Summer Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMP Project Management Professional (PMBOK 7th Version) Exam Practice Test

Page: 1 / 220
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 1

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Question 2

A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer ' s standards

in order to ensure this, what should the project manager define and document?

Options:

A.

Quality

B.

Estimates

C.

Objectives

D.

Requirements

Question 3

A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules

Which two actions should the project manager take with regard to schedule analysis? (Choose two)

Options:

A.

Review with subject matter experts (SMEs) to ensure they have contributed to the schedule development

B.

Evaluate the master schedule and perform fast tracking and task crashing

C.

Look (or gaps in the different schedules to determine which major risks might evolve over time

D.

Review the project schedules to ensure that all tasks end with milestones

E.

Evaluate the schedules for interdependencies to establish the critical path

Question 4

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Question 5

A project manager is managing a hybrid project. During project execution, the project manager was informed that over half of the project budget was reallocated to a project that is handling an emergency that recently occurred.

What should the project manager do?

Options:

A.

Meet with the project sponsor to explain that the project cannot be completed as planned

B.

Meet with the technical lead to review the sprint plan

C.

Meet with the product owner to confirm the minimum viable product (MVP) option

D.

Meet with the project team and reprioritize the backlog

Question 6

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

Options:

A.

Confirmed that the communication was understood and solicited feedback from the team

B.

Sent the roles and responsibilities matrix along with the project management plan

C.

Discussed the roles with the managers to help explain them to their team members

D.

Briefed each team member on their roles before sending the project management plan

Question 7

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

Options:

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Question 8

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team ' s knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodologyfor consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Question 9

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

Options:

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Question 10

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Question 11

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

Options:

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

Question 12

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

Options:

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Question 13

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

Options:

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

Question 14

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Question 15

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

Options:

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Question 16

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Options:

A.

Inform the stakeholder that they must level their knowledge with other stakeholders.

B.

Update the risk register with the potential impact and apprise the steering committee.

C.

Inform the project management office (PMO) that the team will use a predictive approach for this project.

D.

Allocate time to mentor the stakeholder in the selected project approach.

Question 17

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

Options:

A.

Ask the team to solve the issue internally and review the underperforming resource ' s situation

B.

Meet with the team member privately to discuss the problem and work together to find a solution

C.

Contact the functional manager and request to replace the team member with a better resource

D.

Discuss various options to improve the team member ' s performance with their functional managers

Question 18

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Question 19

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Question 20

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member ' s lack of experience does not negatively impact the project?

Options:

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Question 21

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?

Options:

A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.

B.

Inform the senior manager that they will need a new project management plan for this feature,

C.

Complete the most current feature and release the resources for the new feature.

D.

Analyze the impact of this change and present the options to the senior manager.

Question 22

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Question 23

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Question # 23

Options:

Question 24

A project manager wants to make sure that similar projects in the future use the project ' s performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

Options:

A.

Share project documentation in a repository with exclusive access.

B.

Schedule weekly knowledge-sharing sessions with key stakeholders.

C.

Send periodic emails to senior management with the latest project updates.

D.

Keep project artifacts up-to-date and accessible to all stakeholders.

Question 25

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Question # 25

Options:

Question 26

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Question 27

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute toprojects.

B.

Assign employees to agile projects so they can quickly adjust to the new approach.

C.

Train all employees in agile approaches.

D.

Shift the way the company views, reviews, and assesses employees.

Question 28

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager ' s supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone

B.

Delay sending a formal communication until the project team catches up

C.

Ask for a meeting with the sponsor to decide whether to send the formal communication

D.

Forego the formal communication and have a conversation with the supervisor

Question 29

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization ' s project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Question 30

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

Options:

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

Question 31

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company ' s standard vendor selection criteria process,

Question 32

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government ' s cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurityrequirements.

Question 33

A few virtual team members are located in a region that generally has good internet connectivity. However, they frequently experience connectivity

issues joining team calls during the day.

What should the project manager do?

Options:

A.

Procure tools that consume less bandwidth for internet calls.

B.

Record the meeting to share with the team members who were unable to join.

C.

Ask the team members to use chat tools as an alternative to calls.

D.

Determine what the problem is and develop an action plan.

Question 34

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

Options:

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Question 35

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

Options:

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Question 36

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Question 37

A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?

Options:

A.

Have a high-level plan for incremental deliveries and get the customer ' s feedback as early as possible.

B.

Ask the sponsor for support regarding the allocation of additional resources to finish on time.

C.

Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources.

D.

Meet with the customer to agree on the components of the solution and the priorities.

Question 38

What should an agile lead do lo ensure their team is set up for success?

Options:

A.

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.

Schedule sprint meetings and coaching sessions to discuss project-related information

C.

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.

Document team tasks and challenges in order to understand when to step in and help a member of the team

Question 39

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Question 40

A protect manager is working with the team lo deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members causing negative consequences for delivery

How should the project manager avoid this situation in the future?

Options:

A.

Use the same methods until the end of the current delivery and suggest new ones during the retrospective.

B.

Refer to the policies and frameworks used at the company enterprise level and inform the project team members.

C.

Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.

D.

Agree with the project team on a suitable collaboration and make sure information is shared at all times

Question 41

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of everyiteration.

B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.

C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.

D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidentialinformation.

Question 42

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product ' s vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.

B.

Report the concern to the agile project management office (PMO),

C.

Inform the product owner of the concern so that i can be addressed.

D.

Open up to the team to work collaboratively to achieve the outcomes.

Question 43

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

Question 44

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

Options:

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Question 45

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

Options:

A.

Meet with the team to discuss compliance concerns

B.

Review the organizational process assets (OPAs) for compliance topics

C.

Review the compliance strategy and version history

D.

Meet with the project sponsor to discuss their compliance concerns

Question 46

A company has a transformation project in progress. During a planning session, several stakeholders are in constant disagreement and often use personal arguments to support their position. Team members are getting frustrated with the situation.

What should the project manager have done to avoid this situation?

Options:

A.

Established ground rules before the discussion had started.

B.

Asked stakeholders not to voice their opinions during the meeting.

C.

Invited a high-level sponsor to the meeting to reduce the level of disagreement.

D.

Reinforced that higher-level management has the decision power.

Question 47

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?

Options:

A.

Ask senior management to communicate with these departments.

B.

Hire a project management consultant to help resolve the issue

C.

Convince senior management to introduce rewards to resisting departments.

D.

Understand the user concerns and revisit the stakeholder engagement plan

Question 48

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Question 49

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Question 50

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

Options:

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Question 51

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?

Options:

A.

Reassign the task to another member of the team

B.

Support the team member by providing one more resource to complete the task immediately

C.

Ask the team member if there is an impediment and help to remove the blockers

D.

Keep the project sponsor informed about the delay

Question 52

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

Options:

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project ' s change control board (CCB),

Question 53

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team ' s performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Question 54

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

Options:

A.

Accept the change request from country A and reschedule the deployment project for country A.

B.

Take the request into account and ask the sponsor to inform countries B and C about the change

C.

Ask country A to submit a change request that will be analyzed along with countries B and C

D.

Refuse country As request as there is no time for the change as deployment has already begun

Question 55

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

Question 56

A project manager finds an unexpected issue halfway through a customer ' s protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Question 57

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager ' s first step in addressing the problem?

Options:

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan

B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis

C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge

D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Question 58

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Question 59

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project ' s quality management

D.

Determined a budget reserve for this project

Question 60

One of the project manager ' s important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.

Assess the risk register.

B.

Conduct project reviews.

C.

Perform retrospectives.

D.

Complete sprint reviews

Question 61

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization ' s project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Question 62

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Question 63

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Question 64

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Question 65

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

Options:

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Question 66

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member ' s recommendation.

B.

Reconcile the team member to the key stakeholder ' s recommendation.

C.

Escalate the communication concerns to the project management office (PMO) andrequest that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Question 67

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Question 68

A project team member is providing updates to assigned work and reports a task as complete, As the project progresses, it is observed that the task is not fully complete.

What should the project manager do moving forward?

Options:

A.

Provide clear expectations around task requirements.

B.

Review the task list with the team on a regular basis,

C.

Provide templates for the product owner to use in the future.

D.

Review the task with the sponsor to see if they are satisfied.

Question 69

A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

Question # 69

Options:

Question 70

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

Options:

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Question 71

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Question 72

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Question 73

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

Options:

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and culturalobservance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overallproject governance.

Question 74

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Question 75

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Question 76

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

Options:

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Question 77

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

Options:

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Question 78

A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?

Options:

A.

The project manager must ensure that the knowledge transfer occurred and that this is also included in the organizational process assets (OPAs),

B.

The project team members need to ensure they have supplied sufficient knowledge transfer.

C.

The project sponsor must ensure all knowledge transfer is completed before project closure.

D.

The stakeholders need to ensure they have received sufficient knowledge transfer for ongoing support after the project handover.

Question 79

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Question 80

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.

Evaluate demonstrated task accountability

B.

Determine the appropriate approach

C.

Analyze team member influence

D.

Identify levels of decision-making authority

Question 81

After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?

Options:

A.

Consult the risk and issue logs.

B.

Initiate a project change request.

C.

Create a baseline impact assessment

D.

Discuss with the project sponsor.

Question 82

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

Question 83

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

Options:

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Question 84

In the middle of a project, a business unit manager who regularly interacts with the project manager ' s team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.

After getting more information about the new manager, what is the project manager ' s next step?

Options:

A.

Contact the previous business unit manager to learn more about the new manager.

B.

Update the stakeholder register and the stakeholder engagement plan to include the new manager.

C.

Send the new manager a copy of the project charter to ensure the project objectives are understood.

D.

Schedule a meeting with the new manager to discuss the business analysis team ' s plans.

Question 85

The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?

Options:

A.

Reschedule the project execution date.

B.

Continue project execution using the current blueprints from the client.

C.

Escalate this issue to the project sponsor

D.

Consult with the client to determine if project execution should be continued.

Question 86

A project manager is leading a council ' s project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project ' s goal is to remain fully adherent to the council ' s values, policies, and procedures.

How should the project manager ensure project success?

Options:

A.

Enforce the project manager ' s authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project ' s implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager ' s objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Question 87

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

Options:

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Question 88

During the execution of a financial project, a project manager met with the project team weekly to evaluate the project ' s progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.

What should the project manager do first?

Options:

A.

Negotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase. ty

B.

Recommend to the sponsor that performance of the project be reviewed once per week.

C.

Review the communications management plan and submit a change request if required.

D.

Evaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.

Question 89

An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

B.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer

C.

Ask the customer to simplify the feature so that it can be implemented in one iteration

D.

Split the feature into smaller subfeatures. implement them, and then deliver them incrementally in multiple iterations

Question 90

A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.

What should the project manager do to initiate the adoption of agile within the company?

Options:

A.

Organize agile workshops with the developers and testers to gain their support in using agile approaches for their projects.

B.

Request that all the project managers and business managers receive training in the agile framework used previously by the project manager.

C.

Advise the PMO manager to continue with the company ' s current predictive approaches until all the projects in execution are closed.

D.

Assess the organization ' s culture to determine if agile can be used in project delivery and determine the practices to be used.

Question 91

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

Options:

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

Question 92

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

Options:

A.

Concentrate on the current project milestones.

B.

Update the project management plan for this new work.

C.

Develop a business case and submit it to the client.

D.

Make all the changes and then show the client the results.

Question 93

An operations manager continuously raises concerns about a project ' s benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this ' ?

Options:

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager ' s concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager ' s concerns in the risk register and assign actions to mitigate the risks.

Question 94

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

Options:

A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.

B.

Submit a change request to the financial manager to increase the funding and continue as is.

C.

Meet with the stakeholders to recommend the use of a time and materials (T & M) contract to address the problem.

D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.

Question 95

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.

Share the organization ' s decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.

Make a request to human resources for new team members who have agileexperience.

D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.

Question 96

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

Options:

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Question 97

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Question 98

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

Options:

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Question 99

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Question 100

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

Options:

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

Question 101

A project team ' s performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

Options:

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team ' s performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Question 102

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor ' s request because it is out of scope

D.

Validate the proposed change ' s impact on the project.

Question 103

A project manager decided to incorporate the latest technological advancement with the client ' s devices at no additional cost to the project.

Upon completion and submission of the project deliverables, the client rejected the devices, despite having the latest features.

What should the project manager have done?

Options:

A.

Incorporated the change within the scope of the project

B.

Reviewed the quality inspections

C.

Complied with the customer specifications

D.

Documented the technical reviews with the new change

Question 104

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Question 105

A senior management team member contacts an agile project lead and mentions

that certain features the senior manager thought would be in the current release were not

included. What should the agile project lead do?

Options:

A.

Assure the senior manager that these features will be queued up in the next sprint.

B.

Meet with the team to understand why the senior manager’s features were not included.

C.

Invite the senior manager to the next planning meeting.

D.

Send the product roadmap to the senior manager.

Question 106

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?

Options:

A.

Adjust the original budget estimates with the current cost variance.

B.

Negotiate the project changes and adjust stakeholder expectations.

C.

Perform a root cause analysis of the project performance.

D.

Review the activity duration to reforecast the project completion date.

Question 107

The project manager has recently received funding approval for a training program

for the entire project team but has not yet defined the most effective training course. One

team member submitted a request for specialized training that is required for the project.

How should the project manager handle this request?

Options:

A.

Send this change request to the change control board (CCB) for approval.

B.

Approve the request for the specialized training.

C.

Reject the request as it does not impact the project deliverables.

D.

Validate if the training is within scope and budget.

Question 108

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

Options:

A.

Assess the impact of the new requirements and initiate the change request process.

B.

Work with the product manager and the rest of the team to update the project backlog.

C.

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.

Follow the change management plan to update the risk register so It accounts for the added scope.

Question 109

A project manager is hired by a global company. The project manager is an agile specialist and is tasked with supporting the project team to reduce rework and dissatisfaction.

How should the project manager address these objectives?

Options:

A.

Decrease the scope of the portfolio and send new solutions to the customer.

B.

Deliver a schedule with the portfolio timeline and delivery to the customer.

C.

Adopt an incremental cycle of delivering value to the customer.

D.

Prepare deliveries with more details to satisfy the customer.

Question 110

A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.

How should the project manager address this issue?

Options:

A.

Modify the daily standup meetings to include project status reporting.

B.

Escalate the issue to the change control board (CCB) and ask for advice.

C.

Adopt the role of supporting and empowering the project team to do the work.

D.

Change the approach for the project to a predictive approach.

Question 111

At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.

What should have been done to avoid this situation?

Options:

A.

The acceptance criteria should have been properly defined in the contract

B.

The client requirements should have been clearly defined in the contract

C.

The Manage Quality process should have been appropriately conducted

D.

The project manager should have reviewed the standard industry defect rate

Question 112

On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner ' s requirements.

Who is responsible for analyzing the new requirement and making the final decision?

Options:

A.

Project manager

B.

Scrum master

C.

Project sponsor

D.

Product owner

Question 113

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Question # 113

Options:

Question 114

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

Options:

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

Question 115

A large company has agreed on a business case for an environmental project. The

project will cause some major changes in their operations, such as reduction in paper use,

which will obviously affect all of the users.

What is the first thing the appointed project manager should do?

Options:

A.

Evaluate the impact to the users and create a plan to address it.

B.

Inform users about the new changes and ask for their collaboration.

C.

Ask all managers to collaborate implementing this change to users.

D.

Start implementing the change so that users will eventually get used to it.

Question 116

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

Options:

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

Question 117

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

Options:

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Question 118

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

Options:

A.

Assess the stakeholder ' s needs and communication style and propose a tailored approach with regular status reports and progress meetings.

B.

Invite the stakeholder to the regular " show and tell " sessions so the stakeholder is aware of project progress and feedback can be gathered.

C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.

D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.

Question 119

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Question 120

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Question 121

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Question 122

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?

Options:

A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.

B.

Update the stakeholder register and risk management plan.

C.

Update the stakeholder register and revise the stakeholder engagement plan.

