Labour Day Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PfMP Portfolio Management Professional (PfMP) Exam Practice Test

Page: 1 / 50
Total 495 questions

Portfolio Management Professional (PfMP) Questions and Answers

Question 1

One of the stakeholders of one of your components came to you complaining that his manager is not receiving specific information on multiple components progress. What is your best course of action?

Options:

A.

Raise the issue to the governance board as you have already analyzed this manager

B.

Send the manager the needed information asked by the stakeholder

C.

Meet the manager and understand what information is required

D.

Add the manager to the weekly reports distribution list where there is a lot of information on the components

Question 2

Your online ordering company wants to add a component to its portfolio that its sponsor believes will outdistance the competition, but it has risks and also will be subject to regulatory approval. The purpose is to use parachutes to deliver the merchandise ordered through small helicopters so the recipients receive their orders within three hours of the on line purchase. As the portfolio manager you recognize this component is a major change and will require resources if it is approved. You are now performing change management using a change structure that:

Options:

A.

Requires a change request

B.

Facilitates impact analysis

C.

Needs to assess dependencies

D.

Requires an update to the roadmap

Question 3

Assume you work in a weak matrix structure in your pharmaceutical company in which most of the program and project managers are coordinators, and most of the staff that supports them are in functional organizations. On some high priority programs, staff may be dedicated to the program full time for a short time period; however, operational work often takes precedence especially in manufacturing. The demand for some of the pharmaceutical products often outpaces the available supply, and shelf life is short. These fluctuations of resources then:

Options:

A.

Require use of resource smoothing

B.

Led to the development of resource heuristics as to how best to manage the portfolio

C.

Require sign-offs from functional managers on the portfolio charter concerning resource availability

D.

Impact the availability of the work managed within the portfolio

Question 4

Your portfolio management team is a bit confused about the order of steps to follow when defining a portfolio. They have been having debates and they came to you asking for the correct order of steps

Options:

A.

Identification, categorization, ranking, scoring, selection, prioritization, resource allocation

B.

Identification, categorization, scoring, ranking, prioritization, selection, resource allocation

C.

Identification, selection, categorization, scoring, ranking, prioritization, resource allocation

D.

Identification, categorization, scoring, ranking, selection, prioritization, resource allocation

Question 5

You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you have developed a robust performance management plan. What is the expected result from developing this plan?

Options:

A.

Portfolio Management Plan updates, Portfolio updates, Portfolio Reports, Enterprise Environmental Factors updates

B.

Portfolio Management Plan updates, Portfolio Process Assets updates

C.

Portfolio Management Plan updates, Organizational Process Assets updates, Portfolio Process Assets updates, Portfolio updates

D.

Portfolio Management Plan updates, Organizational Process Assets updates, Portfolio Reports, Enterprise Environmental Factors updates

Question 6

Managing Strategic Change is an integral part of any portfolio in order to remain aligned with the strategic objectives. Your portfolio has undergone a major strategic change and you are currently determining if, when, what, and how of implementing the change in order to re-align the portfolio. What are you currently doing?

Options:

A.

Gap Analysis

B.

Readiness Assessment

C.

Change Analysis

Stakeholder Analysis

Question 7

Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently aggregating value delivered by the portfolio components. Which of the following methods are helpful to you?

Options:

A.

Elicitation techniques, Capability & Capacity Analysis, PMIS

B.

Scenario Analysis, Capability & Capacity Analysis, Quantitative & Qualitative Analysis

C.

Elicitation techniques, Communication Requirements Analysis, Stakeholder analysis

D.

Elicitation techniques, Value Scoring & Measurement Analysis, Benefits Realization Analysis

Question 8

After the stakeholder analysis is complete, a best practice is to put stakeholders into a matrix to develop a communications management strategy. A simple but useful approach is to set it up to show:

Options:

A.

Level of authority and level of interest

B.

Level of authority and level of involvement

C.

Level of influence and level of impact

D.

Level of influence and level of interest

Question 9

Assume you have been asked to prepare the portfolio management plan as you are on the staff of your company's Chief Portfolio Officer. In this plan, you will describe the different methods or approaches that your company will use to manage different types of components in the portfolio as specified in the:

Options:

A.

