first available on the target database?

Please choose the correct answer.

Response:

Options:

A.

Uptime migration (EU_CLONE_MIG_UT_RUN)

B.

ParaUel distribution (PARDIST_SHD)

C.

Downtime migration (EU_CLONE_MIG_DT_RUN)

D.

Shadow repository creation (EU_IMPORT*)

Question 20

You want to perform custom code check via ABAP test cockpit in preparation of your SAP S/4HANA conversion? What kind of SAP System can you use to generate the custom code migration worklist?

Options:

A.

AA

B.

A Standalone SAP system with ABAP 7.51 or above

C.

An SAP S4HANA 1709 sandbox system

Question 21

During the configuration of the DMO for SUM, how does the tool behave if option "Do not compare table contents" is selected regarding table comparison?

Please choose the correct answer.

Response:

Options:

A.

It performs a comparison on selected tables using check sum.

B.

It performs a comparison on all tables using row counts.

C.

It performs a comparison of all tables using check sum.

D.

It does NOT perform any table comparison.

Question 22

You want to perform an SAP S/4HANA conversion using SUM with DMO. Which steps run before the beginning of the technical downtime, independent of your SUM configuration?

There are 3 correct answers to this question.

Response:

Options:

A.

Generation of the new ABAP loads in phase RUN_SGEN_GENER8

B.

Import of upgrade and language data from the download directory in phase TABIM UPG

C.

Activation of dictionary objects in phase ACT_UPG

D.

Creation of application tables in the SAP HANA database in phase EU_CLONE_MIG_DT_CREATE

E.

Import of dictionary objects from the download directory in phase DDIC_UPG

Question 23

Which are valid options to check the progress of the database migration in a Microsoft Windows environment?

There is correct answers to this question.

Response:

Options:

A.

Check the "Charts Control Center" in the SUM UI

B.

Check logs for jobs starting with "RSUPG_SGEN" in the system

C.

Check the log files written under "SUM\abap\log"

D.

Check the dump size of the database export on disk

Question 24

You are using the maintenance planner to calculate the required software components for your SAP S4HANA conversion. What do you need to know regarding SUM?

Options:

A.

AA

B.

As soon as the next SP level of SUM is available, the current version of SUM passes into "patch on request mode" immediately.

Page: 1 / 8
Total 80 questions