D.

Explain to the community members why they were not included as stakeholders for the project.

Question 123

A project manager is leading a virtual team that is geographically dispersed. What

should the project manager do to avoid uncertainty in the project due to different cultures?

Options:

A.

Start the project and add any uncertainty that arises to the risk register.

B.

Dissolve the virtual team and build a colocated team.

C.

Gather relevant cultural data and engage members in discussions covering their work ethics.

D.

Build a culturally neutral team that will not be affected by cultural differences.

Question 124

A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?

Options:

A.

Request the project sponsor prioritize and if necessary, allocate additional budget so the team can work on a single project

B.

Provide an incentive plan so the team members will work more unaccounted hours on multiple projects

C.

Brainstorm with the team members on how they can deliver on multiple projects within the given budget

D.

Instruct the team members to spread evenly across projects so mistakes will not occur within the current budget.

Question 125

A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.

Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.

The company asked the project manager to explain the value gained by using an agile process.

How should the project manager respond?

Options:

A.

Early value cannot be achieved until the product is fully released.

B.

Early value can be gained by testing the most important features in the initial stages to fix deviations.

C.

Early value will be gained only if beta products can be released to the market.

D.

Early value will be gained only if the speed can be increased to release the product to the market.

Question 126

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer ' s expectations. What should the project manager have been done

to prevent this situation?

Options:

A.

Involved the customer more in the planning process for the project, and ensuredagreement on the proceedings.

B.

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Question 127

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project ' s health?

Options:

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Question 128

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Question # 128

Options:

Question 129

An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager

do with many tasks still open on the Kanban board?

Options:

A.

Decompose the item immediately and begin work.

B.

Discuss the impact of starting the item with the team.

C.

Finish the small tasks in progress before decomposing the item.

D.

Communicate the impact with the project sponsor.

Question 130

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone ' s schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Question 131

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization ' s upper management.

What should the project manager do first?

Options:

A.

Review the benefits of the proposed changes in relation to the business case.

B.

Assess the time overrun, and start implementation to avoid additional delays.

C.

Request a provisional budget increase to avoid any budget overruns.

D.

Motivate the team to avoid the frustration of working on a prolonged project.

Question 132

Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)

Options:

A.

Host a special meeting to talk about what happened.

B.

Escalate the issue to human resources (HR).

C.

Review the lessons learned document with the team.

D.

Conduct a team-building workshop.

E.

Discuss this incident in the project review meeting.

Question 133

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

Options:

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Question 134

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if theproject deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestonesare achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high untilthe end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of theproject and recognize the work of the team.

Question 135

An events company is planning their annual event for a retirement fund. The organization has run the event planning using agile approaches for the last 3 years. During the initiation phase, while assessing possible risks and improvements for the event, the project manager uses previous event feedback to assist in developing the risk register.

Which ceremony should be used in developing this register?

Options:

A.

Sprint plans

B.

Retrospective results

C.

Sprint report

D.

Project status report

Question 136

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

Options:

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Question 137

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.

Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.

What should the project manager do next?

Options:

A.

Escalate the issue to a higher authority.

B.

Suspend the two key team members immediately.

C.

Put the issue on the agenda for the next team meeting.

D.

Reassign one of the key team members to a different task.

Question 138

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern ' s mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Question 139

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member ' s concerns?

Options:

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

Question 140

A year after implementing a policy change to improve diversity and inclusion within two teams, there is increasing conflict within the company What should have been done to prevent this conflict?

Options:

A.

The organization should have introduced the concept of diversity broadly

B.

The leadership team should have worked closely with the marketing team to get insight on diversity

C.

Organization-wide diversity training should have been provided to the workforce

D.

The critical departments in the organization should have been involved in this exercise

Question 141

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

Options:

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

Question 142

A team has been consistently delivering outcomes. However, based on their current performance, it was discovered that their velocity has decreased by 30%.

What should the project manager do to ensure the velocity is under control?

Options:

A.

Ask the product owner to look at a minimum of four to eight iterations and replan the velocity for the next iteration based on the team ' s current performance.

B.

Ask the scrum master to plug gaps in the team ' s performance by adding a team member to compensate for the velocity decrease.

C.

Request that the team improve their cycle time to compensate for the velocity decrease.

D.

Request the team to improve the lead time, cycle time, and response time individually and track closure.

Question 143

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

Options:

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Question 144

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

Options:

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager ' s understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Question 145

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

Options:

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Question 146

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

Question 147

A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner ' s expectations.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps

B.

Performed risk management analysis during daily scrums

C.

Reviewed the organizational process assets (OPAs) and lessons learned from similar projects

D.

Performed backlog grooming to ensure that acceptance criteria were being met

Question 148

An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager ' s organization is engaged in an internal project, project B, that is about to end.

What should the project manager do?

Options:

A.

Prioritize project A over project B since A is an external project and B is an internal project.

B.

Plan projectA in sprints, starting with the module that does not require machine learning skills.

C.

Engage the human resource manager to employ a machine learning expert for project A.

D.

Plan project A to start at the end of project B when the machine learning expert is available.

Question 149

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Question 150

A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings

What should the project manager do?

Options:

A.

Ask the individual who is hosting the event to use private communication methods.

B.

Set up a meeting with the distracted team member to discuss any issues

C.

Add a social events section to the charter to handle these situations

D.

Ask the individual who is hosting the event to mark it as private

Question 151

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

Options:

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Question 152

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Question # 152

Options:

Question 153

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Question 154

A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.

What should the newly assigned project manager do first to understand the issues?

Options:

A.

Escalate the issues to the project sponsor.

B.

Review the issues log to ensure the issues are captured.

C.

Check the risk management plan to ensure there is a strategy to address the issues.

D.

Ask the key stakeholders to discuss the issues with the project team.

Question 155

At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team ' s productivity.

What should the project manager do next?

Options:

A.

Ask the product owner to speak with the functional managers to ensure future requirements come through the product owner.

B.

Log this as a risk in the risk register and continue to monitor the issue at subsequent meetings.

C.

Address this concern with the functional managers to ensure there will be no further delays.

D.

Schedule a meeting with all of the functional managers to resolve the resource conflicts.

Question 156

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder ' s final product.

D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Question 157

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

Options:

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

Question 158

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

Options:

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

B.

Continue to work on the project until the stakeholders and management come to a decision.

C.

Socialize with the stakeholders to better understand their needs and reset expectations.

D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

Question 159

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder ' s engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Question 160

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

Options:

A.

Request the team member to move to another team.

B.

Delegate other team members to complete this team member ' s tasks.

C.

Mentor the team member and provide the necessary training.

D.

Include this team member in an improvement program through a human resources request.

Question 161

An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.

What should the project manager do?

Options:

A.

Ask the sponsor to approve inclusion of an additional iteration to the project

B.

Ask the team to include the contingency plan in the iteration backlog

C.

Help the team review the project approach to initiate the corrective actions

D.

Ask the sponsor for money to implement the contingency plan.

Question 162

A project sponsor receives project information and updates in a timely manner, but

the sponsor is concerned because key information is missing in the reports. What should the

project manager do?

Options:

A.

Review the communication needs of key stakeholders.

B.

Confirm that the project information is understood and feedback is received.

C.

Determine communication methods, frequency, and level of detail.

D.

Provide all project information to the stakeholder.

Question 163

A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

Options:

A.

Ensure that relevant stakeholders and expectations are identified and assess the component delay.

B.

Perform a detailed analysis of the release content for each component of the solution.

C.

Propose a new design of the solution to replace the external component with an internal one.

D.

Ask for expedited delivery of the component to mitigate the risk of schedule delays.

Question 164

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

Options:

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team ' s agile maturity.

D.

Support the team members ' growth and development.

Question 165

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

Options:

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

Question 166

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

Options:

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Question 167

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

Options:

A.

Reach an agreement with the team on how to handle the situation.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Convince the team member not to leave until the project is completed.

Question 168

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of

the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that

quality has been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

Options:

A.

Show the customer the tolerance and control limits.

B.

Show the customer sample results from the current batch.

C.

Show the customer a sample history of quality.

D.

Show the customer the quality control measurements.

Question 169

A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team

interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Video conferencing

C.

Encrypted emails

D.

Chat conversations

Question 170

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the protect manager do?

Options:

A.

Perform quality control analysis.

B.

Perform root cause analysis (RCA).

C.

Perform trend analysis.

D.

Perform schedule analysis.

Question 171

A project team member is sick and will not be able to return to the project for a few weeks. During the daily meeting, the team shares their concerns as the sick team member was the only one skilled in the component they were developing.

What should the project manager have done to prevent this?

Options:

A.

Requested robust documentation for the component ' s build.

B.

Outsourced development of the specific component to another team.

C.

Acquired more than one resource skilled in each component.

D.

Facilitated cross-functional knowledge transfer during the project.

Question 172

A website application project is underway and the agile team has reached a stable velocity. After eight iterations, they complete 20 story points per sprint. The project lead and team plan to maintain the same velocity for the next 2 months. After this period, the team completed 100 story points. The project sponsor asks for the project status.

How should the project lead respond?

Options:

A.

The cost performance index (CPI) is below average with a 25% reduction.

B.

The schedule performance index (SPI) is 25% less than expected.

C.

The team ' s performance indicator is higher than expected.

D.

The cost and schedule performance indicators are equivalent.

Question 173

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?

Options:

A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.

B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.

C.

Invite the PMO manager to the daily standup with the project team and product owner.

D.

Send weekly reports to all stakeholders, including the project team and the product owner.

Question 174

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the

importance of this document to the project manager?

Options:

A.

Needed to close the work breakdown structure (WBS).

B.

Needed to share it with the stakeholders.

C.

Needed to close out the project or a phase.

D.

Needed to release the team at the end of the project.

Question 175

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?

Options:

A.

Register an issue and escalate it to the project sponsor.

B.

Invite the stakeholders to discuss a new prioritization.

C.

Estimate the management to replace the customer service manager.

D.

Increase the team capacity to finish the project on time.

Question 176

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

Options:

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.

C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.

D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.

Question 177

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

Options:

A.

Ask the new team member to focus only on development and not do the testing.

B.

Coach the new team member to conduct the testing the way it has always been done for this project.

C.

Schedule a meeting with the new team member to learn about the new method of testing.

D.

Request that the new team member do the testing the way it has always been done for this project.

Question 178

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

Options:

A.

Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

B.

Instruct the team to make only a graphical representation of all the data for the report.

C.

Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

D.

Instruct the team to analyze and interpret the data before including it in the report.

Question 179

A project manager is managing an agile project for the first time. Early on, the project manager discovers the team is struggling to agree on the scope of a feature during a sprint.

How should the project manager help the team resolve the issue?

Options:

A.

Direct the senior-most member to determine the scope on behalf of the team.

B.

Discuss this with the team and decide what the scope of the feature should be.

C.

Ask the team to log the story in the product backlog and move on to the next feature.

D.

Encourage the team to collaborate to resolve their understanding of the feature.

Question 180

A project stakeholder complained that they did not receive an important delivery that was stated in the schedule. The team member responsible for this deliverable explained that they sent an email to the stakeholder, advising them that the deliverable would not be delivered on time.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that the team member did not communicate directly with the project stakeholder.

B.

Confirmed that the stakeholder was made aware of the delivery delay.

C.

Told the team member to send the unfinished deliverable to the stakeholder and finalize it later.

D.

Communicated with the stakeholder directly regarding the delivery delay.

Question 181

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

Options:

A.

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.

Schedule meetings with all of the stakeholders to make business decisions when needed.

Question 182

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.

What should the project manager do?

Options:

A.

Request all of the business areas to plan for a portion of the benefit equally and include it in their staffing plans.

B.

Set up a stakeholder session with all teams to agree and document the benefits and establish ownership.

C.

Ask the project sponsor for approval to distribute the project benefits equally to the business areas.

D.

Ask the project sponsor to make a decision on who will own the benefit and document the decision.

Question 183

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager ' s location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

Options:

A.

Request a budget extension to get local resources experienced in agile.

B.

Plan to have the agile resources temporarily relocate to the project manager ' s location.

C.

Engage the agile resources through video conferencing on a daily basis.

D.

Advise the sponsor that the project will be delayed as agile training will be required.

Question 184

During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule. What should the project manager do?

Options:

A.

Replace the team member with another available resource on the team.

B.

Discuss the situation with the team member ' s functional manager to see if the schedule can be adjusted.

C.

Check with the project management office (PMO) on the available resources to complete the activities.

D.

Encourage the team member to prioritize scheduled project activities.

Question 185

A project manager is reviewing several potential changes to the contract with third-party vendors.

Which two changes could trigger a modification to the vendor contractual obligations? (Choose 2)

Options:

A.

Adding new resources to the change control team

B.

Adding vendors to increase flexibility and availability of work crews

C.

Introducing additional requirements based on new regulations

D.

Modifying a supplier ' s name due to a vendor acquisition

E.

Replacing a material type based on product availability

Question 186

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins

to identify, evaluate, and categorize the stakeholder relationships to the program.

What is the purpose of this process?

Options:

A.

Identify all stakeholders who can negatively affect the project.

B.

Incorporate the needs of all stakeholders into the communications management plan.

C.

Incorporate only primary stakeholders into the communications management plan.

D.

Identify all stakeholders who can positively affect the project.

Question 187

A project manager has completed an assessment of the project team ' s performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?

Options:

A.

Develop different approaches based on team members’ motivation and ability.

B.

Develop a standard approach to provide feedback to all team members.

C.

Provide intensive oversight to the team members who performed poorly.

D.

Create a new standard performance measure based on project requirements.

Question 188

A project management office (PMO) is currently stretched for project control resources. Specifically, the cost control resources are short of the staff required for this activity level. A new project is about to start soon.

What should the project lead do to obtain the needed resources?

Options:

A.

Evaluate running the project without the required resources and depend on the lessons learned from similar past projects.

B.

Prepare to perform the duties of the cost controller for the duration of the project.

C.

Meet with the PMO team and review the resource management plan ahead of the project kickoff to ensure resource availability.

D.

Inform the project sponsor and initiate a recruitment exercise outside of the PMO.

Question 189

In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.

Match the project manager ' s goals on the left with the relevant risk parameter on the right.

Question # 189

Options:

Question 190

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

Options:

A.

Create a framework to justify project execution.

B.

Utilize an agile approach for all upcoming projects.

C.

Create a framework to support project success.

D.

Utilize a predictive approach for all upcoming projects.

Question 191

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated

by other team members.

Which three actions should the project manager take? (Choose three)

Options:

A.

Arrange and conduct team-building sessions to improve team effectiveness.

B.

Allow team members to resolve personal issues without involving the project manager.

C.

Get feedback from other team members to understand what led to this situation.

D.

Identify the isolated team member as a risk and document the situation in the risk register.

E.

Obtain feedback from the isolated team member to understand the situation.

Question 192

A company is about to start a complex research project. Due to the level of uncertainty, the project manager recommends the use of a hybrid approach; however, the organization only has experience with predictive projects.

How can the project manager strategize the use of a hybrid approach to the organization?

Options:

A.

Present the benefits of a hybrid approach to key stakeholders to get their support.

B.

Create a project change request to execute the project using a hybrid approach.

C.

Send a letter to the project management office (PMO) requesting to use a hybrid approach.

D.

Submit a notification to the project team confirming they will be using a hybrid approach on the project.

Question 193

A project manager is working on a unique project that is dissimilar to the project nature of the organization. The project manager is tailoring the artifacts for this new project.

Who should determine which artifacts should be used in the project?

Options:

A.

The project sponsor should select the project artifacts that the project manager and project management team should use in the project.

B.

The project manager and project management team should use the standard project artifacts from the database.

C.

The project stakeholders should meet and determine the project artifacts to be used by the project manager and the project management team.

D.

The project manager and the project management team should select the appropriate artifacts for use in the specific project.

Question 194

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

Options:

A.

Counsel both team members and caution them with a final warning.

B.

Escalate the issue to the human resources (HR) manager before a larger problem develops.

C.