Strategic plan

B.

Governance model

C.

Roadmap

D.

Charter

Question 10

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you are coaching your team on the same. A major risk has recently occurred and the risk owner came to you asking advise on how to report it. what would you advise her?

Options:

A.

Portfolio Process Assets

B.

Risk Register

C.

Portfolio Organizational Assets

D.

Portfolio Reports

Question 11

You have just finished a major checkpoint in your portfolio and the portfolio has to undergo several changes in order to re-align with the strategies. One component of your portfolio has been cancelled and the resources are going to be reallocated to other components. Which process does these activities?

Options:

A.

Manage Supply & Demand

B.

Authorize Portfolio

C.

Manage Portfolio Oversight

D.

Optimize Portfolio

Question 12

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. You are currently in the middle of developing the strategic plan and require the following inputs

Options:

A.

Organizational Strategy & Objectives, Enterprise Environmental Factors, Roadmap

B.

Organizational Strategy & Objectives, Enterprise Environmental Factors, Organizational Process Assets, Portfolio Process Assets, Inventory Of Work

C.

Organizational Strategy & Objectives, Enterprise Environmental Factors, Roadmap, Portfolio Management Plan

D.

Organizational Strategy & Objectives, Enterprise Environmental Factors, Portfolio, Portfolio Management Plan

Question 13

Portfolio management processes are performed in an environment broader than a portfolio; therefore, an organization-level implementation team supported by executive management, a governing body, and portfolio managers join forces to implement organization-level portfolio management processes. After Defining roles and responsibilities for portfolio management process implementation, what should be the FIRST next step?

Options:

A.

Define and deploy detailed portfolio management processes and provide training to staff and stakeholders.

B.

Changing business processes

C.

Developing the Portfolio Strategic Plan

D.

Communicate the portfolio management implementation plan

Question 14

In your diversified chicken products company, your portfolio of components in progress consists of approximately 175 programs, projects, and other work. Generally, at each Portfolio Review Board meeting, about 35 new proposals are reviewed to see if they should be part of the portfolio. As the portfolio manager, you have set up categories for these components. They are useful to facilitate portfolio optimization because:

Options:

A.

They use filtering to eliminate certain components from consideration

B.

They help identify the components that meet requirements for consideration

C.

They serve as key evaluation criteria

D.

They address organizational strategy and objectives

Question 15

A big strategic change occurred at the organization level and has impacted multiple portfolios in the organization including yours. The sponsor has asked you to analyze the change and update the needed documents. You managed this change and are currently updating the Portfolio Management Plan. Which of the following are part of this update

Options:

A.

Portfolio Organizational Structure

B.

Communication and Performance Management

C.

Stakeholder Engagement

D.

All of the options

Question 16

As you work to determine which stakeholders had the highest degree of influence over the portfolio, you wanted to especially know about the members of the Portfolio Governance Board because:

Options:

A.

They would have numerous interrelationships with other stakeholders

B.

They would be best suited to work with people who were not portfolio management supporters

C.

The governance processes affect information requirements

D.

All of the portfolio changes, risks, and issues would be of interest to them

Question 17

Your health insurance company has set up its portfolio into five different categories: research and development, IT, Medicare, government health insurance, and non-government health insurance. Funding is allocated yearly to each of these six categories. As the portfolio manager at the enterprise level, you:

Options:

A.

Ensure such allocations are reflected in the portfolio's strategic plan

B.

Meet with the CFO and determine these allocations when the budget for the fiscal year is being prepared

C.

Meet with the managers of the five portfolios once the budget allocations are known

D.

Use your existing inventory of components in the portfolio and in the pipeline to determine funding allocations

Question 18

As part of developing the Communication Management Plan, a portfolio manager executes the Communication Requirements Analysis, in addition to Stakeholders Analysis. Which of the following options in your opinion is a result of the Stakeholders Analysis?

Options:

A.

All of the options

B.

Communication Matrix

C.

Communication Strategy matrix

D.

