Question 1

Where can you find pre-delivered integration content? Note: There are 3correct answers to this question.

Options:

A.

Cloud Integration Automation service

B.

SAP Business Accelerator Hub

C.

SAP Help Portal

D.

SAP Cloud ALM

E.

SAP Discovery Center

Question 2

Which tool migrates the database and converts the data during a system conversion to SAP S/4HANA Cloud Private Edition?

Options:

A.

Custom Code Migration app

B.

SAP Data Services

C.

SAP S/4HANA migration cockpit

D.

Software Update Manager

Question 3

Which of the following are prerequisites for using the "RISE with SAP system transition workbench"? Note: There are 2correct answers to this question.

Options:

A.

A migration server has been provisioned.

B.

The user received permission to access the operating system of the target system.

C.

The SAP Host Agent has been correctly configured.

D.

All custom ABAP code have been removed from the system.

Question 4

What does the Side-by-Side extensibility option mean?

Options:

A.

Extending SAP S/4HANA using SAP ABAP Development Workbench.

B.

Extend SAP S/4HANA using APIs published on SAP Business Accelerator Hub.

C.

There are two SAP S/4HANA instances: one for standard code and another for custom developments

D.

SAP S/4HANA extensions are context-aware and focused on tight integration.

Question 5

Which of the following is used to perform configuration in SAP S/4HANA Cloud, private edition?

Options:

A.

SAP Solution Manager

B.

IMG (Implementation Guide)

C.

Self Service Configuration Uls (SSCUIs)

D.

SAP Central Business Configuration

Question 6

What accelerator can help you document the configuration definition in the Explore phase?

Options:

A.

Data definition template

B.

Backlog template

C.

Change request template

D.

Test plan template

Question 7

How is SAP’s organizational change management framework connected with the SAP Activate methodology? Note: There are 2correct answers to this question.

Options:

A.

The SAP Activate phases build the dimensions of the organizational change management framework.

B.

C) Each change management dimension is assigned to a specific SAP Activate phase.

C.

The start of each change management activity is assigned to one specific SAP Activate phase.

D.

Some change management activities are executed in more than one SAP Activate phase.

Question 8

Which tool is used for documenting progress, managing tasks, and supporting quality gates throughout the RISE with SAP implementation phases?

Options:

A.

SAP Enable Now

B.

SAP Cloud ALM

C.

SAP Build Apps

D.

SAP Signavio Process Insights

Question 9

What is the primary purpose of the SAP Activate methodology?

Options:

A.

Texpedite all deployments of SAP products

B.

To provide end-to-end application lifecycle management

C.

To enable access to the SAP ecosystem

D.

To manage project documentation

Question 10

How do you move extensions between SAP S/4HANA Cloud Private Edition systems? Note: There are 2correct answers to this question.

Options:

A.

Assign items to a software package

B.

Mark items relevant for transport

C.

Import the collection

D.

Assign items to a software collection

Question 11

How would you describe the different dimensions of SAP’s organizational change management framework? Note: There are 3correct answers to this question.

Options:

A.

Change communication encompasses activities to provide relevant project information to the different stakeholder groups at the right time.

B.

Change leadership involves activities to enable all management levels to handle the cloud implementation and deal with resistance.

C.

Change strategy covers activities to set up change management properly.

D.

Change realization includes activities to realize the business benefits associated with the cloud implementation.

E.

Change effectiveness contains activities that can be applied to evaluate the impact of change management interventions.

Question 12

Which items are provided by the clean core quality gate report? Note: There are 2correct answers to this question.

Options:

A.

Policies and procedures governing the project

B.

Integration, Extensibility, Data, Cross Topics, Process, and Operation topics

C.

Project management quality gates

D.

Recommended Action Plans

Question 13

What is the main purpose of the Transformation Preparation Service (TPS)?

Options:

A.

To train end-users on the new SAP system functionalities

B.

To develop custom extensions for the SAP Cloud ERP private edition

C.

To align business objectives with execution strategies accelerating adoption of software entitlements acquired by the customer

D.

To provide post-implementation support and maintenance

Question 14

Which organizational change management activity is usually performed in which SAP Activate phase? Note: There are 2correct answers to this question.

Options:

A.

The business readiness assessment is usually conducted in the discover phase.

B.

The change plan is usually developed in the explore phase.

C.

The user adoption analysis is usually conducted in the run phase.

D.

The change assessment is usually conducted in the prepare phase.

Question 15

Which of the following elements should be included in the solution design to ensure alignment with business requirements? Note: There are 3correct answers to this question.

Options:

A.

System landscape blueprint detailing the technical architecture

B.

Test plan focusing on validating functionality

C.

Business case including project goals, cost estimates, expected ROI!

D.

Data migration strategy and approach for transitioning to the new solution

E.

Integration design specifications for connecting SAP and non-SAP systems

Question 16

What is identified in a customer's system through the SAP Readiness Check? Note: There are 2correct answers to this question.

Options:

A.

Overview of financial data quality

B.

Recommended SAP Business Technology Platform services

C.

Recommended SAP Business Accelerator Hub prebuilt integration content

D.

Related simplification items and corresponding compatibility packages

Question 17

In the SAP Activate prepare phase, the cloud project is set up and officially launched.Which change management activities are usually started in this phase? Note: There are 3correct answers to this question.

Options:

A.

Develop and align the change network strategy

B.

Identify the key stakeholders and conduct a stakeholder analysis

C.

Facilitate the role mapping process

D.

Conduct a detailed change impact analysis

E.

Develop an initial change plan for the cloud project

Question 18

What are the special characteristics of SAP’s organizational change management framework? Note: There are 3correct answers to this question.

Options:

A.

It contains activities that help to enhance system performance.

B.

It is aligned with the SAP Activate implementation methodology.

C.

It supports an agile way of working.

D.

It is only suitable for large-scale, complex cloud deployments.

E.

Itis targeted at fostering fast and sustainable user adoption.

Question 19

During a system conversion, which of the following does SAP recommend you do in the Discover phase of the SAP Activate methodology ?

Options:

A.

Define an integration test strategy.

B.

Create a cutover plan.

C.

Perform a sandbox conversion.

D.

Define a system conversion strategy.

Question 20

You are transitioning to SAP S/4HANA.In which phase do you adjust custom code?

Options:

A.

Realize

B.

Prepare

C.

Explore

D.

Deploy

Question 21

What can you use to migrate data to SAP S/4HANA Cloud Private Edition for a new implementation? Note: There are 3correct answers to this question.

Options:

A.

Core data services

B.

Adirect connection to an SAP ERP system

C.

XML or CSV templates

D.

The zero-downtime service

E.

Aseparate SAP HANA database

Question 22

Which of the following tasks are included in the SAP S/4HANA Cloud Private Edition standard services delivered by SAP for a new implementation? Note: There are 3correct answers to this question.

Options:

A.

Activating SAP Best Practices content in the system

B.

Implementing customizations tthe SAP Best Practices business processes

C.

Configuring the SAP Best Practices business processes

D.

Provisioning a client with the desired client setup alternative

E.

Activating required business functions in client 000

Question 23

Which of the following steps are part of the fit-to-standard process? Note: There are 2correct answers to this question.

Options:

A.

Enable customers on standard business processes

B.

Design to-be business process models

C.

Document integration requirements

D.

Review Best Practices process flow

Question 24

Which of the following connectivity options can you use to connect to a customer's SAP S/4HANA Cloud Private Edition environment?

Options:

A.

VPN connection to the customer's network.

B.

SSH connection tthe application server.

C.

Remote Desktop Protocol (RDP) access to the migration server.

D.

Direct access to the HANA database server's operating system.