Help cultivate self-awareness between the two team members through emotional intelligence (El).

D.

Relocate the two project team members into different project teams.

Question 195

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no

longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects,

and there is no capacity for any developer to take on additional work.

What should the project manager do next to fulfill this resource need?

Options:

A.

Determine resource allocation options based on project priority.

B.

Apply changes to the existing resource allocations and inform the development manager.

C.

Meet with the sponsor to determine how to rebaseline the schedule.

D.

Inform the sponsor of the situation and request an extension of the target completion date.

Question 196

After a recent status review meeting, the project manager becomes aware that an influential stakeholder is unclear about the purpose and benefits of the project Consequently, the stakeholder has questioned the viability of continuing the project What should the project manager do next to address the situation?

Options:

A.

Speak with the project sponsor to find out if the stakeholder would agree to a one-on-one review session

B.

Log the stakeholder ' s comments in the risk register as a high-impact threat to the project ' s completion

C.

Consider the stakeholder ' s concerns and review the project charter with the project sponsor.

D.

Note the stakeholder ' s concerns but disregard them with regard to the project activities.

Question 197

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team

member ' s deliverables do not meet the requirements.

What should the project manager do first?

Options:

A.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables aresubmitted.

B.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework thedeliverables.

D.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

Question 198

During daily team standup meetings, team members constantly ask about which tasks they should focus on first. How should the project

manager ensure the team is fully productive?

Options:

A.

Review the project backlog during the team ' s standup meeting.

B.

Encourage project team members to prioritize the product backlog.

C.

Ensure team members are working according to the project plan.

D.

Work with the product owner to ensure the project backlog is prioritized.

Question 199

A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.

Which tool should the project manager use?

Options:

A.

Retrospective meetings

B.

Daily meetings

C.

Kanban board

D.

Gantt chart

Question 200

During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal

impact on project resources. However, the client has only been focused on the next milestone.

How should the project manager approach this situation?

Options:

A.

Apply additional resources to realize the early deliverable and ensure the next milestone is achieved.

B.

Focus on the deliverable of the next project milestone as per the client ' s strict instructions.

C.

Review the change management plan to discuss early benefits realization with the client.

D.

Evaluate whether the client ' s request will add extra features to the project deliverable.

Question 201

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

Options:

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

Question 202

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?

Options:

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor ' s facility to eliminate extra work on-site.

Question 203

A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?

Options:

A.

Follow the requirements management process.

B.

Follow the stakeholder engagement process.

C.

Follow the risk management process.

D.

Follow the change management process.

Question 204

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner ' s recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Question 205

An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.

How can the project manager ensure that the appropriate acceptance criteria are applied to the features?

Options:

A.

Define the acceptance criteria and specific functional test cases only after analyzing the user feedback from testing the early feature release.

B.

Integrate the acceptance criteria review into the definition of ready (DoR) for each feature and associated tests into the feature ' s definition of done (DoD).

C.

Use the broadest set of acceptance criteria to ensure that all features have a common quality baseline and associated functional test cases.

D.

Integrate the specific tests into the definition of ready (DoR) for each feature and the acceptance criteria into the feature ' s definition of done (DoD).

Question 206

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

Options:

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Question 207

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Question 208

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Options:

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

Question 209

During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project

kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.

What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

Options:

A.

Develop a stakeholder-by-stakeholder engagement assessment matrix.

B.

Send a letter to the stakeholders to inform them about the project scope and start date.

C.

Schedule meetings with key stakeholders in advance to gather feedback on the project scope.

D.

Identify stakeholder rejection as a risk in the project risk register.

Question 210

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

Options:

A.

Product roadmap

B.

User stories

C.

Business requirements document

D.

Product backlog

Question 211

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?

Options:

A.

Reject the changes and stay the original course as initially agreed with the client.

B.

Review the changes and make the decision based on the project team ' s recommendations.

C.

Discuss the changes with the client and jointly make the decision on how to proceed.

D.

Review the risk register to see if mitigations have already been outlined for this scenario.

Question 212

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two)

Options:

A.

Discuss the issue with the external supplier ' s authority.

B.

Review the lessons learned from similar past projects.

C.

Gather additional information and estimate the impact.

D.

Update the risk log and bring this up in the meeting with the client.

E.

Wait for the client to raise a concern and collect more information.

Question 213

A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two

projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.

What kind of leadership style should the project manager utilize for the current project?

Options:

A.

Transformational

B.

Interactional

C.

Laissez-faire

D.

Charismatic

Question 214

A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project

manager knows this team member could add value to the project.

What should the project manager do to get the most value from this team member?

Options:

A.

Advise the team member not to share personal information from past projects with the entire team.

B.

Consult with the project sponsor to find out if it is allowed to share personal information with the entire team.

C.

Advise the team member to focus on the current project and consider the past conflicts as lessons learned.

D.

Consult with human resources (HR) and check company policies on what is allowed to advise the team member.

Question 215

A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.

What should the project manager do next?

Options:

A.

Discuss extending the mass production timeline by 3 months with the project sponsor.

B.

Meet with senior management to discuss the possibility of an extension to the project timeline.

C.

Engage a consultant to shorten the certification process to meet the schedule requirement.

D.

Assess and evaluate the certification process and understand the best and worst case scenarios.

Question 216

A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a

successful project completion?

Options:

A.

Update the project management plan to reduce the possibility of scope creep.

B.

Schedule a regular risk review with the project management team.

C.

Increase the active engagement and participation of key stakeholders.

D.

Create a project change roadmap to keep track of all unforeseen changes.

Question 217

A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.

What should the project manager do to select the most effective project framework?

Options:

A.

Adopt an agile framework to agree with the project sponsor.

B.

Perform a market evaluation with key stakeholders and determine the best approach.

C.

Evaluate project characteristics with the project team and adopt the most suitable framework.

D.

Suggest using a hybrid approach to the sponsor for project execution.

Question 218

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company ' s newest offering. The project manager learns that the company ' s main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor ' s offering is better in multiple ways compared to the project manager ' s project.

What should the project manager do?

Options:

A.

Perform a Kano analysis factoring in the competitor ' s offering and present it to the stakeholders.

B.

Meet with the development team to see what changes will improve the project compared to the competition ' s deliverable.

C.

Meet with the project team to discuss the concerns and determine how to ensure the project ' s deliverable can compete with the competitor ' s.

D.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor ' s offerings.

Question 219

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

Options:

A.

The customer ' s requirements should have been captured in order to meet the customer ' s standards.

B.

The iteration review planning meeting should have been planned accordingly.

C.

The sprint retrospective meeting should have included necessary stakeholders.

D.

The customer ' s requirements should have been captured and modified to meet the supplier’s standards.

Question 220

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Options:

A.

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Question 221

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

Options:

A.

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.

Continue the meeting and use facilitation techniques to improve communication within the team.

Question 222

In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project

manager do next?

Options:

A.

Produce a value-added product for the customer as continuously as possible.

B.

Produce a value-added product for the customer in the beginning of the project.

C.

Produce a value-added product along with the supporting documentation.

D.

Produce a value-added product for the customer in each phase of the project.

Question 223

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

Options:

A.

Business Documentation

B.

Stakeholder Register

C.

Risk Register

D.

Project Charter

Question 224

A project manager is managing a project that requires specialized architecture services. This project was identified as a high risk for the

organization. The project manager works with an external architect who is highly specialized. However, the architect will soon resign because they

accepted an offer from another firm.

What should the project manager do next?

Options:

A.

Discuss this with the project team, assess the impact, and decide on the appropriate actions to follow.

B.

Ask the architect for the contact details for their new employer and call their account manager.

C.

Call the account manager and ask them to retain the expert by offering them an incentive.

D.

Escalate the issue to the procurement department and ask them to discuss this with the vendor firm.

Question 225

A project lead is working on an agile project to build the team ' s vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

Options:

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Question 226

A project manager is leading a project that has a dependency on the client ' s vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

Options:

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.

Review the terms of reference of the steering committee to include the vendor management head.

C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Question 227

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member ' s reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?

Options:

A.

Assign the task to someone else on the team.

B.

Discuss it with the team member in confidence.

C.

Discuss this matter during the project meeting.

D.

Include this item in the risk register.

Question 228

A project manager is tasked with developing a coaching model to support and recognize team members ' growth.

What should the project manager consider when defining their coaching strategy?

Options:

A.

Established patterns of communication

B.

Organization ' s strategic goals

C.

Individual and personal objectives

D.

Project team ' s shared objectives

Question 229

There is a conflict on an agile project about following organizational processes, many of which do not add any value to the project. To resolve this, which one of the following

should be regarded with the highest priority?

Options:

A.

Needs of the customer

B.

Needs of the project manager

C.

Needs of the agile lead

D.

Needs of the organization

Question 230

A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.

How should the project manager address this situation?

Options:

A.

Distribute the release plan among the team members.

B.

Ask the team members to focus only on their assignments.

C.

Ask the product owner to clarify the project ' s vision with the team.

D.

Meet with the product owner to validate the backlog prioritization.

Question 231

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

Options:

A.

Continue the iteration and add the requested changes.

B.

Continue the iteration and review the change with the customer.

C.

Cancel the iteration and meet with the product owner.

D.

Cancel the iteration and add the requested changes.

Question 232

A project with a geographically distributed team is ending its first iteration out of eight. During the daily meetings, the project manager realizes that some team members are not engaging in the discussion.

What should the project manager do?

Options:

A.

Conduct a team activity to determine the reasons for this situation.

B.

Speak with the team to find a better time to hold the meeting.

C.

Ask the team members to speak during the meetings.

D.

Update the risk log and follow the team members ' performance.

Question 233

A new file vault system vendor is being considered by a protect sponsor who has supported several projects over the previous year What should the project manager review to assist the sponsor on the decision?

Options:

A.

Lessons learned database

B.

Procurement strategy

C.

Vendor ' s website

D.

Appropriate financial regulations

Question 234

The scope of a project is to replace the street signs within a 10-km radius. The client does not want to sign the project closure report if the radius

is not extended by 1 km, to be aligned with the council ' s development plan.

What should the project manager do?

Options:

A.

Delay the approval and ask the project sponsor for additional funding.

B.

Contact the council and ask for their approval to extend the scope of the project.

C.

Initiate a new project and discuss the request because it came in too late.

D.

Obtain formal acceptance for the completed work and submit a change request.

Question 235

In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.

What should the project lead do?

Options:

A.

Ask the developer to postpone the leave until the backlog item is delivered.

B.

Ask the development manager to provide a replacement for a couple of days.

C.

Work with the product owner to change the priorities in the sprint backlog.

D.

Work with the product owner to inform the users that the feature is delayed.

Question 236

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.

Add 4 additional weeks to the schedule and request additional resources.

B.

Ask the sponsor to obtain a special work permit to continue work.

C.

Review the project management plan to see the impact of the possible delay.

D.

Crash the resource management plan to keep the schedule on track.

Question 237

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

Options:

A.

Ask the project team to review and modify all of these reports.

B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.

C.

Explain to the stakeholder that these are the approved templates for the reports.

D.

Ensure that the reports comply with the communications management plan.

Question 238

A project manager is working on a software development project for an oil and gas client using an agile approach. The project manager is having difficulty preparing the schedule because the project has various unknowns.

Which scheduling method should the project manager use to develop the schedule?

Options:

A.

Iterative scheduling

B.

Three-point scheduling

C.

Parametric scheduling

D.

Analogous scheduling

Question 239

A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the

importance of the project meeting the company ' s strategy, investment, and compliance requirements.

What should the project manager do?

Options:

A.

Replicate the organizational governance to the project governance.

B.

Put into place a project governance model in line with the requirements.

C.

Create an organizational project management governance.

D.

Ask the organization to create a project portfolio governance.

Question 240

A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.

How should the project manager recognize high performance?

Options:

A.

Thank the team member privately to avoid conflict among the team members.

B.

Acknowledge the high-performing team member in the next team meeting.

C.

Choose a reward for the team member that aligns with their personal goals.

D.

Ask the sponsor to approve a bonus for the high-performing team member.

Question 241

A project manager is leading a project team that consists of five team members. One of the team members, a senior technical staff member, always criticizes the ideas of other members during team meetings. However, this senior technical member is not performing well on their own daily tasks. Other team members are frustrated and have become silent in meetings.

What should the project manager do?

Options:

A.

Reduce the team meeting frequency and seek input separately from team members.

B.

Ask human resources (HR) to reassign the senior technical staff member.

C.

Encourage other team members to provide one another with their valuable ideas.

D.

Provide feedback to bring the team members ' focus back to the performance of their daily tasks.

Question 242

During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to

be involved in the regular project communications and reporting cycles.

What should the project manager do?

Options:

A.

Ask the project team members to include the manager in all of their communications regarding this project.

B.

Inform the manager that only stakeholders identified in the communications management plan should be involved.

C.

Perform a stakeholder analysis and update the communications management plan to reflect the new situation.

D.

Suggest the manager contact the steering committee and project management office (PMO) to be included.

Question 243

A project team has finished its first iteration out of six. The iteration ' s delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

Options:

A.

Update the issue log and escalate it to the project sponsor.

B.

Meet with the team to review internal actions to resolve the situation.

C.

Ask the technical manager to help the team with the issue.

D.

Ask to replace some team members with more experienced ones.

Question 244

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

Options:

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Question 245

After conducting a performance assessment, the project manager identified that some gaps still exist. What should the project manager ensure?

Options:

A.

Assessment results are kept private and not shared among team members.

B.

Performance improvement programs are organized for all team members who were assessed.

C.

All team members rotate their job schedules immediately to make them versatile.

D.

Awards are given to all team members for playing a role in the project and undertaking the assessment.

Question 246

A company wants to show the commercial advantages of a product in a competitive market. They commissioned a project team to create a prototype. The team is building the prototype incrementally.

What should the project manager set as a priority?

Options:

A.

Implement the plan-do-check-action (PDCA) cycle.

B.

Deliver business value as soon as possible.

C.

Emphasize the use of Kanban methods.

D.

Ensure that the project sponsor knows the schedule.

Question 247

A healthcare company is in the process of deploying an innovative healthcare solution globally. The project team has completed a limited release.

The stakeholders have raised concerns about global healthcare guidelines and risks.

What should the project manager do next?

Options:

A.

Evaluate lessons learned from similar projects prior to deployment.

B.

Perform a qualitative risk analysis on the identified project risks.

C.

Review compliance and regulatory requirements with stakeholders.

D.

Conduct a feasibility analysis of deploying the solution globally.

Question 248

A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?

Options:

A.

Update the issue log and escalate the problem to the project sponsor.

B.

Ask for a project extension to deliver the committed scope.

C.

Review the options and possible solutions with the project team.

D.

Ask for help to increase the team capacity to deliver on time.

Question 249

A team working on a close deployment waits to receive critical information from the customer. The customer keeps postponing sending the information which is delaying the

deployment.

What should the project manager have done to prevent the delay?

Options:

A.

Obtained all critical information ahead of time

B.

Involved upper management in the process

C.

Involved the customer in the deployment process

D.

Used the sample data already in place

Question 250

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

Options:

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site

B.

Review the contract requirements and ask for the applicable evidence for quality assurance

C.

Have the vendor issue the quality documentation prior to the next delivery.

D.

Call the vendor and have them verbally guarantee the quality of the next site delivery

Question 251

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

Options:

A.

Consult the project scope document to make sure the addition is in scope.

B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.

Engage the stakeholder to solicit more information before responding to the request

Question 252

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?

Options:

A.

Make the decision on behalf of the organization

B.

Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision

C.

Schedule a project decision meeting with all stakeholders to discuss the decision.

D.

Follow the stakeholder engagement plan

Question 253

Drag the to the correct scenario on the right

Question # 253

Options:

Question 254

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team ' s efforts What should the project manager do in this situation?

Options:

A.

Work to understand the key stakeholder ' s concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder ' s concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder ' s behavior is impacting progress

Question 255

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?

Options:

A.

Four iterations

B.

One iteration

C.

Two iterations

D.