Elicitation technique

Question 19

Chartering the portfolio is an important step towards the initiation of the endeavor. It authorizes the portfolio managers to use the resources and marks the first step towards the allocation of resources to the components upon their initiation. Which of the below can help you while developing the charter?

Options:

A.

Strategic Alignment Analysis, Prioritization Analysis, Portfolio Component Inventory

B.

Prioritization Analysis, Interdependency Analysis, Cost-Benefit Analysis

C.

Scenario Analysis, Capability & Capacity Analysis

D.

Gap Analysis, Readiness Assessment, Stakeholder Analysis

Question 20

Assume you are the portfolio manager for your training company. It decided to implement portfolio management in a major way to ensure it remained competitive in the changing market and could offer a variety of methods to deliver courses rather than only in a face-to-face setting. The company set up a Portfolio Management Group, and you are responsible for providing information on portfolio status and then providing information to those interested stakeholders about the Board's decisions. You want to make sure the reports meet stakeholder requirements. After performing a detailed communications requirements analysis, you found it interesting that stakeholders wanted information about:

Options:

A.

Portfolio infrastructure costs

B.

Goal achievement

C.

Benefit realization

D.

Changes in the roadmap

Question 21

Your organization, a leading restaurant focusing on pancakes, is seeking to expand its portfolio. It is interested in ensuring new components support: return on investment, customer satisfaction, reputation enhancement, and branding. These four areas represent:

Options:

A.

Metrics

B.

Organizational value areas

C.

Organizational strategic objectives

D.

Critical success factors

Question 22

You are managing a portfolio linked to multiple business units and you set clear roles and responsibilities from the beginning to avoid delays and to enhance the decision making process. An unanticipated issue occurred last week, which relates to one of your team members missing to check the market fluctuating currency. In which of the following documents should you look to know which member was responsible of this?

Options:

A.

Strategic Plan

B.

Governance Model

C.

Risk Register

D.

Risk Roles & Responsibilities

Question 23

Assume before you prepared your portfolio management plan for your company that you did some benchmarking and learned that if you used elicitation techniques it was useful in the portfolio development stage and before there were significant scope changes because of strategy changes to the portfolio. You decided to involve the Portfolio Review Board members, other key stakeholders, and some subject matter experts in this process and then decided to poll input from the group as a majority vote. This meant you were using:

Options:

A.

Collaboration techniques

B.

Facilitation techniques

C.

Interviews and observations

D.

Negotiation techniques

Question 24

One of your team members came to you asking about the risk "Watch List"; he heard this term in a meeting on risk analysis and did not know what it meant. What will your advice to your team member be?

Options:

A.

Watch Lists include the risks with low probability and low impact that do not require further analysis

B.

Watch Lists include the risks with low probability and high impact that needs to be watched closely

C.

Watch Lists include the risks with high probability and low impact that needs to be watched closely

D.

Watch Lists include the risks with high probability and high impact that needs to be watched closely

Question 25

Your team members were having a discussion about the contents of the Portfolio Charter and they came to you for advice because they could not agree on a common answer. What would be your advice to them?

Options:

A.

Portfolio structure, scenario analysis, capability and capacity analysis

B.

High-level scope and high-level timelines, critical success criteria and justification

C.

Scope and timelines, all success criteria and justification

D.

Scenario analysis, capability and capacity analysis

Question 26

You are managing a portfolio for a major car dealer in the region and due to diversity of locations, funding terms and your client's corporate structure, you have a big number of components to be included in the portfolio. With such a huge number, you need to prioritize the components in order to prepare the mix of components to execute. Where can you find the prioritization model?

Options:

A.

Portfolio Strategic Plan

B.

Portfolio Charter

C.

Portfolio Roadmap

D.

Portfolio Risk Management Plan

Question 27

Your company is currently on the verge of bankruptcy due to the lack of transparency within the organization; this alerted the CEO to take decisive actions and request that new reporting lines be established in order to be fully transparent. Following this, the portfolio structure has changed to cope with the new reporting lines. Where is this change reflected when it comes to portfolio documents?

Options:

A.

Portfolio Charter updates

B.

Portfolio Strategic Plan updates

C.

Portfolio Management Plan updates

D.

