PeopleCert MSP-Practitioner MSP Practitioner, 5th edition Exam Exam Practice Test
MSP Practitioner, 5th edition Exam Questions and Answers
Here are three statements about the programme justification for the Smart Meter Programme. In which document should the statements be recorded?

The programme is in the ‘design the outcomes’ process. One risk to the programme is that new and improved meter technology may be developed during implementation. This risk has been assessed as high probability and high impact and is therefore a high priority. The initial delivery approach proposes a phased roll-out of the meters so that the programme can exploit any new technology that emerges. The CTO has been appointed as the owner of this risk.
Is this appointment an appropriate application of the identify and prioritize risks’ activity, and why?
The CFO has been appointed as the SRO for the Smart Meter Programme.
Is this appointment an appropriate application of the ‘organization’ theme, and why?
During the ‘plan progressive delivery’ process, it was decided that the call centre managers would hold a weekly meeting with all call centre staff to update them on progress and understand any concerns that they might have. This information was documented by the programme manager.
Which theme is being applied?
Which of the following is Management document?
Which type of cost is associated in training, moving and supporting an operational unit?
The programme is in the ‘deliver the capabilities’ process. When the Call Centre Rationalization Project is complete, it will be important to inform all staff and customers. This is because there will be new contact details for the new single call centre with longer opening hours. The programme manager has planned for both internal and external announcements to publicize this.
Which theme is MOST relevant to these planned activities?
The programme is in the first tranche. The programme manager met with the project managers from the Employment Contracts and Call Centre Rationalization projects as well as the BCM. Many topics were discussed. After the meeting, the programme manager reviewed the information gathered at the meeting.
Which information should result in an addition to the risk register?
When approval to proceed is given at the end of Defining a Programme, what does this mean?
Which of the following is an Information Baseline?
The Employment Contracts Project in Tranche 1 will identify the skills needed by sales staff. However, the Customer Processes Project in Tranche 2 will define new ways to sell gas and electricity to existing water customers which may result in changes to the previously defined skills requirements. If any rework is required, this would delay increasing the number of electricity and gas customers. The programme manager has set up a process to independently monitor the situation, so they can be warned immediately if this becomes likely to happen.
Which principle is being applied MOST by the programme manager when implementing the independent monitoring, and why?
Which activity from the Smart Meter Programme should be delivered using a continual improvement approach?
POTI model is part of which governance theme?
The following statement needs to be recorded:
"The vision statement will be developed and tested in a facilitated workshop with the senior officers from each department, before final approval by the CEO."
In which section of the programme strategy should this be recorded?
Which of the following is NOT normally a characteristic of the Vision Statement?
The ‘identify the programme’ process has started. The programme manager organized a meeting to discuss the work being planned for the ‘design the outcomes’ process. It was agreed that the Call Centre Manager and the CEngO should be included in future planning meetings.
Which theme is being applied?
Here are three actions to be performed during the Smart Meter Programme. Which role has an area of focus associated with each statement?

The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
At which transformational flow basic programme controls are established?
The programme is in the ‘design the outcomes’ process for the first time. The Research and Development Project team has recommended that UU sources an imported next generation smart meter. This is an alternative to the development of the smart meter internally. The imported meter can be fully implemented before the CEO retires in three years' time. However, there is a possibility that this meter could lead to future information security risks.
Is this recommendation an appropriate application of the ‘decisions' theme, and why?
Which of following is not expected from senior leadership of programme?
Which of following groups can be a stakeholder for building a city programme?
In delivering the capability, which role is responsible for aligning projects with programme objectives?
The programme manager has analysed the costs of using an expert external company to work on the Research and Development Project. Although using the external experts is likely to produce a higher quality solution which would lead to increased organizational adoption, the SRO has insisted that the project only uses internal staff to minimize costs.
Is the SRO's response an appropriate application of the ‘deploy diverse skills' principle, and why?
Which of following Best defines capital cost?
Select the best option defined by following sentence: 'Action of carrying out the coordinated organization, direction and implementation of dossier of projects and transformation activities to achieve desired outcomes'
Which of the following statements is NOT TRUE?
Which of following is output of 'Defining the programme'?
Which of the following is not true about programme control?
Which is not a valid response for a threat?
As the influence of a stakeholder increases, it is recommended that a 'higher' level of engagement is appropriate. Which of the following describes this increasing engagement?
The programme is starting Tranche 1 and there is a lot of dissatisfaction in the workforce about the planned merging of the engineering roles. The programme board has made some proposals on how to deal with this issue but is unsure whether to involve the sponsoring group.
According to the ‘decisions’ theme, which document should be consulted to clarify whether it is necessary to escalate this issue to the sponsoring group?
UU has always used a linear project management methodology in the past with varying degrees of success. During the ‘design the outcomes’ process, UU has decided to trial an agile approach to deliver projects throughout Tranche 1.
Which theme is being applied to the ‘design the outcomes' process?
The programme has successfully completed all projects and work according to the delivery plan and is in the ‘close the programme' process. All internal staff, who had worked on the programme, must now be transferred back into business as usual roles.
Which role should be responsible for managing these activities?
For a programme that focuses on Political and societal change which scenario will lead to lower probability of success?
Which of the following is an activity in Defining a Programme?
There is a risk that the utilities market is changing, with green energy solutions becoming more attractive to customers. As UU does not currently offer this type of green energy, the benefits gained from cross-selling electricity and gas to current water customers may be overestimated.
Which activity is relevant in the ‘plan’ phase of the Plan-Do-Check-Act (PDCA) cycle?
During the 'identify the programme’ process, the SRO identified that the utility regulator may be considering a fair pricing policy to protect vulnerable customers. The introduction of this policy would have a significant impact on the benefits expected by UU. The programme manager included this information in the programme brief.
How well does this apply the 'deal with ambiguity’ principle, and why?
The engineering department has been asked to produce a weekly report for the programme board. The report will include data on how many new water meters have been installed in the last seven days. The programme manager is writing the assurance approach. The engineering department report has been included as part of the first line of defence.
Is this an appropriate application of the assurance’ theme, and why?