Three iterations

Question 256

The following table shows the business value created and the development effort required to implement various features in a product

Question # 256

Which feature should the team prioritize first? Enter the feature name in the box below

Question # 256

Options:

Question 257

A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to what has occurred.

What can the project manager do to help increase the team ' s motivation and engagement with the project?

Options:

A.

Review sprint progress with the project team members

B.

Set up one-on-one meetings with the project team members

C.

Review sprint planning procedures with the project team members

D.

Perform a sprint retrospective with the project team members

Question 258

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

Options:

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Question 259

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?

Options:

A.

Determine which agile software tools will be required to support agile delivery within the organization

B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project

C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted

D.

Determine how to transform the organization using agile techniques, including organizational training and communications

Question 260

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

Options:

A.

Impact mapping

B.

Rolling wave planning

C.

Collective code ownership

D.

Scrum of Scrums

Question 261

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team ' s needs

D.

A risk management plan to incorporate known risks

Question 262

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?

Options:

A.

Ask the new team member to follow the team ground rules.

B.

Ask an experienced team member to identify a replacement

C.

Ask the new team member to reassess their own capabilities

D.

Ask an experienced team member to coach the new team member

Question 263

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

Options:

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project ' s changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Question 264

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Question 265

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

Options:

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

Question 266

A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?

Options:

A.

Include the executives in team retrospectives

B.

Train the executives on agile practices

C.

Negotiate with the executives and agree on a process.

D.

Request that the executives use agile practices

Question 267

A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts

What should the project manager do next?

Options:

A.

Raise the issues in the retrospective and propose solutions

B.

Inform management that commitments will not be met.

C.

Involve management to help resolve the conflicts

D.

Coach the team both as a whole and individually

Question 268

A company recently used desktop research for a feasibility study, which showed that the project is behind schedule The project team also has concerns about the impact of scope changes on the project schedule

What should the project manager do to keep the project on schedule while still meeting project objectives ' ?

Options:

A.

Collaborate with the change control board (CCB) to review the scope and submit any change requests

B.

Submit a change request to the CCB and update the schedule

C.

Update the scope and add more resources to the project

D.

Update the scope and move on to the next project milestone

Question 269

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Question 270

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

Options:

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Question 271

The customer ' s project manager changes during the final stage of a project How can the project manager avoid a project closure delay’

Options:

A.

Update the stakeholder engagement plan

B.

Review the latest project status report and update the stakeholders

C.

Escalate the case to the customer ' s management team

D.

Issue the project payment invoice to the customer in advance

Question 272

A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks

Drag each risk type on the left to its correct example on the right

Question # 272

Options:

Question 273

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

Options:

A.

A directive style that makes decisions for the group to reach early outcomes

B.

A leadership style that coaches people who want help and fosters greater team collaboration

C.

A passive leadership style that allows the team to self-organize until the norming stage is reached

D.

A democratic style that uses techniques where majority opinion prevails

Question 274

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?

Options:

A.

Update the issue log and escalate to the project sponsor

B.

Identify the lack of information as a risk and update the risk register

C.

Schedule more frequent meetings with the technical manager.

D.

Review and update the stakeholder engagement plan

Question 275

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

Options:

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Question 276

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

Options:

A.

Allocate and use part of the project ' s contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory ' s hazards, providing employment to the local community

Question 277

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?

Options:

A.

Schedule a meeting with the project team to reinforce the ground rules.

B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action

C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.

D.

Ask the functional manager to replace team members not following the ground rules

Question 278

After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined The project manager is also informed that the key stakeholder does not want to hold a working session

What should the project manager do first?

Options:

A.

Share the project documents and invite the key stakeholder to discuss any concerns

B.

Ask the project sponsor to exert authority on the key stakeholder in order to maintain the approved timeline

C.

Proceed with a working session for teams that do not belong to that key stakeholder

D.

Invite the key stakeholder to the project ' s change control board (CCB) to discuss adjustment of the project strategy

Question 279

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Question 280

According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

Question # 280

Options:

Question 281

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

Options:

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Question 282

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations

What should the project manager do?

Options:

A.

Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate

B.

Review the historical information and lessons learned from last year’s project to justify the new budget estimate

C.

Change the budgeting technique to a more accurate, bottom-up cost estimation.

D.

Use soft skills to convince the project sponsor to approve the new budget estimate

Question 283

A project manager has been selected to deliver one of an organization ' s key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings

What is one of the key activities that the project manager should undertake to ensure company success?

Options:

A.

Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables

B.

Request more funding from the project sponsor to hire additional skilled resourcesand to incorporate additional quality in the project delivery approach and outcome

C.

Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions

D.

Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives

Question 284

During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?

Options:

A.

Ask the customer to issue a change request with the information to analyze and provide a solution.

B.

Review the deliverable requirements, check the customer approval criteria, and proceed accordingly

C.

Meet with the customer to reach agreement on the scope of the deliverable that will satisfy both parties

D.

Contact the project sponsor and ask for help in negotiating the closing of the project with the customer

Question 285

Drag the organizational characteristics on the left to the correct scenario on the right

Question # 285

Options:

Question 286

A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two)

Options:

A.

Complexity and the cost of development

B.

Industry trends and the technical approach

C.

Cost of delaying some features against business value

D.

Reusing components from another product

E.

Length of time each feature has been on the backlog

Question 287

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

Options:

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.

Speak with the project sponsor about changing the team composition

C.

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Question 288

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

Options:

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Question 289

A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?

Options:

A.

Ask the product owner, who is the key stakeholder, to choose among the different ideas.

B.

Propose ideas to the group, ask everyone to vote, and then choose the most popular idea

C.

Schedule a session to give everyone the chance to express their opinions about each idea, then vote and decide.

D.

Offer an opinion about the pros and cons of each idea and try to reach a consensus in a facilitated meeting

Question 290

A project manager for a government organization often deals with stakeholder engagement issues Drag the interpersonal skill the project manager should use on t he left to the correct situation on the right

Question # 290

Options:

Question 291

A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished

How should the project manager approach this situation?

Options:

A.

Request that the customer reviews and clarifies feature definitions for the current sprint

B.

Send a burndown chart of the current sprint to the customer and seek clarifications.

C.

Educate the customer and have them participate in daily standup meetings.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements

Question 292

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem ' s root causes and define the ground rules with all project team members to minimize interferences

B.

Hire a coach to help all project teams to improve their abilities to solve problems ontheir own.

C.

Reunite with the project team members affected and tell them not to reduce the team ' s capacity

D.

Recommend to the project team members that they should improve their planningand make their stones smaller

Question 293

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team ' s request " ?

Options:

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

Question 294

In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.

What should the project manager calculate to address this critical budgetary situation? (Choose two)

Options:

A.

Contingency control in the project and rebaseline

B.

Mitigation control in the project

C.

Benefits management control in the project

D.

Integrated change control in the project

E.

Currency exchange rate

Question 295

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation

B.

Ask the stakeholders about the priority of this regulation

C.

Ask the product owner to include the requirements in the product backlog

D.

Ask the security department for details about regulations

E.

Ask the team members to include the requirements in the next iteration

Question 296

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people tocompensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Question 297

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Question 298

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?

Options:

A.

Develop a work plan for the project team member with the help of the resource manager

B.

Advise the functional manager and the project team member to review the resource management plan

C.

Tell the functional manager and the project team member to review the projectcharter

D.

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member

Question 299

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Question 300

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product ' s feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Question 301

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Question 302

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

Options:

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Question 303

A project manager for a large multiyear industrial project has a project with diversified stakeholders from various geographical areas. Recently, the project manager encountered an issue with stakeholder engagement

Which two tools should the project manager use to determine the underlying reason for why engagement is not having the planned effect? (Choose two)

Options:

A.

Five whys

B.

Communications management plan

C.

Ishikawa diagrams

D.

Issue log

E.

Open-space meetings

Question 304

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

Options:

A.

Support the product owner ' s decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Question 305

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

Options:

A.

Contact the team member ' s functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Question 306

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experienceto build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Question 307

A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities

How should the stakeholder be engaged in the project?

Options:

A.

Keep the stakeholder informed and consult with them based on their needs

B.

Involve the stakeholder in governance and decision making

C.

Consult with the stakeholder and increase their level of interest

D.

The stakeholder needs to be made aware of the project progress

Question 308

A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?

Options:

A.

Increase the details of the work breakdown structure (WBS) to minimize errors and delays.

B.

Split the backlog into phases to ensure that the key features are delivered first

C.

Ask the sponsor to prioritize some functionalities of the product.

D.

Identify the minimum functionality required for the product

Question 309

A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery

Which two actions should the project manager take to mitigate this risk? (Choose two)

Options:

A.

Introduce a recognition program to motivate and reward resource performance

B.

Enhance the competencies of the project team through training, mentoring and coaching.

C.

Increase the trained staff to create back-up for resources

D.

Meet with management to discuss dividing the project into smaller projects

E.

Convince senior management to hire third-party staff

Question 310

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project ' s success?

Options:

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

C.

Continuously monitor the risk of the partner system ' s unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

Question 311

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?

Options:

A.

Sent the meeting minutes to the stakeholders after the kick-off meeting

B.

Reviewed all the approvals immediately after the kick-off meeting was over

C.

Ran separate kick-off meetings for each culture and time zone

D.

Validated each stakeholder ' s understanding during the kick-off meeting

Question 312

A project manager has two projects that are being executed at the same time The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal In addition, the schedule does not have activities that can be overlapped

What should the project manager do?

Options:

A.

Analyze both projects to determine the most effective use of common resources

B.

Use resource optimization to justify requesting more resources for the critical project

C.

Provide schedule optimization training to the project teams to improve their skills.

D.

Apply fast-tracking techniques to compress the schedule of the critical project

Question 313

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

Options:

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Question 314

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

Options:

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Question 315

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

Options:

A.

Send an email invitation to the project sponsor to attend all of the project team ' s weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks andissues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Question 316

The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress What should the project lead do?

Options:

A.

Provide a link to the project ' s shared drive for the executive to search through for any artifacts that are of interest.

B.

Invite the executive to the project ' s meeting space to determine if the project information radiators meet their needs

C.

Reach out to the project management office (PMO) for status report templates and provide project updates in that format

D.

Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments

Question 317

While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves

What should the project manager do?

Options:

A.

Ask the product designer why the deviation was not considered in the design phase

B.

Report to the project sponsor that the product is working and the project is struggling with the budget.

C.

Evaluate and initiate the change request process with the stakeholders

D.

Ask the quality team to discard the sample and test again with a new sample

Question 318

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?

Options:

A.

Add an entry in the risk log

B.

Implement the changes

C.

Review target benefits.

D.

Improve the team ' s velocity

Question 319

A project manager of a large company needs to categorize the stakeholders ' involvement at the beginning of a project initiated by the board of directors. The sales and delivery teams are internal teams.

Drag each stakeholder scenario on the left to the correct engagement level on the right.

Question # 319

Options:

Question 320

A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client ' s needs.

What should the project manager do?

Options:

A.

Set up a meeting with key stakeholders to clarify requirements

B.

Escalate to the project steering committee and request additional time

C.

Travel to the development team ' s office to push the schedule

D.

Create prototypes with the development team to confirm requirements

Question 321

A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.

Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck

Question # 321

Options:

Question 322

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

Options:

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Question 323

The project schedule is falling behind and the project manager observes that the project team seems to be spending the majority of their time writing documentation instead of performing project tasks What should the project manager do to help ensure that the team focuses on project tasks?

Options:

A.

Assign a team member to handle the documentation activities.

B.

Coach the project team to complete the project documentation activities

C.

Review and adapt the appropriate project artifacts.

D.

Save all documentation activities until tire end of the project

Question 324

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) - > stops working and crashes the system

1.500 rpm (rate-per-minute) - > warns of max rate allowed

1.400pm (rate-per-minute) - > reduces the power and brakes the engine

Which of the following statements is correct?

Options:

A.

0 1,600 rpm is a project risk,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.1,500 rpm is a project issue and 1,400 rpm is a project risk.

Question 325

An organization has historically executed most projects using a predictive approach The organization now wants to change over to an agile approach

Which strategy will be useful to effectively help prepare the organization for this change?

Options:

A.

Create a task force of executives who will monitor agile projects on a daily basis

B.

Add multiple layers of managers who will be accountable for the agile execution

C.

Improve organizational readiness by addressing impediments to agile in the organization.

D.

Take a big bang approach of moving the whole organization to agile at once

Question 326

After the project charter ' s approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

Options:

A.

Email, call, or meet with each stakeholder separately to obtain their input

B.

Conduct a meeting to build the project management plan with the stakeholders who are available

C.

Escalate to the project sponsor that not all stakeholders are available for a meeting

D.

Meet with the project management team to build the project management plan before consulting stakeholders

Question 327

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

Options:

A.

Retrospect frequently and suggest improvements.

B.

Incorporate a predictive approach for this element.

C.

Implement mitigation strategies for this element

D.

Request additional team members to help with improvements

Question 328

A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.

Using a hybrid approach, what techniques can be used to achieve this goal?

Options:

A.

Daily Scrum and product owner quality assessments.

B.

Scrum master reviews and the quality Kanban method

C.

Paired work and the customer role method.

D.

Time-boxed iterations and standup review meetings

Question 329

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

Options:

A.

Hold a stakeholder meeting to align timelines and scope expectations.

B.

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.

Reduce the scope of the project by removing activities and shortening the timeline

Question 330

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

Options:

A.

Clarify project benefits with the sponsor.

B.

Identify the goal of each work product

C.

Perform integration testing of each release

D.

Include the entire project team in testing

Question 331

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team ' s performance?

Options:

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Question 332

A new team member has joined an agile project, replacing a team member who recently left The project team needs the new team member to speed up their ability to contribute effectively to the project

What should the project manager do to help in this situation?

Options:

A.

Assign the new team member the same tasks that were assigned to the previous team member who they replaced

B.

Schedule knowledge transfer sessions and assign less complex tasks to the new team member

C.

Send technical documentation to the new team member and schedule training for the next iteration.

D.

Have the new team member complete all of the company’s mandatory training

Question 333

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

Options:

A.

Understand the customer ' s perspective and provide mentoring on agile mindsets.

B.

Call for an internal team retrospective and create an improvement action plan.

C.

Ask the customer to work with the product owner to prioritize all requests.

D.

Work with the team to receive customer directions and improve the process.

Question 334

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

Options:

A.

Ask the vendor to communicate via the established channels.

B.

Invite the vendor to a meeting to discuss the concerns.

C.

Escalate the vendor ' s lack of responsiveness to the project sponsor.

D.

Proceed with other tasks while awaiting a response from the vendor.

Question 335

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

Options:

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

Question 336

A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the

obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.

What should the project manager have done to avoid this issue?

Options:

A.

Prioritized blockers on the critical path

B.

Distributed the daily standup meeting agenda beforehand

C.

Followed the quality control measurements

D.

Developed the team members’ competences:

Question 337

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

D.

In the initiation process, as it happens concurrently with the project contract and project charter creation

Question 338

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.

B.

The project is under budget and on schedule.

C.

The project is under budget and behind schedule.

D.

The project is on budget and on schedule.

Question 339

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

Options:

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.

Trust the development team ' s risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

Question 340

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor ' s request?

Options:

A.

Work with the organization ' s real estate department and reach out to the local government to identify the best location for the store.

B.

Work with the local government to build the profiles of employees that will be working in the store.

C.

Work with the organization ' s legal department to identify local regulations to ensure project compliance.

D.

Work with the organization ' s project management office (PMO) to build a project team of residents located in the city.

Question 341

A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.

What should the project manager do in this situation as a servant leader?

Options:

A.

Request an exception to allow the team to return to work on-site

B.

Allow the team to address the problem as a self-organized team

C.

Coach team members to increase their engagement and collaboration

D.

Force the team to attend the daily standups to gather the project status

Question 342

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

Options:

A.

Select members for their skill or potential.

B.

Establish the project scope and set clear team objectives.

C.

Set performance standards and direction.

D.