Portfolio Roadmap updates

Question 28

You are managing a portfolio in a functional organization and resources are shared between operations and projects. You are continuously performing capability and capacity analysis in order to optimize the portfolio. Which of the following capability and capacity analysis is used to limit the number AND size of components the organization can execute?

Options:

A.

Financial

B.

Human Resources

C.

Knowledge Basis

D.

Assets

Question 29

As you grow older, you gain more experience and things that once seemed hard to assimilate, can become very easy. One junior member of your portfolio management team is confused on the relationship between the Optimize, Authorize and Provide Oversight processes. What could your advice to him be?

Options:

A.

The provide portfolio oversight process may trigger the other two processes as part of the review meetings

B.

The three processes are not related and are in different focus areas

C.

The Optimize portfolio comes first, then authorize portfolio and finally Provide Portfolio oversight

D.

The Optimize portfolio process is used to balance the portfolio so that the authorize portfolio and Provide Portfolio Oversight processes can start

Question 30

A problem related to internal corruption has occurred in your company. The CEO has setup a new management team and had to do budget cuts until the situation is stabilized. Your portfolio is highly affected by this budget cut and you were obliged to cancel a few components. What is your best course of action in this case?

Options:

A.

Cancel the components that are not performing well

B.

Do not cancel components; and request additional budget from the management

C.

Prioritize components and assign the available resources to them

D.

Raise the issue to the sponsor so he can get you additional resources

Question 31

Portfolios include a lot of work and as a portfolio manager you need to keep an eye on the value realization while maintaining the strategic alignment. You are currently aggregating value delivered by the portfolio components. What outputs do you expect to get out of this?

Options:

A.

Roadmap updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process Assets updates, Portfolio Component Reports updates

B.

Roadmap updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process Assets updates

C.

Roadmap updates, Portfolio Management Plan updates, Portfolio Reports, Portfolio Process Assets updates, Portfolio Strategic Plan updates

D.

Portfolio Reports, Portfolio Management Plan updates, Portfolio Process Assets updates

Question 32

You have been asked to be the manager for a governmental portfolio, and your starting point should be tendering a strategic plan to the board for validation and approval for continuation. Which documents/artifacts do you have debuting the portfolio that you can use to develop the strategic plan?

Options:

A.

Prioritization analysis, portfolio process assets, portfolio roadmap

B.

EEF’s, portfolio component inventory, organizational process assets

C.

Organizational strategy and objectives, inventory of work, portfolio process assets

D.

Portfolio charter, portfolio roadmap, organizational strategy and objectives

Question 33

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. For this you start by developing the strategic plan. What output do you expect from this process?

Options:

A.

Portfolio, Portfolio Strategic Plan

B.

Portfolio, Portfolio Strategic Plan, Portfolio Reports

C.

Portfolio, Portfolio Strategic Plan, Enterprise Environmental Factors updates

D.

Portfolio Process Assets updates, Inventory Of Work, Portfolio, Portfolio Strategic Plan

Question 34

One of the major resources on your portfolio is needed by two of the components at the same time. This resource has high technical knowledge and is aware of all the business needs. Which of the following tools and techniques can you use in order to solve this issue?

Options:

A.

Sequencing Techniques

B.

Capability and Capacity Analysis

C.

Scenario Analysis

D.

Interdependency Analysis

Question 35

As part of the Portfolio Communication, the Portfolio Manager analyzes the raw data assimilated from the portfolio process assets and from the stakeholder analysis. This analysis aims to isolate the data that hold value to the receiving audience. Which tool can the portfolio manager use to help him in performing this analysis?

Options:

A.

Communication Methods

B.

Elicitation

C.

Stakeholder Analysis

D.

Communication Requirements Analysis

Question 36

Portfolio Governance is important in a portfolio to maintain correct alignment, monitor and control performance and status, reshuffle the mix of components as found necessary, etc. Governance management includes which of the following processes?

Options:

A.

Develop Portfolio Communication Plan

B.

Optimize Portfolio

C.

Develop Charter

D.

