Month End Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

SAP C_TS422_2023 SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Exam Practice Test

Page: 1 / 8
Total 80 questions

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Questions and Answers

Question 1

What information do you have to maintain to define the relationship between supply source and demand source in the Kanban process? Note: There are 2 correct answers to this question.

Options:

A.

Routing

B.

Work Center

C.

Replenishment strategy

D.

Production supply area

Question 2

You are trying to create a production order, but NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.

Options:

A.

The order lot size is NOT within the validity range of a production version.

B.

NO production lines are assigned to the production versions.

C.

All production versions for the material are locked.

D.

NO bills of material (BOMs) are assigned to the production versions.

Question 3

You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.

Options:

A.

Set the creation indicator for purchase requisitions on the initial screen of the MRP run.

B.

Add the agreement to the source list mark it for MRP relevance.

C.

Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.

D.

Add the agreement to the quota arrangement mark it for MRP relevance.

Question 4

How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.

Options:

A.

They are created together with the independent requirement for the finished product.

B.

They are created on assembly level during the planning run.

C.

They are created with exact times in Advanced Planning.

D.

They are only created for multilevel bill of material (BOM) structures.

Question 5

Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

Options:

A.

In which storage location is the BOM required?

B.

Is the material type allowed in the BOM?

C.

Which base unit of measure does the material have?

D.

What status does the BOM have?

Question 6

What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?

Options:

A.

The MRP run assumes external procurement.

B.

The MRP run assumes in-house production.

C.

The MRP run plans the material only if a quotation has been maintained.

D.

The MRP run does NOT consider the material; it has to be planned interactively.

Question 7

Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

Options:

A.

Assign the alert profile to the overall profile.

B.

Assign the overall profile to the authorization profile.

C.

Create an object selection variant for alerts according to the priority of ATP categories.

D.

Create an object selection variant for production-planning-related alerts.

Question 8

Your company manufactures materials whose characteristics differ for each manufacturing process. Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track and use this information in all areas of logistics?

Options:

A.

Process order management

B.

Engineering change management

C.

Quality management

D.

Batch management

Question 9

Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

Options:

A.

Assign planned orders manually in the planning table.

B.

Run MRP with quota arrangement.

C.

Run MRP with automatic selection of production version.

D.

Run PP/DS heuristics for repetitive manufacturing.

Question 10

What are some SAP-recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.

Options:

A.

Establish an organizational structure, technical foundation, and transformation methodology for clean core.

B.

Integrate clean core practices in the end-to-end value process chain.

C.

Establish release management.

D.

Establish regular housekeeping tasks and procedures.

E.

Define roles and responsibilities as part of a process transformation office.

Question 11

How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

Options:

A.

Execute an infinite production planning run for the critical resources.

B.

Reduce the planning time interval.

C.

Determine a time period with available capacity on the planning board.

D.

Increase the capacity supply in a time-phased interval.

E.

Form optimum sequences to reduce setup times.

Question 12

Where do you maintain the data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.

Options:

A.

Work center

B.

Material master

C.

Routing

D.

Production version

Question 13

How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.

Options:

A.

Digital signature

B.

Approved resources

C.

Recipe approval

D.

GMP-compliant flag

E.

Batch record

Question 14

You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?

Options:

A.

The previously dispatched operation stays as is; the new operation is inserted before the dispatched operation.

B.

The previously dispatched operation stays as is; the new operation is inserted after the dispatched operation.

C.

The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

D.

The new operation is inserted at the desired time; the previously dispatched operation is moved backward.

Question 15

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Options:

A.

Assembly processing with production orders (82)

B.

Planning with final assembly (40)

C.

Planning without final assembly (50)

D.

Make-to-stock production (10)

Question 16

Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.

Options:

A.

You can use trigger points to automatically create rework orders via confirmations.

B.

You can use mass processing to set production orders to technically complete.

C.

You can use the production scheduling profile to automatically set orders to technically complete.

D.

You can use mass processing to read PP master data for production orders.

Question 17

Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.

Options:

A.

Net requirements calculation is carried out for every sales order individually.

B.

Production orders are created with sales order reference.

C.

Storage location MRP areas are required for sales-order-specific stock.

D.

Both the reduction of make-to-order stock and requirements occur on delivery.

E.

Sales orders have to be ATP-confirmed (available-to-promise) to be saved.

Question 18

What does the material type influence? Note: There are 2 correct answers to this question.

Options:

A.

Which document types and class categories are allowed

B.

Which plant-specific and plant-independent statuses are allowed

C.

Which material master screens appear and in which sequence

D.

Whether the material is produced in-house, procured externally, or both

Question 19

What can you use standard heuristics in Advanced Planning (PP/DS) for?

Options:

A.

To automate material movements in material staging

B.

To set default values in production master data

C.

To solve planning problems for defined objects

D.

To optimize costs and times in production plans

Question 20

Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

Options:

A.

Wait time

B.

Float before production

C.

Processing time

D.

Pick time

E.

Setup time

Question 21

Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.

Options:

A.

Procurement type

B.

Material type

C.

MRP type

D.

MRP group

Question 22

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

Options:

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities.

C.

Alternative work centers are fully occupied.

D.

The Change Planning Direction indicator is set in the strategy profile.

Question 23

During production order creation, several valid production versions are found. How does the system choose the production version?

Options:

A.

Alphanumeric or quota arrangement

B.

Planned order or material number

C.

Validity period or sales order

D.

Lot size or material cost

Question 24

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.

Options:

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Orders (dispatched) chart

D.

Work center capacities chart

Page: 1 / 8
Total 80 questions