Hold early kick-off meetings and regular weekly meetings.

Question 343

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)

Options:

A.

Require the team to have daily mandatory meetings with the project management office (PMO).

B.

Recommend the use of formal written documentation in all project communications.

C.

Review the communications strategy with the team regularly with a view for continuous improvement.

D.

Send out a survey to review the preferred method, time frequency for communications.

E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.

Question 344

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

Options:

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

Question 345

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Question 346

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Question 347

A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.

What should the project manager do?

Options:

A.

Suggest the team member focus on positions with technical aspects and possible technical career opportunities.

B.

Recommend the team member for effective communication training and support their career development interests.

C.

Encourage the team member to stay in their current role as they are important to the project.

D.

Ask the team member to refrain from pursuing new opportunities as they are not a suitable fit for a leadership position.

Question 348

A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project

manager for mentoring.

Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)

Options:

A.

The junior project manager reports administratively to their mentor so that human resource (HR) questions can be answered quickly.

B.

The junior project manager can discuss certain problems with their mentor without fear of retribution.

C.

The mentor will be immediately available to take over the project if there are problems or project delays.

D.

The mentor will be involved in the decision-making processes implemented by the junior project manager.

E.

The mentor can provide past project documentation with early warning indicators that potential problems could occur.

Question 349

A multinational company is launching a company-wide digital transformation project that covers all of its regions and business lines. The project is expected to go through five phases and finish in 2 years. The project manager schedules a kick-off meeting.

What should the project manager do next?

Options:

A.

Ensure there is enough budget to mandate all team members to fly to corporate headquarters for the kick-off meeting.

B.

Consider using digital or virtual tools to conduct the kick-off meeting to minimize geographic boundaries.

C.

Document the kick-off meeting and close out the planning phase after the meeting is held.

D.

Limit to one kick-off meeting in the project ' s first phase in order to control the budget.

Question 350

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager ' s recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Question 351

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

Question # 351

Options:

Question 352

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

Options:

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Question 353

A project manager for an iterative project noticed that retrospective items indicate that the team is not fully conversant with the principles of iterative development. The team meets to analyze the gaps in the training that recently concluded with a third-party trainer.

What should the project manager do next?

Options:

A.

Initiate hybrid development as an interim approach.

B.

Let the project team self-organize and develop their skills.

C.

Mentor and coach the team to meet the project needs.

D.

Review the training contract to determine the next steps,

Question 354

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource ' s refusal?

Options:

A.

Speak directly with the resource.

B.

Communicate with their supervisor.

C.

Organize a team meeting.

D.

Speak with their colleague.

Question 355

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Question 356

A project manager who is experienced in predictive and adaptive approaches has been assigned to a new project. Most of the project

stakeholders have only worked on predictive projects, and only a few have been exposed to adaptive projects.

What should the project manager do?

Options:

A.

Propose a hybrid approach and determine which stakeholders will be engaged in each phase of the project.

B.

Follow a predictive approach to reduce the training effort, even though there are incremental deliveries in the project.

C.

Use an adaptive approach, engage the stakeholders who have been exposed to adaptive projects, and train those who have not.

D.

Understand the scope complexity and project magnitude prior to determining which approach to use.

Question 357

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

Options:

A.

Move the task to the next sprint.

B.

Ask the team member to bring up the concern in the next daily meeting.

C.

Send an email explaining the issue to all team members.

D.

Reassign the task to another team member.

Question 358

A project manager who takes over halfway through a project determines that the cost performance index (CPI) is 0.65. A detailed audit identifies that the project cost was analogously estimated, and the audit team thinks that something was missing in the way the estimates were done.

What should have been done to avoid this problem?

Options:

A.

Included lessons learned from past projects

B.

Used bottom-up estimating

C.

Utilized three-point estimates

D.

Validated the schedule performance index (SPI) to evaluate deviation

Question 359

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Options:

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Question 360

A project manager ' s customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

Options:

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.

B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.

C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

D.

Invite the customer to join the regular sprint planning sessions to better understand the project ' s progress.

Question 361

In a project steering committee meeting, a few stakeholders raise concerns that the project manager ' s report shows that the outcome of the project is already in the market

while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.

What should the project manager do to avoid a reoccurrence of this scenario?

Options:

A.

Ensure the content of the project report is clearly understood and request any necessary feedback.

B.

Invite critical stakeholders to the daily project review meetings to ensure their full engagement and involvement.

C.

Send a detailed report to each steering committee member ahead of the meeting.

D.

Ensure that all product features are completed as per the communicated specifications before releasing to market.

Question 362

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

Options:

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Question 363

A project manager holds meetings every Monday to review the team members ' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

Options:

A.

Analyse the team members ' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

Question 364

At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting

with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.

What should the project manager do to assess the priorities and meet the new objective?

Options:

A.

Submit a change order request with the new project objective to the project management office (PMO).

B.

Initiate a crashing routine to gain extra time for the added feature.

C.

Communicate the results and negotiate the needed resources and time with the stakeholder.

D.

Ask the project team to work overtime in order to accommodate the new changes.

Question 365

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Question 366

A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.

What should be me project manager ' s response?

Options:

A.

Sprint plan and product roadmap

B.

Product roadmap and sprint backlog

C.

Product backlog and scrum board

D.

Sprint backlog and scrum board

Question 367

A project manager has just taken over a project that is in the requirements gathering phase. A stakeholder indicates that they have not received any progress updates even

though reports have been sent on a weekly basis.

What should the project manager do to ensure all stakeholders are receiving proper information about the project?

Options:

A.

Hold a steering committee meeting with all stakeholders to provide a comprehensive update on the project progress.

B.

Create daily progress reports and send them to all stakeholders.

C.

Include stakeholders in the weekly status meetings with the team.

D.

Assess all of the project stakeholders and document their preferred communication method and frequency.

Question 368

A project sponsor has approved the project charter and business case. The project manager has reviewed the artifacts to initiate the project and is unclear if the intended benefits of the project align with the strategic objectives of the business.

What should the project manager do first?

Options:

A.

Start executing the project since leadership is responsible for the business strategy.

B.

Meet with the project sponsor to better understand the strategic benefits of the project.

C.

Propose an updated business case and project charter that are more aligned with the business strategy.

D.

Conduct qualitative and quantitative risk analysis and record the results in the risk register.

Question 369

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?

Options:

A.

Project sponsors

B.

Other project managers

C.

Business unit managers

D.

Program managers

Question 370

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

Options:

A.

Invite the stakeholders to the retrospective meetings.

B.

Invite the stakeholders to the sprint review meetings.

C.

Hold a meeting every 2 weeks with the stakeholders.

D.

Negotiate by sending an informative email to stakeholders.

Question 371

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

Options:

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Question 372

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

Options:

A.

Create better plans to test the functionality in more detail.

B.

Review the definition of done (DoD) with the product owner.

C.

Include previous sprint defects and close them in the actual sprint.

D.

Get approval from the product owner on the user stories.

Question 373

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Question 374

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team ' s collaboration approach?

Options:

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team ' s velocity with other teams in the organization.

D.

Focus on the team ' s engagement during the next retrospective meeting.

Question 375

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?

Options:

A.

Plan for continuous validation of the product.

B.

Discuss adding business scenario tests with the customer.

C.

Discuss adding additional test cases with the product owner.

D.

Add more test scenarios based on the issues found.

Question 376

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

Options:

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

Question 377

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Question 378

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

Options:

A.

Remove one of the team members from the project to improve team dynamics.

B.

Make a decision based on expert judgment as a project manager.

C.

Consider the view of each team member about the issue in order to reach consensus.

D.

Remove both team members since they are not productively adding to the team.

Question 379

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

Options:

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Question 380

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Question 381

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master ' s program will coincide with the last phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

B.

Suggest the team member postpone their enrollment in the master ' s program until the project is completed.

C.

Ask the team member to inform human resources (HR) about their enrollment in the master ' s program.

D.

Assess the team member ' s commitment to the master ' s program and its impact on project performance.

Question 382

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Options:

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Question 383

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)

Options:

A.

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,

B.

Share weekly status reports with detailed information about the project and team performance.

C.

Submit performance reports and task assignments to keep the stakeholder informed.

D.

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

E.

Provide training to the team on emotional intelligence and status reporting techniques.

Question 384

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

Options:

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Question 385

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager ' s expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

Options:

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Question 386

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

Options:

A.

Meet with the functional managers to align the expected frequency and results reporting for the team members.

B.

Provide performance feedback to the learn members ' functional managers at the end of the year.

C.

Assure team members that this project is a high priority for the company and they will be evaluated accordingly.

D.

Request to be made responsible for the performance plans of those on this project team

Question 387

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.

Look at the stakeholder assessment matrix to find stakeholders ' interests and make updates if necessary.

B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.

C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.

D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders ' approvals.

Question 388

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.

What should the project manager do?

Options:

A.

Coordinate design document preparation

B.

Perform a qualitative risk analysis

C.

Request further clarification of the requirement

D.

Manage the engagement of this stakeholder.

Question 389

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

Question # 389

Options:

Question 390

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Motivate the team member to stay by providing them with incentives.

D.

Ask human resources (HR) to counsel the team member to balance the workload.

Question 391

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Question 392

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project ' s purpose, mission, and vision.

D.

Carry out the product backlog creation.

Question 393

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team ' s progress. The project is now at risk of completing later than expected.

What should the project leader do?

Options:

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

Question 394

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager ' s functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

Options:

A.

Schedule a one-on-one meeting with the functional manager to prove the project is on time

B.

Listen carefully and show understanding of the growing needs of the functional manager.

C.

Admit that the functional manager is right and promise to rectify the situation immediately.

D.

Show the functional manager that the progress is on time based on the schedule.

Question 395

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer ' s complaints and critical issues in the issue log.

Question 396

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

Options:

A.

Share a template with the stakeholder to receive feedback on deliverables.

B.

Ask the project sponsor to arrange a meeting with the stakeholder.

C.

Use networking skills to approach the stakeholder.

D.

Update the stakeholder engagement plan for the stakeholder.

Question 397

A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one

member reported an impediment that requires collaboration from an expert who is assigned to another project.

What should the project manager do first in this situation?

Options:

A.

Review the project ' s key performance indicators (KPIs) to determine the impact of this assignment.

B.

Check the expert ' s availability within the organization on an as-needed basis.

C.

Develop the team member ' s capacities through mentoring and training.

D.

Ask the project sponsor to assign a new resource with the necessary expertise to the team.

Question 398

A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The

procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.

How should the project manager approach this project?

Options:

A.

Apply a predictive project management approach.

B.

Evaluate and decide on a phased project management approach.

C.

Implement an adaptive project management approach.

D.

Use a hybrid model to combine predictive and adaptive life cycles.

Question 399

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?

Options:

A.

Focus on the implementation of a software as a service (SaaS) solution for the customer.

B.

Specify the scope and features to be deployed in the contract clearly.

C.

Work very closely with the customer and third parties to meet their needs.

D.

Change the marketing and product management definitions to meet stakeholder needs.

Question 400

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

Options:

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Question 401

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.

What should the project manager do to address this issue?

Options:

A.

Request that the project team change their task deliverables to reflect the project sponsor ' s requirements.

B.

Set up a daily standup and request that the project sponsor attend to understand the project ' s tasks and deliverables.

C.

Ask the project team to compile a project scope document and obtain approval from the project sponsor.

D.

Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.

Question 402

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member ' s functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Question 403

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Question 404

During a project ' s initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion

What should the project manager do next?

Options:

A.

Discuss this issue with the project sponsor to request additional funding to implement mitigation

B.

Hire a construction management consultant to develop a comprehensive site execution plan

C.

Prequalify contractors with proven track records to eliminate productivity concerns

D.

Add construction productivity to the risk register and develop a mitigation strategy for site execution

Question 405

A construction project for a nuclear power plant will reduce the region ' s energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

Options:

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

Question 406

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

Options:

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

Question 407

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Question 408

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Question 409

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

Options:

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Question 410

A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.

What should the project manager do?

Options:

A.

Review the requirements on a weekly basis.

B.

Implement a requirements traceability matrix.

C.

Add the requirements to the project charter.

D.

Understand the project management plan.

Question 411

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

Options:

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Question 412

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Question # 412

Options:

Question 413

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?

Options:

A.

Follow the Perform integrated Change Control process and submit a change request

B.

Ask the team members to draft a justification before processing the reimbursements

C.

Update the project management plan with the incurred costs

D.

Review the budget and allocate funds for the reimbursements

Question 414

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a

previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Question 415

A project manager ' s new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager ' s background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

Options:

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Question 416

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

Options:

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

Question 417

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

Options:

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Question 418

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

Options:

A.

Company ' s historical organizational project artifacts

B.

Company ' s project responsibility assignment matrix (RAM)

C.

Company ' s resource management plan

D.

Company ' s resource calendars

Question 419

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

Options:

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Question 420

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor ' s support for the project.

Question 421

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

Options:

A.

Instruct the team to work as planned and Ignore the stakeholder ' s requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Question 422

A large company is transitioning its projects to an agile approach After the transition executive management requests the information that was previously available in old reports and dashboards Many of the old reports and dashboards are no longer relevant after the shift to agile practices.

What should the project manager do in this situation?

Options:

A.

Explain to the management team that reporting and management dashboards are not effective agile practices

B.

Ask the management team to review the endorsed agile concepts to prove that the old information s not relevant

C.

Help the management team understand how the change to an agile approach impacts the relevance of certain reports and key performance indicators (KPls)

D.

Remind the management team that an agile approach empowers teams to be self-directed and therefore there is no need for reporting

Question 423

A project manager has experience working with a specific provider that has been

requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.

What should the project manager do during the planning phase?

Options:

A.

A. Hire resources to obtain knowledge about the provider ' s specific capabilities.

B.

B. Add penalty clauses to the contract and update the risk register.

C.

C. Encourage the provider to work overtime with no additional costs to the project.

D.

D. Contract another provider with less experience and give them a chance to provide the deliverables.

Question 424

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Question 425

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

Options:

A.

Provide mentoring for the key team members on agile practices and support the teamwith training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rulesstated in the document.

C.

Replace the key team members with new resources who are already aware of the agilemindset.

D.

Provide directions to the team members on how to accelerate the company ' stransformation, bringing the project back on track.

Question 426

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

Options:

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

Question 427

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

Options:

A.

Document the issue in the issue log and escalate to the project sponsor

B.

Inform the project sponsor and suggest canceling the project

C.

Review the project goals and eat criteria m the project charter

D.

Ask the leader of research and development to decide on next steps

Question 428

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager ' s company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

Options:

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.

Question 429

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

Options:

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members ' manager and schedule a meeting to discuss the details of this assignment

Question 430

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office ' s (PMO ' s) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO ' s status reports have sufficient enough information

How should the new project manager proceed*?

Options:

A.

Continue using the outgoing project manager ' s status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Question 431

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

Options:

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Question 432

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Question 433

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?

Options:

A.

Let the product go to market and wait for customer feedback regarding quality

B.

Ask the quality manager to include the final user tests in the quality management plan.

C.

Submit a change request to analyze a new set of quality tests

D.

Ask the product manager to include the final user tests in the quality management plan

Question 434

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project

How should the agile leader ensure successful delivery?

Options:

A.

Ensure participation from all team members

B.

Ask the client to attend all daily calls.

C.

Ensure cross-departmental teams are colocated

D.

Request additional project resources

Question 435

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.

Identified and reported the issue

B.

Monitored and controlled the issue

C.

Identified the appropriate response and had it implemented

D.

Communicated any identified action to impacted stakeholders

Question 436

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor and request extra time and budget to obtainthe component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to theperformance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) andrelevant stakeholders to identify alternatives to address the problem.

Question 437

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual ' s participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for theproject.

Question 438

A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team

What should the project manager do first to solve the situation?

Options:

A.

Speak with the team member about their engagement and contributions

B.

Perform an assessment of each member of the project team

C.

Assign the team member to a team where they can contribute more

D.