Manage Supply & Demand

Question 37

Moving from project management to program management and now being appointed as the first portfolio manager in your cyber warfare company, you know you always wondered what happened to the various reports you had to prepare, and the metrics you had to collect. You are working now to determine critical metrics for portfolio management and decided to involve as many people as possible through questionnaires and surveys. You also held some focus groups. The purpose is to:

Options:

A.

Ensure the metrics that are collected support the SMART principle

B.

Maximize portfolio value

C.

Represent the vital few rather than the trivial many

D.

Can be gathered with minimal disruption

Question 38

Different types of risks affect the portfolio, and they may be positive or negative. As the portfolio manager, one has to maximize the opportunities and minimize the threats. An example of a negative portfolio risk is:

Options:

A.

External participants who are highly specialized

B.

Integrated systems

C.

A large number of concurrent programs and projects

D.

Full-cost estimates for programs and projects

Question 39

Assume you are helping the Portfolio Review Board select and implement the portfolio with the best alignment to strategy as you work to create a list for to be considered for prioritization. One possible component on the surface does not seem to be one that is profitable, but you believe that over time changes will occur that will make it cost/beneficial to pursue. This means you are using:

Options:

A.

Market analysis

B.

Business value analysis

C.

Scenario analysis

D.

Options analysis

Question 40

You are managing a portfolio linked to multiple business units and you set clear accountabilities from the beginning to avoid delays and to enhance the decision making process. Roles and Responsibilities are recorded in multiple portfolio documents. Where are the portfolio component managers roles and responsibilities stored?

Options:

A.

Specifically the Communication Management Plan

B.

Strategic Plan

C.

Portfolio Management Plan

D.

Portfolio Process Assets

Question 41

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team to attain the end goal and achieve the expected strategy. You are managing the strategic change and using multiple tools and techniques. What are they?

Options:

A.

Prioritization Analysis, Interdependency Analysis, Cost-Benefit Analysis

B.

Scenario Analysis, Capability & Capacity Analysis

C.

Gap Analysis, Readiness Assessment, Stakeholder Analysis

D.

Strategic Alignment Analysis, Prioritization Analysis, Portfolio Component Inventory

Question 42

While defining the portfolio mix, the portfolio manager performs a categorization of the portfolio components based on multiple categorization criteria. Which of the following is considered as a portfolio component category?

Options:

A.

Continuous Improvement

B.

Risk Reduction

C.

All of the options

D.

Process Improvement

Question 43

Risks perspectives differ within the organization between executive management, operations management, portfolio management and project/program management. When it comes to Operations management, which of the following is a risk concern?

Options:

A.

Issues with Product development

B.

Time to market

C.

Reporting and data accuracy

D.

Time, cost and scope commitments

Question 44

You have been managing a complex portfolio for the banking industry and it is sought to be the shifting to the top-notch digital banking era for one of the major international banks. You know you will have changes along the lifecycle and you plan to manage them correctly in order to maintain alignment and correct execution. If you need to reflect changes based on cost, requirements, and schedule. To which of the following section in the portfolio management plan will you refer?

Options:

A.

Performance management

B.

Manage strategic change

C.

Resource management

D.

Change control and management

Question 45

As a portfolio manager and in the aim of defining the preliminary list of components to be included in your portfolio, which will serve as a starting point for developing a portfolio. You start by identifying existing and potential portfolio components by reviewing documentation such as business plans/proposals in order to

Options:

A.

Create a basis for decision making

B.

Create portfolio scenarios

C.

Provide a guiding framework to operationalize the organizational strategic goals and objectives

D.

Understand the strategic priorities

Question 46

In a portfolio, data is an abundant asset, and managing the information aiming for a better decision making is critical. Information is considered to be the link between the portfolio activities and entities. You are currently collecting, analyzing, storing, and delivering portfolio information to stakeholders in accordance with their requirements. What can help you in doing this?

Options:

A.

Portfolio Roadmap, Portfolio, Portfolio Reports, Portfolio Management Plan, Portfolio Component Reports

B.

Enterprise Environmental Factors, Portfolio, Portfolio Reports, Portfolio Management Plan, Portfolio Component Reports

C.

Portfolio Process Assets, Portfolio, Portfolio Reports, Portfolio Management Plan, Portfolio Component Reports

D.

