What information do you have to maintain to define the relationship between supply source and demand source in the Kanban process? Note: There are 2 correct answers to this question.
You are trying to create a production order, but NO valid production version can be selected. What could be the reasons? Note: There are 2 correct answers to this question.
You have a scheduling agreement with a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? Note: There are 2 correct answers to this question.
How are dependent requirements for assemblies created? Note: There are 2 correct answers to this question.
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
Your company manufactures materials whose characteristics differ for each manufacturing process. Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track and use this information in all areas of logistics?
Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
What are some SAP-recommended guiding principles to achieve clean core operations? Note: There are 3 correct answers to this question.
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
Where do you maintain the data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.
You want to insert an operation at a certain time on a work center in the graphical planning table. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?
Which of the following automation options can you use for production orders? Note: There are 2 correct answers to this question.
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision? Note: There are 3 correct answers to this question.
What does the material type influence? Note: There are 2 correct answers to this question.
What can you use standard heuristics in Advanced Planning (PP/DS) for?
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
Which master data fields can have an impact on whether MRP creates planned orders or purchase requisitions for a material? Note: There are 2 correct answers to this question.
What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.
During production order creation, several valid production versions are found. How does the system choose the production version?
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA Cloud Private Edition? Note: There are 2 correct answers to this question.