Conduct a team building event to involve the team member

Question 439

A project manager is assigned to a project related to taxes, which will be managed

using an agile approach. By reviewing lessons learned from a previous project, the project

manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Recognize the stakeholder ' s skills are important for the project and evaluate thepossibility of the stakeholder supporting the project team.

B.

Request the functional manager to assign the team from the lessons learned project tothe current project to avoid a learning curve.

C.

Ask the project team to review the lessons learned and have the team contact thestakeholder directly if there are any questions.

D.

Send a request to the project sponsor to hire the stakeholder and have them becomepart of the project team.

Question 440

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Options:

A.

Seek the sponsor ' s approval to extend the project schedule.

B.

Set up a meeting to perform a root cause analysis.

C.

Update the issue log and communicate it to the team.

D.

Permanently colocate the team for better performance.

Question 441

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Question 442

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.

Invite the product owner to attend daily standup meetings so they can assessprogress.

B.

Set up a feedback session with the product owner once a week so they can assessprogress.

C.

Instruct the team to refer the product owner to the project manager for information.

D.

Invite the product owner ' s functional manager to a feedback session to escalate theissue.

Question 443

A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget

What should the project manager update first?

Options:

A.

Issue log

B.

Lessons learned register

C.

Stakeholder engagement plan

D.

Risk register

Question 444

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

Options:

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

Question 445

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Question 446

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A ' s team focuses on the features of data capture.

• City B ' s team focuses on the user experience and development pieces.

• City C ' s team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

Options:

A.

Ensure all three teams deliver independently without interactions so that they remainfocused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern ofhanding off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issuesbetween the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any otherunforeseen risks that might prevent progress.

Question 447

An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.

What should the agile leader do?

Options:

A.

Reassign the task to another team member and require the team member to complete training

B.

Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint

C.

Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.

D.

Speak directly with the team member about improvements and commit to an agreed-upon time frame.

Question 448

During the setup of an agile project, the product owner expressed clear interest in

having features released during product development over having the product completed in

one year. What should the project manager do?

Options:

A.

Promote a productive environment where everybody can work without interruptionsfrom the rest of the team members.

B.

Create a reward system recognizing group contributions to get people motivated andimprove performance.

C.

Facilitate sprint planning sessions with a focus on defining the minimum viable product(MVP).

D.

Design a set of metrics including velocity, which is a good measure of value delivered.

Question 449

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

Options:

A.

Modeling directive leadership

B.

Modeling commanding leadership

C.

Modeling adaptive leadership

D.

Modeling servant leadership

Question 450

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

Options:

A.

Identify how the proposed changes will benefit the project in relation to the businesscase.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on alengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Question 451

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Question 452

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

Options:

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Question 453

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Question 454

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team ' s integration leads is a subject matter expert (SME) m this integration area. The other team ' s integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

Options:

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

Question 455

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

Question # 455

Options:

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Question 456

Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.

What should the project manager do to resolve this issue and help the team move on to the next iteration?

Options:

A.

Postpone the selection of the technology used until more information is gathered

B.

Suggest their own approach to solve the issue and ask the team to follow it

C.

Call for an open dialogue which the team will arrive at through consensus

D.

Allow the team to decide since the teams should be autonomous

Question 457

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

Options:

A.

Communicate the situation to the team and plan for the necessary training and coaching arrangements

B.

Report the situation back to upper management and request to have the scope changed

C.

Plan to hire more experienced team members and lay off a few of the existing team members.

D.

Communicate the situation to the customer and inform them about potential delays in delivery.

Question 458

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project ' s completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

Options:

A.

Issue a change request to remove items from the scope of work and keep the project on schedule.

B.

Issue a change request to include the additional scope, and track the completion of the work items.

C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.

D.

Arrange to pass the cost to the operational area since the customer will benefit.

Question 459

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

Options:

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Question 460

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager ' s approval.

What should the project manager do?

Options:

A.

Update the issue log and review the lessons learned register for options

B.

Implement conflict resolution to accommodate the team ' s needs

C.

Implement decision-making techniques to advance the stones

D.

Empower the team to self-organize and make their own decisions

Question 461

During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?

Options:

A.

Asking and listening

B.

Being collaborative

C.

Managing expectations

D.

Building trust

Question 462

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday ' s tasks. What should the agile coach do first to address the situation?

Options:

A.

Emphasize the ground rules and then focus on today ' s activities and impediments.

B.

Let the discussion go on as it is important that the team is clear on priorities for theday.

C.

Address the team members involved during the next sprint retrospective.

D.

Avoid the discussion by referring to the team charter.

Question 463

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem ' s root causes and define the ground rules with all project team members to minimize interferences.

B.

Recommend to the project team members that they should improve their planning and make their stories smaller.

C.

Reunite with the project team members affected and tell them not to reduce the team ' s capacity.

D.

Hire a coach to help all project teams to improve their abilities to solve problems on their own.

Question 464

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Question 465

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

Options:

A.

Add the stakeholder details into the periodic reports and update the project management plan

B.

Invite the stakeholder to all future project review meetings and update the project management plan

C.

Update the project management plan with the new information and inform all of the relevant stakeholders

D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan

Question 466

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

Question 467

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration " ?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Question 468

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

Options:

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

Question 469

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

Options:

A.

Ensure that the whole team is appropriately recognized and organize a project farewellparty to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and savethem in the organization ' s project management information system (PMIS).

C.

Archive all the project documents following the organization ' s accepted practices sothe documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult toundertake because the current project is not yet complete.

Question 470

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

Options:

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

Question 471

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

Options:

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization toresolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the projectforward.

Question 472

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

Options:

A.

Reviewed the risk register to identify a response plan for the audit

B.

Assigned a project team member to ensure all project documentation was updated

C.

Updated the project management plan regularly and had it securely shared with all stakeholders

D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Question 473

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.

A team whose members work independently and are the best subject matter experts(SMES)

B.

A team whose members have more general aptitudes but like to work individually

C.

A team whose members have different skill sets and are spread out geographically

D.

A team whose members have more general aptitudes and can collaborate on different tasks

Question 474

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Question 475

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

Options:

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach

B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using

C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use

D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project

Question 476

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Question 477

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives

B.

Subdivide the team to handle different aspects of the project

C.

Support the team to find and execute the minimum viable product (MVP)

D.

Organize project execution to satisfy the project sponsor s request

Question 478

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

Options:

A.

Develop project onboarding guidelines for the team members assigned to the project.

B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders toparticipate.

C.

Ensure that lessons learned are considered as part of the project scheduledecomposition.

D.

Confirm that no conflicts exist in resource calendars with assigned activities on otherprojects.

Question 479

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

Options:

A.

Request to meet with the team member and ask that any issues be escalated separately.

B.

Reprimand the team member and provide immediate coaching on goal alignment.

C.

Proceed with defining the goals with the team members given the majority approval from the team.

D.

Approach the team member with empathy and obtain agreement through collaboration.

Question 480

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

Options:

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Question 481

A project has been running for 2 months and now requires approval for a supplier to

begin some execution tasks. The project team has evaluated several suppliers and selected

their top two preferred suppliers. The project sponsor requested that another supplier who has

lower costs be added to the list. However, the project manager is aware that this supplier

does not always fulfill the project requirements.

What should the project manager do?

Options:

A.

Set up a requirements review session and obtain agreement for selection criteria.

B.

Recommend to the team to add the sponsor ' s preferred supplier to the list.

C.

Choose the sponsor ' s preferred supplier for the project to avoid conflict between theteam and sponsor.

D.

Recommend to the sponsor to review the results of the team ' s supplier evaluation.

Question 482

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

Options:

A.

An agreed-upon work method and tools that should fit the business need and project constraints

B.

A detailed mitigation plan on the risks for each work method and the tools used

C.

A consensus that everything will run as anticipated once the tools and work methods are identified

D.

A technology roadmap for creating similar deliverables in the future with the same tools

Question 483

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder ' s details and make sure the projectstatus reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder ' s needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register forincorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder ' s needs are captured in the project management plan.

Question 484

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Question 485

On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client. The project manager is now in the initial stage of a new project with the same subcontractors and client.

How should the project manager set up communications?

Options:

A.

Inform the client that all communications moving forward will go through the project manager

B.

Ensure that the communications management plan covers contractual obligations

C.

Consult the communications management plan from a recent project that has been closed

D.

Update the communications management plan to allow the subcontractors to communicate directly with the client

Question 486

A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?

Options:

A.

Include the issue in the risk register and update the team

B.

Document the continuing issue and failed solution

C.

Inform the stakeholders about the failure and update the issue log

D.

Meet with the project team to find another solution

Question 487

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

Options:

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

Question 488

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Options:

A.

Functional managers, team members, and external consultants with experience in the field

B.

Team members, engineers, and weather experts

C.

Team members, consultants from outside the project with experience in the field, and the customer

D.

Weather experts, functional managers, and team members

Question 489

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Question 490

A leader from project B consistently reaches out to a team member in project A for

assistance. What should project A ' s project manager do?

Options:

A.

Allow project B ' s leader to continue building relationships.

B.

Talk with project B ' s leader to discuss possible impacts to both projects.

C.

Tell project A ' s team member to ignore project B ' s leader.

D.

Ensure project A ' s team member can finish the work committed to project A.

Question 491

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working asexpected.

Question 492

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

Options:

A.

Meet with each stakeholder individually to gather input to the product backlog andbegin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learnedand complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for theproduct backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Question 493

In the planning phase, a project manager receives identified risks from the sponsors

and subject matter experts (SMEs) and wants to develop a risk response strategy for them.

What should the project manager do first?

Options:

A.

Perform a risk reserve analysis.

B.

Assign allocated budget to cover key risks.

C.

Agree on the criteria to prioritize risks.

D.

Assign a risk responsibility to each team member.

Question 494

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members ' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Question 495

A project stakeholder has expressed concern that the established success criteria for

the project are not being met. What should the project manager do next?

Options:

A.

Review the established project benefits tracking metrics.

B.

Update the project business case document.

C.

Document the agreed-upon ownership of benefits realization.

D.

Create a project benefits management plan.

Question 496

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

Options:

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

Question 497

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Explain the impact of the scenario to the project team member.

B.

Remove the project team member from all future meetings.

C.

Talk to the client privately to highlight the situation.

D.

Recommend a performance improvement plan to the project team member.

Question 498

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.

Replace the team member immediately to maintain a good relationship with thefunctional manager.

B.

Discuss the issue with the functional manager to understand the reason for thecomplaint.

C.

Support the team member and provide documentation to the functional managerproving their performance.

D.

Protect the team member and ask the project sponsor to minimize any externalinterruptions.

Question 499

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

Options:

A.

Hold separate retrospective meetings for both the vendor team and the internal team.

B.

Schedule a preliminary meeting with the account manager from the vendor and the test manager.

C.

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.

D.

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.

Question 500

A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?

Options:

A.

Ask the team member to contact the learning and development team for additional help.

B.

Share the required documents with the team member.

C.

Arrange a required training session for the team member.

D.

Raise this issue in the next team meeting and ask the rest of the team to clarify.

Question 501

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

Options:

A.

11 days

B.

12.5 days

C.

12 days

D.

11.5 days

Question 502

During a discovery phase, a project manager coordinated a brainstorming event to determine the best strategy to meet the product release date. After the project overview,

the subject matter expert (SME) remained quiet during the call.

What should the project manager do next?

Options:

A.

Cancel the meeting if team members do not have the skills to suggest a strategy.

B.

Pose direct questions to the participants based on their area of expertise to start engaging them in the conversation.

C.

Review the roles and responsibilities during the call to determine who is accountable for the strategy.

D.

Create a strategy based on the project manager ' s experience and get approval during the call.

Question 503

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?

Options:

A.

Schedule a lessons learned meeting with the project team and close out the project.

B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.

C.

Prepare a transition plan to hand over the operations and other closing documentation.

D.

Document the project manager ' s departure and the missing documents in the risk log.

Question 504

A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.

What should the project manager do to handle the scope change?

Options:

A.

Define an initial backlog and start working on the clearest tasks, then incrementally refine the scope.

B.

Create a risk entry in the risk management plan due to the lack of a global project management plan.

C.

Review the organizational process assets (OPAs) from past projects with similar scope changes.

D.

Formalize the change in the scope with the project sponsor to limit accountability for the specific tasks.

Question 505

An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.

What should the project manager do first to resolve this dispute?

Options:

A.

Escalate to the project sponsor to provide a solution to the conflict.

B.

Interpret the source and stage of the conflict and select a resolution approach.

C.

Apply a compromising resolution approach, involving both groups.

D.

Ask the functional managers of both groups to help find a workable solution.

Question 506

A project is on schedule. However, during a site visit, a project manager notices that the contractor ' s productivity is low.

What should the project manager do?

Options:

A.

Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.

B.

Discuss the need to increase productivity with the contractor.

C.

Plan the close-out activities since the project is on schedule.

D.

Update the project schedule to align with the contractor ' s productivity.

Question 507

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Question 508

Developers spend most of the sprint writing code for user stories, leaving little time for testing. As a result, user stories cannot be tested in time and the stories remain unfinished by the end of the iteration, resulting in poor metrics.

What should the scrum master do first in this situation?

Options:

A.

Divide the user stories into two categories: development stories and test stories.

B.

Increase the number of developers on the team so stories are completed faster.

C.

Revalidate the team ' s velocity to ensure development and testing can be completed within the iteration.

D.

Request the developers work overtime to ensure the testers have enough time to perform their tests.

Question 509

A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?

Options:

A.

Asked the project sponsor to review the budget

B.

Updated the budget before moving to another stage of the project

C.

Added enough budget to cover all uncertainties

D.

Used past projects as a reference during budget estimations

Question 510

A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?

Options:

A.

Ask the least experienced team members to work as assistants to the more experienced team members so they can gain some project experience.

B.

Ask the project sponsor to replace the least experienced team members with more experienced ones.

C.

Identify how the team members with no experience can contribute according to their capabilities and provide training if needed.

D.

Assign critical project tasks to the most experienced team members as they are the only ones with the knowledge.

Question 511

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

Options:

A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.

Question 512

In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO ' s support?

Options:

A.

Update the stakeholder engagement plan to include the CEO.

B.

Meet with the CEO to review the current deliverables for the project.

C.

Identify the CEO ' s preferred method of communication.

D.

Send the updated project management plan and documents to the CEO.

Question 513

A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?

Options:

A.

Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.

B.

Separate the tender into two parts, one for the building and one for the equipment, with careful selection of contractors.

C.

Lock down the requirements for the equipment early and avoid any changes during further phases of the project.

D.

Put a fixed price contract out to tender for the research building and issue a cost-reimbursable contract for installing the equipment.

Question 514

During a sprint, the team is experiencing conflict because the customer asks for additional features that increase the complexity. The scrum master is trying to resolve the conflict.

Which approach should the scrum master use?

Options:

A.

Discuss the definition of done (DoD) with the customer.

B.

Approach the product owner to determine the next course of action and update the backlog.

C.

Discuss the acceptance criteria with customer.

D.

Perform backlog prioritization to ensure that everyone is working on the highest value features.

Question 515

A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?

Options:

A.

Ask the team to adapt based on their current resources.

B.

Plan a meeting with the stakeholders to get more resources.

C.

Replan the upcoming deliverables based on the available tools.

D.

Ask the project sponsor to provide the needed resources.

Question 516

A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor ' s feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.

How should the project manager mitigate this situation?

Options:

A.

Execute a retrospective meeting to solve the misalignment.

B.

Review the actions listed in the risk management plan.

C.

Review and update the organizational process assets (OPAs).

D.

Submit a change request to replace the product owner.

Question 517

The sponsor calls the project manager and questions why the stakeholders have not received updates for over 1 month. The project recently implemented a project management information system (PMIS) that provides real-time access to various project status measurements and information. The project manager is certain that all stakeholders have the opportunity and permissions for status updates.

How should the project manager proceed?

Options:

A.

Call and apologize to the team members and provide an update on how this issue was caused.

B.

Review the communications management plan and stakeholder engagement plan for the project.

C.