Enterprise Environmental Factors, Portfolio, Portfolio Reports, Portfolio Management Plan, Portfolio Strategic Plan

Question 47

Throughout the course of the portfolio lifecycle, components are initiated, terminated and updated. In order to be initiated, portfolio components receive go/no-go decisions during governance meetings. During which process the go/no-go decisions are taken?

Options:

A.

Review Meetings

B.

Provide Portfolio Oversight

C.

Authorize Portfolio

D.

Manage Strategic Change

Question 48

Assume you are a functional manager in your medical device company in research and development. Your scientists have determined a new product that will be a breakthrough for the company, and you want to serve as the sponsor for this component and present it to your Portfolio Review Board. You will need resources from other parts of the company to commercialize it. As you prepare your proposal you are following the key descriptors set up by the portfolio staff and will include:

Options:

A.

Risk reduction

B.

Regulatory and compliance issues

C.

Internal and external dependencies

D.

Qualitative benefits

Question 49

Risk Management is integrated in all the other processes and process groups and is an integral recurrent activity throughout the portfolio life cycle. Which of the following is considered the most effective method for analyzing the effect of risks on portfolio strategic objectives, and determining whether they have high or low effect

Options:

A.

Tornado Diagram

B.

Risk vs. Return charts

C.

Burn Down/Up charts

Monte Carlo Analysis

Question 50

As you focus on managing the value pf the portfolio, you find that portfolio variance/alert reports are helpful. Assume you have been using a 'traffic light' format as it is easy to prepare, but an objective is to:

Options:

A.

Add in blue to show completed components

B.

Show dependencies between components with a different color

C.

Set it up to show the organizational value areas in the company

D.

Use a standardized format across components

Question 51

Portfolio managers tend to use the efficient frontier analysis as a modeling approach that gives decision makers the analytical tool to optimize portfolios given resource constraints such as risk. In which of the Portfolio management processes the efficient frontier is mostly used

Options:

A.

Optimize Portfolio

B.

Manage Supply & Demand

C.

Manage Portfolio value

D.

Manage Portfolio Information

Question 52

As soon as you complete the portfolio risk management plan, and you have been working on it now with a team, you realize you need to update some organizational process assets such as:

Options:

A.

Risk checklists

B.

Risk register

C.

Lessons learned

D.

Risk interview guide

Question 53

Your sponsor has urged you to analyze Portfolio Risk before the end-of-week governance board meeting as the CEO will be present and is interested in Portfolio risk data in particular. Currently, you do not have adequate risk information in order to analyze data and give recommendations. Which tool is the most suitable for you to use in this case?

Options:

A.

Cumulative distribution

B.

Weighted Ranking and Scoring Techniques

C.

Delphi

D.

Graphical Analytical methods

Question 54

The interest, influence, and communication needs of business operational stakeholders who are looking to ensure alignment between portfolio components, while minimizing negative impact and maximizing positive benefits of all portfolio-managed changes to their business operations, relate to which type of stakeholders?

Options:

A.

Internal and External Stakeholders

B.

External Stakeholders

C.

Does not relate to stakeholders

D.

Internal Stakeholders

Question 55

Assume your telecom company is time constrained and needs to be first to market with new smart phones with features that are different from those of the competition and also have the traditional features desired by your existing customers. The Portfolio Review Board meets weekly to assess performance and to consider new components. Lack of technical resources is a recurring issue. To make the case for acquiring new resources, you decided to assess capability and capacity. This approach is:

Options:

A.

Part of the PMIS

B.

Included in finite capacity planning and reporting

C.

Used to prepare a detailed forecast of ongoing and future capability needs

D.

Used to identify resource capacity and capability

Question 56

While defining the portfolio, the portfolio manager uses a set of evaluation criteria in order to generate a list of portfolio components for optimization and balancing. Which of the following is not an evaluation criteria?

Options:

A.

Technology capabilities and capacities

B.

Costs

C.

Benefits, financial and non-financial

D.

Customer

Question 57

Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed. Which document do you, as a portfolio manager, update to reflect the change to the timeline?

Options:

A.

Communication Management Plan

B.

