SAP C_ACT_2403 SAP Certified Associate - Project Manager - SAP Activate Exam Practice Test

Page: 1 / 8
Total 82 questions

SAP Certified Associate - Project Manager - SAP Activate Questions and Answers

Question 1

What is the purpose of the scrum board?

Options:

A.

To visualize team progress

B.

To manage the resource load

C.

To show the functional breakdown of the solution scope

D.

To document the results of the Integration Test

Question 2

Which systems are part of the private cloud edition landscape?Note. There are 2 correct answers to this question.

Options:

A.

Production

B.

Sandbox

C.

Starter

D.

Evaluation

Question 3

Which of the following capabilities does SAP Solution Manager Test Suite support? Note: There are 2 correct answers to this question.

Options:

A.

Multi-technology change impact analysis

B.

Tests for SAP and non-SAP solutions

C.

Manual and automated functional tests

D.

Load and volume testing

Question 4

What is the objective of a sprint retrospective meeting?

Options:

A.

Improve the Scrum process.

B.

Provide formal feedback to the Project Manager.

C.

Define the stakeholder management approach

D.

Review and prioritize the backlog.

Question 5

When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape, in which phase are the Business Roles updated?

Options:

A.

Explore

B.

Realize

C.

Deploy

D.

Discover

Question 6

Which of the following are cornerstones of SAP's security strategy? Note: There are 3 correct answers to this question

Options:

A.

Secure Company

B.

Secure Projects

C.

Secure Operations

D.

Secure Infrastructure

E.

Secure Products

Question 7

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

Options:

A.

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

B.

Project Manager's relative effort estimate that will be needed to implement and test the user ^ story

C.

Detailed bottom-up effort estimate by the product owner that breaks up each story into short ^ tasks

D.

Relative effort estimate in Ideal Person Days that reflects the best estimate by the project ^ team

Question 8

What is Scrum of Scrums?

Options:

A.

Frequent inspection of code and configuration prior to quality gates

B.

Integration meeting among the various Scrum teams

C.

Mechanism for gathering and validating requirements

D.

Alternative to regular Scrum process for smaller teams

Question 9

Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question.

Options:

A.

Test strategy document

B.

Requirements feature in SAP Cloud ALM

C.

Quality gate checklist and quality gate guide

D.

Business-Driven Configuration questionnaire

Question 10

Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question.

Options:

A.

Design to-be business process models

B.

Review Best Practices process flow

C.

Document integration requirements

D.

Enable customers on standard business processes

Question 11

What accelerator can help you document the configuration definition in the Explore phase?

Options:

A.

Data definition

B.

Change request template

C.

Test strategy

D.

Backlog template

Question 12

What findings do you document in the Explore Phase workshops? Note: There are 3 correct answers to this question.

Options:

A.

Business role mapping

B.

Key business decisions

C.

Detailed design of extensions

D.

Confirmation of scope

E.

Process models

Question 13

When deploying a new implementation on-premise, which of the following is recommended when performing custom development?

Options:

A.

SAP Business Technology Platform

B.

SAP Best Practices

C.

SAP API Business Hub

D.

SAP ABAP Workbench

Question 14

When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?

Options:

A.

Realize phase scope, planning, and budget should be completed and final.

B.

Release plan and sprint ceremony guidelines should be finalized.

C.

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

D.

User stories on product backlog should be in ready state for the first 2 to 3 sprints.

Question 15

What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?

Options:

A.

SAP Support Portal

B.

SAP Roadmap Viewer

C.

SAP Transformation Navigator

D.

SAP Cloud ALM

Question 16

What is the correct order of the SAP Activate methodology phases?

Options:

A.

Discover > Prepare > Explore > Realize > Deploy > Run

B.

Plan > Build > Run > Sustain

C.

Plan Design > Build > Operate

D.

Prepare > Discover > Explore > Realize > Deploy > Run

Question 17

Which of the following characteristics relate to the Focused Build for SAP Solution Manager functionality? Note: There are 2 correct answers to this question.

Options:

A.

SAP delivers all knowledge required with the solution.

B.

SAP delivers a standard solution with its own separate license

C.

SAP delivers a standard solution without any additional coding required

D.

SAP delivers all configuration activities within your project

Question 18

Which of the following are SAP Activate workstreams?Note: There are 2 correct answers to this question.

Options:

A.

Change Management

B.

Project Management

C.

Extensibility

D.

Data Migration

Question 19

You are implementing SAP S/4HANA Cloud, public edition for your customer.How are your customer systems activated?

Options:

A.

Via the SAP Cloud ALM

B.

Via the SAP Contact Center

C.

Via the Central Business Configuration System

D.

Via the SAP Business Technology Platform

Question 20

Which of the following characteristics are unique to SAP S/4HANA Cloud, public edition?Note:

There are

3 correct answers to this question.

Options:

A.

Software upgrades performed by SAP

B.

Choice of hardware vendor

C.

Customer data center deployment

D.

Optional 3-system landscape

E.

Mandatory upgrades

Question 21

What criteria does the product owner use to sequence the backlog?Note: There are 2 correct answers to this question.

Options:

A.

Technical dependencies

B.

Release planning schedule

C.

Business priority

D.

Complexity of the story

Question 22

What is the primary purpose of the SAP Activate methodology?

Options:

A.

To provide end-to-end application lifecycle management

B.

To manage solution documentation

C.

To expedite all deployment options for SAP products

D.

To enable access to the SAP ecosystem

Question 23

When doing a new implementation on premise or private cloud, which system is recommended to demonstrate standard functionality in the Explore phase?

Options:

A.

Starter

B.

Development

C.

Trial

D.

Sandbox

Question 24

What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question

Options:

A.

Prioritize backlog user stories by business priority.

B.

Define objectives for each release

C.

Estimate the backlog user stories.

D.

Analyze the functional and technical dependencies between user stories

Page: 1 / 8
Total 82 questions