Request the operations support team to troubleshoot and determine the root cause of the issue.

D.

Obtain a list of the affected stakeholders and email the current status information to them.

Question 518

A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.

What should the project manager do?

Options:

A.

Demonstrate that risky projects are subject to change so adding reserves to the budget is a necessity.

B.

Explain to the project sponsor and key stakeholders the need to add the reserve and get their buy-in.

C.

Seek key stakeholders ' approval and finalize the budget with the reserve.

D.

Agree with the project sponsor and finalize the budget without the reserve.

Question 519

Two project team members are having difficulty communicating updates and issues. One team member prefers telephone calls for any kind of urgency, whereas the other team member prefers email communication. This difference results in a lack of understanding between the team members and sometimes hinders timely communication.

What should the project manager do?

Options:

A.

Ask the team members to resolve this issue themselves.

B.

Provide these team members with feedback that this issue is causing a delay.

C.

Ask the team members to follow the ground rules in the project management plan.

D.

Provide guidance to the team members to resolve the conflicts.

Question 520

A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.

What should the project manager do?

Options:

A.

Request human resources (HR) to help.

B.

Move the team member to another project.

C.

Confront the issue with the rest of the team directly.

D.

Ask other team members to be more welcoming.

Question 521

A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.

What should the project manager do?

Options:

A.

Give the team member some time to learn agile practices.

B.

Assign an agile mentor and follow the training process.

C.

Ask to increase the capacity of the team to finish on time.

D.

Ask the sponsor for additional budget for training.

Question 522

A railroad construction project is in the planning stage. During a monthly progress meeting, an external project manager from the sponsoring organization mentioned there is a potential delay in the design completion date. The external project manager wants to know the impact of this delay on the overall project completion date in the next monthly meeting.

Which three actions should the internal project manager take next? (Choose 3)

Options:

A.

Perform variance analysis.

B.

Validate the critical path method (CPM).

C.

Establish what-if scenario analysis.

D.

Determine the schedule performance index (SPI).

E.

Execute a Monte Carlo simulation.

Question 523

A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project

manager do to finish planning?

Options:

A.

Review project documents to identify and eliminate uncertainties and inconsistencies.

B.

Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.

C.

Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.

D.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

Question 524

During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager ' s influence, the project team is concerned about the overall impact to the project.

What should the project manager have done?

Options:

A.

Obtained a list of the critical stakeholders from the project sponsor

B.

Consulted with the project sponsor on stakeholder roles and responsibilities

C.

Identified and consulted stakeholders during requirements gathering

D.

Requested stakeholders to participate in project initiation and planning phases

Question 525

A project team is working together for the first time. During the first sprint, the project manager was asked to solve a prioritization conflict between the Scrum Master and the Product Owner related to a feature requested by an important customer.

How should the project manager resolve this conflict?

Options:

A.

Refer to the roles and responsibilities for the agile team.

B.

Schedule a meeting with the Scrum Master and Product Owner.

C.

Emphasize that the Scrum Master has the responsibility to conduct the sprint planning.

D.

Contact the customer to understand the request in order to make a decision.

Question 526

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

Options:

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager ' s knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

Question 527

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

Options:

A.

Analyze the communication needs of the stakeholders.

B.

Communicate the project details to the stakeholders.

C.

Communicate progress more frequently to the stakeholders.

D.

Introduce a separate stakeholder engagement meeting.

Question 528

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

Options:

A.

Share a work performance report with the team member ' s supervisor.

B.

Assign a mentor to work with the senior team member.

C.

Speak with the senior team member to identify the difficulties.

D.

Collect feedback from all team members about team performance.

Question 529

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

Options:

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

Question 530

During a sprint retrospective, the project manager notices that one of the team members does not achieve the sprint objectives on a regular basis. This team member is an experienced resource.

How should the project manager properly address this situation?

Options:

A.

Align the project goals with the team member.

B.

Reassign the team member to another project.

C.

Nominate the team member to receive agile training.

D.

Allocate another resource to support the team member.

Question 531

A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.

In closing this project midway, which activities should the project manager execute first?

Options:

A.

Perform contract, financial, and administrative tasks.

B.

Finalize the in-progress administrative tasks.

C.

Evaluate contract and administrative tasks.

D.

Execute financial and administrative tasks.

Question 532

The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?

Options:

A.

Assign a project team member to document exchanged communication for future reference.

B.

Assign the project sponsor as the point of contact for all provider communication.

C.

Ensure that all project stakeholders participate in the scope definition meetings.

D.

Establish a common language of terms with which to communicate with the provider.

Question 533

A project manager is reviewing the team ' s Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.

Will the project manager meet this objective?

Options:

A.

Yes, it will take 4 working days to complete these tasks based on the estimate.

B.

No, it will take 6 days to complete all these tasks based on the estimate.

C.

No, it will take 7 days to complete all these tasks based on the estimate.

D.

Yes, it will take 5 working days to complete these tasks based on the estimate.

Question 534

A project is starting its first iteration out of eight. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

Options:

A.

Assign a resource from the core team to handle the acquisition.

B.

Register a risk and escalate it to the project sponsor.

C.

Update the status report with information about this dependency.

D.

Register a risk and monitor its exposure variation.

Question 535

A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.

What should the project manager do first?

Options:

A.

Conduct a root cause analysis (RCA) and plan the correct actions to ensure completion of the tasks on time.

B.

Allocate another resource to help the team member to complete the tasks and meet the estimated activity time.

C.

Train the team member in the methodology to get the sufficient knowledge to meet the estimated activity time.

D.

Apply crashing to the strategic tasks to recover any time that was lost to bring the project on track.

Question 536

A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.

What should the project manager do to address this concern?

Options:

A.

Register the issue as a risk with the project team members.

B.

Review the project schedule with project team members and the suppliers.

C.

Advise the procurement department to develop a new supplier strategy.

D.

Use the procurement and risk management plans to manage this issue.

Question 537

To limit the amount of time and cost of using a contract programming firm, a product manager announces that the developers will not be paid for unrequested embellishments to the product. What should the development team and scrum master do to ensure they are paid for all their work?

Options:

A.

Have the product manager work with the scrum master to assign specialists to user stories to meet the requirement.

B.

Convert the story points on user stories to hours to provide estimates of the potential costs to the product manager.

C.

Ensure that the task board is used as an information radiator and all stories have enough detail to build the required feature or function.

D.

Refine the definition of done (DoD) for user stories to ensure that part of the completion is a verification review of the code.

Question 538

A team is performing above expectations, and the sponsor wants to expand the project scope to benefit the organization. However, there are only a few team members with the needed leadership experience.

What should the project manager do?

Options:

A.

Communicate the risks and propose hiring members with leadership experience before continuing with the request.

B.

Decline the scope expansion until the team members get appropriate leadership opportunities within the project.

C.

Implement the scope expansion and suggest the team members get a mentor due to their lack of leadership experience.

D.

Recognize each team member for their contributions and recommend them to the leadership development program.

Question 539

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

Options:

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Question 540

A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.

What should the project lead do?

Options:

A.

Use Pareto techniques to identify the knowledge required by the majority of the team.

B.

Recommend putting the project temporarily on hold and focus on onboarding and training.

C.

Develop a training curriculum and schedule training delivery throughout the project.

D.

Document the processes and organize a week-long, off-site meeting with the project team.

Question 541

A product owner is continuously adding requirements to a project that will significantly impact project delivery. How should the project manager address this?

Options:

A.

Reprioritize the work and add all new work to the product backlog.

B.

Check with the project team about their availability to continue project work.

C.

Consult with senior managers on how to address this to ensure the product owner ' s expectations are fully met.

D.

Ask the product owner to reprioritize and consider the project done when the highest priorities are delivered.

Question 542

A project team is defining the ground rules during their first meeting as a team. During this session, only a few of the team members suggested and approved the ground rules while most remained silent. As a result, the team ' s ground rules favor those few team members.

What should the project manager do?

Options:

A.

Conduct a round table and ask the team to share their opinions one by one.

B.

Propose new team ground rules and communicate them to all.

C.

Ask the silent team members to share their opinions via email.

D.

Perform focus group interviews based on the new team ground rules.

Question 543

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

Options:

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Question 544

A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.

What should the project manager do first?

Options:

A.

Gather additional information and ask the team to perform a root cause analysis.

B.

Update the master schedule to reflect the reprioritized deliverables.

C.

Ask the team to work with the product owner to reprioritize the backlog.

D.

Request additional information and discuss the feasibility options and impacts with the team.

Question 545

A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?

Options:

A.

This framework is not appropriate for agile.

B.

This is a learning experience for the agile team.

C.

An agile approach is easily adaptable.

D.

An agile approach is different.

Question 546

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.

What should the project lead do?

Options:

A.

Review the product backlog items to evaluate the impact on scope and prioritize accordingly.

B.

Develop a change request for more resources and update the project budget and schedule.

C.

Ask the internal legal department to evaluate if the regulatory law could be managed internally.

D.

Work with the team to develop an alternative solution with no additional effect on the project ' s budget.

Question 547

A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.

What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?

Options:

A.

Involve all of the stakeholders in the escalation by setting up a conference call.

B.

Escalate to the other party ' s management and inform the steering committee.

C.

Reach out to peer managers for similar escalation situations and follow past experiences.

D.

Review the established project escalation process and take the appropriate action.

Question 548

During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.

What should the project manager do?

Options:

A.

Ensure a continuous feedback environment is leveraged to improve the quality and overall satisfaction.

B.

Review the requirements and instruct the team to develop the deliverables according to the documentation.

C.

Mentor the team members and ensure they perform peer reviews of their work before implementation.

D.

Utilize the retrospectives to identify issues in the development phase that may cause deliverables to not be accepted.

Question 549

In an organization transitioning to agile, the project team is in the norming phase. Team members became uncomfortable when the project manager assigned reporting responsibilities to the newest team member. Team members began questioning the project manager ' s decision.

What should the project manager do?

Options:

A.

Invite team members to volunteer for roles for which they feel qualified.

B.

Revoke the delegated responsibilities to keep the team members harmonious.

C.

Remind team members that administrative decisions are the project manager ' s duties.

D.

Explain the rationale for delegating responsibilities to team members.

Question 550

A project is late due to a large number of scope changes. This was raised as a risk in the risk register during the initiation phase. The team is afraid that they will be blamed in case of failure and recommends that the project manager ask for an extension.

What should the project manager do first?

Options:

A.

Ask the sponsor for their advice on the way forward.

B.

Ask the team to document the impact of the risk in detail.

C.

Refer to the risk register and follow the mitigation plan.

D.

Refer to the change log and ensure that changes are documented.

Question 551

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?

Options:

A.

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.

B.

Update the schedule and project risk register according to the regulatory requirement.

C.

Consult the project management plan for guidance on addressing the regulatory requirement.

D.

Assess the impact of implementing the potential regulatory requirement on the project.

Question 552

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor ' s concerns?

Options:

A.

Document the team member ' s mistake in the lessons learned.

B.

Train the team member to improve their performance to avoid future mistakes.

C.

Talk with the team member to identify the reason for the mistake.

D.

Relocate the team member to another project due to the mistake.

Question 553

A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.

What should the project leader do next?

Options:

A.

Organize a meeting between the product owner and the sales manager.

B.

Invite the sales manager to the next sprint review.

C.

Organize a demo for the sales manager with the development team.

D.

Invite the sales manager to the sprint retrospective.

Question 554

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.

What should the project manager of the contracting company do?

Options:

A.

Record that the delay is attributable to the client and request a meeting.

B.

Check the contractual terms about liquidated damages and reject if not applicable.

C.

Meet with the sponsor to analyze the delays and the associated liquidated damages.

D.

Schedule a detailed analysis of the delays using cause and effect.

Question 555

A project sponsor indicates that the time frame for a project needs to be shortened. The project network diagram cannot be modified, but there are extra resources available in the company.

What action should the project manager take?

Options:

A.

Crash the project schedule.

B.

Conduct earned value management (EVM) analysis.

C.

Fast track the project.

D.

Perform Monte Carlo analysis.

Question 556

A team member mentions to the scrum master that the user stories are too long. The team member believes this may be the cause of the team ' s inability to deliver value for stakeholders.

What should the scrum master do?

Options:

A.

Review the user stories with the team and ask the product owner to break them down into more manageable units.

B.

Review the user stories with the stakeholders and ask the product owner to break them down into more manageable units.

C.

Ask the team member to suggest using shorter user stories to the product owner so that the next sprint can move faster.

D.

Ask all the team members for their views about using shorter user stories so that value can be created for stakeholders.

Question 557

A company has decided to create a new product to prepare itself for the changing economy. The technology required for the new product is not well understood yet, and the requirements are still being debated.

Which approach should the project manager advise for this project?

Options:

A.

Lean

B.

Predictive

C.

Agile

D.

Hybrid

Question 558

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

Options:

A.

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Question 559

A project schedule ' s risk level continues to increase during project execution because sprints are consistently delivering less than the intended results. The project manager becomes concerned that the deliverable will be delayed and cost more than the project sponsor intended.

What should the project manager do first?

Options:

A.

Engage with the project team to understand the schedule risk problem and present a solution to the project sponsor.

B.

Conduct a risk review meeting to gain a better understanding of the schedule, then document the results.

C.

Schedule a meeting with the scrum master to explain that adding additional sprints is necessary to reduce risks.

D.

Notify the project sponsor of the schedule risk and request support to increase the project budget.

Question 560

During project execution, a project manager is leading the team to work on the project schedule. During a meeting, the team has difficulty understanding the complexity of a task and is unable to provide an estimate for the required resources.

What should the project manager do first to resolve this issue?

Options:

A.

Register the issue as a risk in the risk register.

B.

Report to the sponsor that there is a new challenge in the project.

C.

Engage an external expert to provide the estimation.

D.

Refer to the organization ' s lessons learned from past projects.

Question 561

An experienced project manager has been assigned to a hybrid project that requires an extensive amount of information to be updated. Which tool should the project manager use along with the team?

Options:

A.

Pareto chart

B.

Kanban board

C.

SharePoint

D.

Excel files

Question 562

An agile team member discovers an impediment that is preventing them from doing their work efficiently. At which of the meetings should they bring up this impediment for resolution?

Options:

A.

Sprint review meeting

B.

Retrospective meeting

C.

Daily Scrum meeting

D.

Sprint planning meeting

Question 563

A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.

How should the project manager handle the situation?

Options:

A.

Inform the team member that decisions were already made and feedback should have been provided in the past.

B.

Schedule a meeting to review the team member ' s concerns and revisit the decisions if required.

C.

Explain to the team member that it is mandatory that they increase their participation in project meetings.

D.

Add the team member ' s concerns to the risk register and discuss them during the next regular meeting.

Question 564

A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.

What should the project manager do?

Options:

A.

Give some advice to the team member to reduce their stress and anxiety.

B.

Review team participation in the next retrospective meeting with all team members.

C.

Reach out to the team member to discuss and address their concerns as soon as possible.

D.

Evaluate upcoming project deadlines and reorganize team member assignments.

Question 565

A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.

What should the project manager do first?

Options:

A.

Meet with the team to define together a plan that would help them deliver despite the budget cuts.

B.

Work with the team to understand what can motivate them to try and complete the project.

C.

Remind the team of their commitment with the client and the need to adapt to the client ' s needs.

D.

Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.

Question 566

A project manager notices that an extroverted project team member appears to be increasingly controlling the direction of the entire team. The other team members are not complaining but seem to be more passive.

What should the project manager do?

Options:

A.

Meet with each team member to better understand the situation.

B.

Meet with the extroverted team member and ask them to be more sensitive to others.

C.

Address the situation in a team meeting and ask everyone to be more active.

D.

Observe the team dynamics closely and step in if a team member complains.

Question 567

A project management office (PMO) is following the execution of an organization ' s critical project. Some of the project phases are experiencing serious delays due to an international supply chain crisis. Project team members suggested revisiting the planned project phases to maintain the project ' s value delivery.

What should the project manager do?

Options:

A.

Schedule a meeting with the project sponsor to report and discuss the issue.