Portfolio Management Plan

C.

Portfolio Strategic Plan

D.

Portfolio Roadmap

Question 58

The portfolio manager defines the portfolio based on a listing of already existing work in the organization and selects the right components in order to be able to prioritize them. What do you use for defining the portfolio based on the listing of work?

Options:

A.

Prioritization

B.

Inventory of Work

C.

Portfolio Component Inventory

D.

Elicitation technique

Question 59

Strategies are changing, the portfolio mix is changing, the portfolio is progressing and you are doing a great job optimizing the mix of components. What tools and techniques are you using in the case?

Options:

A.

Weighted Ranking and scoring techniques, Portfolio Component inventory, Categorization

B.

Integration of Subsidiary Plans, Organizational Structure Analysis, Elicitation techniques

C.

Capability & Capacity Analysis, Weighted Ranking and scoring techniques, Graphical Analytical Methods, Quantitative & Qualitative Analysis, PMIS

D.

Capability & Capacity Analysis, Weighted Ranking and scoring techniques, Graphical Analytical Methods, Quantitative & Qualitative Analysis

Question 60

Your company has had a portfolio management process in place for five years at the enterprise level, in its business units, and even in its complex programs. This year the company's Center for Excellence received an award for its work in this area from PMI®. As the Portfolio Manager, you have predefined metrics in place, which are critical because:

Options:

A.

They show transparency at all levels

B.

They provide stakeholders with critical information on the health of the portfolio

C.

They show the link of each initiative to the company's strategic goals

D.

They provide insight into the processes being used

Question 61

The audit department has found out that two of the departments have conflicting standards and have asked you to analyze and compare them in order to be able to take a decision which could impact the portfolio alignment. Which analysis will you use to compare conflicting standards in different departments

Options:

A.

Capacity Analysis

B.

Force Field Analysis

C.

Qualitative Analysis

D.

Quantitative Analysis

Question 62

The company's management is not happy with the bared risk for the expected Portfolio value return and has reached a subject matter expert to try to re-align the risk level with the management expectations. The expert stated that it is preferable to diversify the portfolio components in order to get more results. In that case, you

Options:

A.

Disagree with the expert because the company should have came to you before reaching an outside-party

B.

Disagree with the expert because diversification will bring more complexity, thus more risks

C.

Agree with the expert because he is the expert and you should abide by his recommendations

D.

Agree with the expert because diversification in a portfolio may allow for the same portfolio expected return with reduced risk

Question 63

As part of developing the Communication Management Plan, a portfolio manager executes the Communication Requirements Analysis, in addition to Stakeholders Analysis. Which of the following options in your opinion is a result of the Communication Requirements Analysis?

Options:

A.

Stakeholder matrix

B.

Communication Matrix

C.

All of the options

D.

Communication Strategy matrix

Question 64

A junior Portfolio manager has come to you for advice. He is hearing a lot about the focus of portfolio management practices, however, he is not sure anymore of the exact answer. What do you, as an experienced portfolio manager tell him?

Options:

A.

Portfolio is undertaken to produce deliverables that support specific organizational objectives

B.

Portfolio is undertaken to achieve one or more organizational strategies and objectives

C.

Portfolio is undertaken to achieve benefits

D.

Portfolio is undertaken to handle operational daily activities

Question 65

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing risk is key to success and you continuously report risks and issues to stakeholders. One of the key stakeholders is furious as he cannot find an issue that has occurred a week ago in the risk register. What should you do in this case?

Options:

A.

Inform the stakeholder that risk that have occurred are removed from the risk register and not used anywhere else

B.

Inform the stakeholder that issues are risks that have occurred and are tracked as part of the issue register

C.

Inform the stakeholder that you will directly fix this and include it in the risk register

D.

Inform the stakeholder that when positive risks occur they become realized opportunities and when negative risks occur they become realized threats

Question 66

Assume you are the portfolio manager for the Federal Railroad Administration. Funding is provided annually according to the Government's budget process. Any monies that are not spent at the end of a fiscal year are lost, and there are some restrictions in place concerning whether funds can be transferred to different programs, projects, or operations work in the agency. Therefore, to maximize the use of funding you require:

Options:

A.

Regular reports on funds for authorized components

B.

Projections on a quarterly basis as to the funds components require

C.

Mechanisms for internal audits to ensure funds are allocated effectively

D.

Accurate estimates of the funds needed when the component is proposed for consideration

Question 67

The Strategic Plan is an important document that is referenced throughout the portfolio life cycle. Which of the following is correct regarding the Strategic Plan purpose and focus?

Options:

A.

Articulates the options, preferences, and factors that will be considered in a specific portfolio

B.

Describes the approach and intent of management in identifying, approving, procuring, prioritizing, balancing, managing, and reporting a portfolio

C.

Identifies recipients for information associated with the portfolio management process

D.

Shows how and when the portfolio resources will be planned, balanced, and allocated to the portfolio components

Question 68

One of the major steps for a portfolio manager is to know which components qualify to be included in the mix of components that will achieve the strategic objectives sought by the portfolio. As a program manager, you will use a variety of methods to help you achieve this purpose. Which of the following are valid tools and techniques?

Options:

A.

Capability & Capacity Analysis, Weighted Ranking and scoring techniques, Graphical Analytical Methods, Quantitative & Qualitative Analysis, PMIS

B.

Integration of Subsidiary Plans, Organizational Structure Analysis, Elicitation techniques

C.

Weighted Ranking and scoring techniques, Portfolio Component inventory, Categorization

D.

Capability & Capacity Analysis, Weighted Ranking and scoring techniques, Graphical Analytical Methods, Quantitative & Qualitative Analysis

Question 69

Multiple communication methods are used by the portfolio manager in order to proactively convey messages and engage the stakeholders at the right time and in the right manner. Which tool is used to visually convey multiple messages at the same time?

Options:

A.

Efficient Frontiers

B.

Dashboards

C.

Communication Calendar

D.

Resource sheets

Question 70

You have been assigned as the manager for a major transformation portfolio in your company. You have a new direction in sight and you need to work with the team handle this strategic change. Which of the following can serve as input here?

Options:

A.

Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Portfolio Process Assets, Organizational Process Assets

B.

Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Organizational Process Assets, Portfolio Management Plan

C.

Portfolio Strategic Plan, Portfolio Roadmap, Portfolio Charter, Portfolio Process Assets, Portfolio

D.

Portfolio Strategic Plan, Portfolio Management Plan, Portfolio Roadmap, Portfolio Charter,Portfolio Process Assets, Portfolio

Question 71

You are the portfolio manager in a large organization including a diversity of stakeholders. From the start, you knew the importance of correctly managing the stakeholders requirements and concerns and you grouped them in order to

Options:

A.

Group stakeholders as internal and external

B.

Facilitate stakeholders identification

C.

Group stakeholders from the same functional area

D.

Group stakeholders having same concerns and interests

Question 72

Consider you have the following efficient frontier graph with multiple portfolios on it. Which portfolio do you choose?

Larger image

Options:

A.

Portfolio D

B.

Portfolio B

C.

Portfolio C

D.

Portfolio A

Question 73

The portfolio undergoes a lot of changes through the portfolio life cycle, and the state of the portfolio changes on the go. Some components are terminated, other are added and initiated. When it comes to the authorize portfolio process, which of the following represents the state of the portfolio

Options:

A.

List of current components that need to be weighted, scored and ranked

B.

List of selected and balanced components

C.

List of strategically aligned portfolio components without the need for them to be balanced

D.

List of selected, balanced and authorized components ready to be initiated

Question 74

Having worked in portfolio management for several years, assume you were hired as the portfolio manager for a Real Estate Investment Trust, one of the largest in your country that specializes in apartments. The company continues to grow and wants to maximize value and profits for its investors. As you set up processes and procedures for portfolio management, you know from past experience that buy in from executives is insufficient. As you prepare a communications strategy, you focus on:

Options:

A.

Satisfying important information needs of stakeholders

B.

Surveying stakeholders through a questionnaire to determine information requirements

C.

Using focus groups to assist in determining information needs

D.

Focusing first on the executive team's communications requirements and then involving others

Page: 1 / 50
Total 495 questions