B.

Update the project schedule in response to the external crisis.

C.

Develop a contingency plan and seek alternative suppliers.

D.

Assess and consolidate projects phases and update the project management plan.

Question 568

A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?

Options:

A.

Create incentives to promote better communication among team members.

B.

Assign the work packages based on geographical working groups.

C.

Understand and consider the emotions of each team member.

D.

Plan for communication training workshops for all team members.

Question 569

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

Options:

A.

Create a communications management plan.

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a kanban board.

D.

Send a copy of the project charter to all project stakeholders.

Question 570

A project team is using a vendor solution. The project team has been notified that the vendor solution will no longer be on the premises, but in the cloud. The cloud transition will require additional infrastructure resources and adherence to new security standards.

What should the project manager do first?

Options:

A.

Initiate a change request for covering additional security scope.

B.

Research alternative vendor solutions for on-premise security.

C.

Ask the sponsor to provide security training for the project team.

D.

Schedule a meeting with security to understand the standards.

Question 571

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

Options:

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team ' s workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Question 572

A project manager is confused when the operational results from previous iteration solutions have not been acceptable to the client. Team members have already delivered all previous solutions, which were accepted by the client as complete.

What should the project manager do?

Options:

A.

Recommend a change in the project methodology or the approach.

B.

Develop and execute a stakeholder engagement strategy.

C.

Determine the criteria and measuring systems for objective success.

D.

Allocate more time for mentoring project team members.

Question 573

An important project to build a new airport was suddenly stopped because of the complaints from residents in the surrounding communities. The residents stated that they were not consulted and that the project would cause ecological and pollution damage.

What should that project manager have done first in order to avoid this situation?

Options:

A.

Identified the stakeholders and their expectations

B.

Presented the project to the community

C.

Added this situation to the risk register

D.

Added these requests to the project scope statement

Question 574

During a sprint, the product owner requested a change in the features to be delivered in the same sprint. According to the product owner, the request from the customer is due to regulatory reasons and they have a deadline to meet.

What should the project manager do?

Options:

A.

Perform the change only if it has a higher or equivalent priority of the current remaining features.

B.

Submit the feature changes to the change control board (CCB) so they can evaluate and approve.

C.

Follow the plan by delivering the features and handle the change later in the project.

D.

Discuss with the stakeholders about the possibility of accommodating the feature changes.

Question 575

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?

Options:

A.

Relocate the project to another country that is not shutting down.

B.

Evaluate the possibility of having another country complete the task.

C.

Identify additional team members who are able to complete the task.

D.

Determine if the project has built-in slack to remain on schedule.

Question 576

A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?

Options:

A.

Send the team to a data center optimization training workshop.

B.

Partner with a company that is an expert in this area.

C.

Outsource the data center optimization work to a vendor.

D.

Request a budget to build this competency among project team members.

Question 577

As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?

Options:

A.

Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.

B.

Schedule a working session with the project sponsor to review the project charter and estimate the cost per project phase.

C.

Review historical project files and lessons learned to identify a similar project and adapt the budget used in the historical project.

D.

Ask key project stakeholders to estimate the cost of delivering the project, then calculate an average that can be used for the budget.

Question 578

The project team is conducting iteration planning and having difficulty evaluating a new technology that will be used in this iteration. What should the project lead do?

Options:

A.

Hire an external subject matter expert (SME) to help with design and implementation.

B.

Coach the team to determine a path forward to achieve an efficient solution.

C.

Provide technical guidance on complexity assessment.

D.

Guide the team with estimating the time required.

Question 579

A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?

Options:

A.

Schedule meetings every 2 days at the same time with all team members.

B.

Organize a daily meeting for all team members and extend it, if required.

C.

Schedule meetings every 2 days that align with team members ' time zones.

D.

Organize a standard meeting time to engage all of the team members.

Question 580

During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?

Options:

A.

Wait for the next project status meeting to evaluate the impact of one less resource.

B.

Ask the project sponsor to replace the resource immediately.

C.

Record the situation in the issue log immediately and evaluate the impact of losing the resource.

D.

Freeze the activities of the lost resource until they are replaced.

Question 581

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

Options:

A.

Set up regular project status meetings and invite all team members.

B.

Encourage the team to define the ground rules for performance.

C.

Set up individual calls to follow up on each team member ' s progress.

D.

Invite team members to an informal meeting to get to know one another.

Question 582

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

Options:

A.

Assess the opportunities to deliver project value incrementally

B.

Gather all the requirements’ details and schedule a refinement meeting

C.

Prepare a project management plan for the full scope using an agile approach

D.

Approve a change request to change the project approach to agile

Question 583

One-on-one interviews with members of an agile team reveal that they distrust an expert member. Their explanations seem to point to the expert’s communication style in daily coordination meetings, which team members interpret as avoiding accountability.

What two actions should the project manager take to address the situation? (Choose 2)

Options:

A.

Instruct the expert member to avoid phrases that make the team uncomfortable.

B.

Help the team gain trust in the expert by describing the expert’s experience.

C.

Encourage the team to respectfully ask questions to promote clear communication.

D.

Help the expert member feel secure enough to communicate more freely.

E.

Remind the team that all communications are valid and worthy of trust.

Question 584

A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive pieces of equipment. The project manager is aware that some purchasing amounts require higher levels of approval.

What should the project manager do to properly manage the purchase of equipment?

Options:

A.

Agree on a purchasing approval escalation method according to organizational governance.

B.

Ask the organization to allow the project manager to approve all of the purchases.

C.

Propose that the project sponsor approve all of the pieces of equipment that need to be purchased.

D.

Replace the most expensive pieces of equipment with cheaper ones to allow easier purchase approval.

Question 585

A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?

Options:

A.

Discuss the risk response strategies with the stakeholders

B.

Add buffers to the schedule to accommodate unforeseen changes

C.

Ensure the risk register includes all identified risks

D.

Develop a communications management plan to share updates with stakeholders

Question 586

An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and provides regular status reports.

What should the project lead do to satisfy the customer?

Options:

A.

Schedule a meeting with the customer and let them know that the team is new to agile and the situation will improve.

B.

Review the situation with the customer and make the required adjustments with the team.

C.

Reduce the frequent communication with the customer and improve the format of the status reports to include the team’s progress.

D.

Review the progress of the project with the customer and modify the frequency of sprint reviews.

Question 587

A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?

Options:

A.

Conduct a retrospective meeting to identify what went well and what went wrong.

B.

Review the email marketing standards of that country with the stakeholders.

C.

Schedule a meeting with project team members to identify the root cause.

D.

Schedule additional country-specific user testing to reduce email opt out.

Question 588

A project manager is leading a software development project with agile practices and has outsourced work to three well-qualified subcontractors. Over time, problems arise related to supply-chain management, and the project manager considers replacing the subcontractors with new suppliers. What should the project manager have done to avoid this problem?

Options:

A.

Hired more Scrum Masters so every Scrum Master manages one supplier.

B.

Escalated the issue to the product owner to seek possible solutions.

C.

Engaged the suppliers by category and validated the strategy with stakeholders.

D.

Created user stories for the suppliers and saved their qualification records to the backlog.

Question 589

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?

Options:

A.

Revise the project schedule with the customer

B.

Schedule a meeting with the project team to address timelines

C.

Negotiate revised timelines with the project sponsor

D.

Discuss the situation with the project team member

Question 590

A project manager is assigned to an IT project to deliver a new accounting system. Some managers at the company do not see the value of this project and say they will not use the new system. What two actions should the project manager take? (Choose 2)

Options:

A.

Review the list of stakeholders that will be affected by starting this business initiative.

B.

Continue with the project the way it was planned and validated by the sponsor.

C.

Describe the outcome of the project and business value to all company stakeholders.

D.

Add this issue to the risk register and monitor stakeholder engagement at the next milestone.

E.

Modify the project management plan and scope of work to avoid future difficulties.

Question 591

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed, which impacts the project schedule.

What should the project manager do?

Options:

A.

Arrange a meeting with the two departments to understand their differences and address their needs.

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments.

C.

Work with the project team to find a compromise solution that suits both departments.

D.

Assess the risk of postponing this specific solution and advise both departments of the delay.

Question 592

A project manager is leading a highly visible project initiative. A few weeks after kickoff, the project manager starts receiving requests for updates from various stakeholders. What should the project manager do?

Options:

A.

Remove those stakeholders from the project since they may negatively affect project goals

B.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed

C.

Schedule a meeting with relevant stakeholders to review the project communications plan

D.

Explain to the stakeholders that they must request project updates from the project sponsor

Question 593

A project manager is struggling to provide timely updates to the project team due to team members being spread across multiple time zones. Which communications method should the project manager utilize in this situation?

Options:

A.

Interactive communication

B.

Public communication

C.

Pull communication

D.

Push communication

Question 594

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department.

What should the project manager do to align with this requirement?

Options:

A.

Leverage the enterprise environmental factors (EEFs).

B.

Review the statement of work (SOW).

C.

Perform a make-or-buy analysis.

D.

Refer to the organizational process assets (OPAs).

Question 595

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder in order to provide necessary resources. However, the stakeholder is refusing to get involved because the stakeholder believes there is no benefit in using the project deliverable.

What should the project manager do to resolve this?

Options:

A.

Meet with the stakeholder to discuss the impact of the deliverable.

B.

Escalate to the project sponsor due to the political nature of the issue.

C.

Consider the stakeholder as a risk and evaluate possible solutions with the project team.

D.

Improve communication with the stakeholder to obtain their assistance in the future.

Question 596

A self-organized project team is sharing facilitator responsibilities, with each person on the core team taking turns serving as facilitator to enable communication, collaboration, and engagement. One of the team members acting as facilitator missed an email from the project client regarding an important change. This oversight caused a project delay and significant rework.

Where does the accountability for this oversight reside?

Options:

A.

The team should take accountability based on the decentralized project management style.

B.

The project sponsor who approved the decentralized project management style should be held accountable.

C.

The team member facilitator who missed the email should be held accountable.

D.

The working agreement should be accountable since it did not cover situations involving oversight.

Question 597

A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded, and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan, which the team member believes will be cheaper and equally effective.

What should the project manager do?

Options:

A.

Evaluate the new proposal with the project team to determine if it is a more beneficial alternative.

B.

Adhere to the issue response proposed in the risk management plan, as it is the agreed-upon solution.

C.

Ask the project team member to write a formal email explaining the proposal and send it to the change control board (CCB).

D.

Implement the new proposal as soon as possible, as it is supposed to be cheaper and equally effective.

Question 598

A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?

Options:

A.

Increase the sprint duration to accommodate the additional work

B.

Conduct a root cause analysis before addressing the issue

C.

Escalate the issue to the stakeholder ' s functional manager

D.

Cancel the one-on-one sessions and obtain the information via email

Question 599

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

Options:

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

Question 600

A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?

Options:

A.

A decrease in the project cost

B.

An increase in the project risk

C.

Additional project scope

D.

Additional resources

Question 601

A project manager is leading a contract for a new market that was awarded to their company. The client wants to jump-start the market with the informal sector traders.

What should the project manager do?

Options:

A.

Plan the project in phases, starting with the informal sector, to deliver business value to the client quickly.

B.

Divide the project team into groups to execute the project as small parallel projects, including the informal sector.

C.

Execute the projects simultaneously following the project schedule and the communications management plan.

D.

Gather requirements and convert them into backlog items to quickly deliver value to the client.

Question 602

A project manager is leading a team that is delivering new software to a finance team. The new software will streamline the finance team’s monthly closing activities and reporting.

What should the project manager use to promote knowledge transfer for the new solution?

Options:

A.

Project documents

B.

User handbook

C.

End-user training

D.

Support portal

Question 603

A project is in its fourth iteration out of eight with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable not visible in the status report. What should the project manager do?

Options:

A.

Include the deliverable in the status report and resend it to the stakeholder

B.

Invite the stakeholder to the next iteration review

C.

Invite the stakeholder to the next daily meeting

D.

Schedule a meeting with the stakeholder to review the status report

Question 604

An organization is about to start a time-critical project and has decided to use an agile approach for the first time. However, stakeholders are worried that they will not be able to verify the status of the project, since they believe that their usual governance model will not work for an agile project.

What should the project manager do?

Options:

A.

Recommend following the existing governance structure with the project team.

B.

Meet with stakeholders to discuss and review the governance structure.

C.

Review the governance structure to reflect scope changes.

D.

Discuss using a hybrid governance structure with stakeholders.

Question 605

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?

Options:

A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.

B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.

C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.

D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.

Question 606

A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?

Options:

A.

Remove the current backlog item from the sprint and replace it with defect fixing

B.

Remove the current backlog item from the sprint and replace it with a similar item

C.

Update the backlog and advise the team to add this to the acceptance criteria

D.

Update the product backlog and include the change as a high priority for the next iteration

Question 607

A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?

Options:

A.

Evaluate the sprint backlog

B.

Evaluate the product backlog

C.

Evaluate the sprint increment

D.

Evaluate the product development cycle

Question 608

A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?

Options:

A.

Add more resources to complete the remaining deliverables early.

B.

Review and analyze the risks associated with compressing the schedule.

C.

Prioritize critical activities and skip noncritical activities.

D.

Perform several activities in parallel to compress the schedule.

Question 609

A project is in its fourth iteration out of eight, with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable that is not visible in the status report.

What should the project manager do?

Options:

A.

Invite the stakeholder to the next iteration review.

B.

Include the deliverable in the status report and resend it to the stakeholder.

C.

Invite the stakeholder to the next daily meeting.

D.

Schedule a meeting with the stakeholder to review the status report.

Question 610

During daily team coordination meetings, team members constantly ask which tasks they should focus on first.

How should the project manager ensure the team is fully productive?

Options:

A.

Encourage project team members to prioritize the product backlog.

B.

Work with the product owner to ensure the project backlog is prioritized.

C.

Ensure team members are working according to the project management plan.

D.

Review the project backlog during the team’s coordination meeting.

Question 611

A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?

Options:

A.

Plan the risk responses and assign risk response owners.

B.

Start monitoring and controlling the identified risks.

C.

Proceed with executing the risk management plan.

D.

Spend the contingency budget on the identified risks.

Question 612

A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?

Options:

A.

Negotiate with operations to absorb the cost while the product is launched and remediate the issue.

B.

Engage with the sales team to increase the sales price since it is a breakthrough product.

C.

Evaluate the most cost-effective containment action and use their influence to implement it.

D.

Assess what corrective action is appropriate and use their influence to implement it.

Question 613

A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project. Which approach should the project lead choose to deliver business value?

Options:

A.

Subdivide project tasks to find the minimum viable product (MVP)

B.

Identify and communicate clear risk mitigation plans

C.

Recommend predictive project management to the sponsors

D.

Ensure commitment from sponsors on executing the project until it ends

Question 614

A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?

Options:

A.

Schedule a meeting with stakeholders and explain the situation.

B.

Discuss the situation with the sponsor and seek their guidance.

C.

Arrange a time to meet with the team to understand the parameters.

D.

Meet with the team to understand the areas of concern.

Question 615

A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?

Options:

A.

Improve the configuration management process

B.

Register an issue for the missing documents

C.

Ensure the lessons learned register is up to date

D.

Review the quality assurance (QA) processes

Question 616

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget.

What should the project manager do first to obtain the funding to hire the needed resources?

Options:

A.

Introduce a change request.

B.

Update baselines to accommodate the delay.

C.

Use management reserves.

D.

Ask the sponsor for additional financial resources.

Question 617

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

Options:

A.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.

Escalate the issue to the sponsor and register the new risk response in the project documents

C.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.

Submit a change request to perform a different issue response than what is registered in the risk management plan

Question 618

Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget. What should the project manager do first to obtain the funding to hire the needed resources?

Options:

A.

Ask the sponsor for additional financial resources

B.

Introduce a change request

C.

Use management reserves

D.

Update baselines to accommodate the delay

Question 619

The project team has reviewed the requirements and identified some concerns. The project sponsor has asked the team how they will handle each concern. What should the project manager do next?

Options:

A.

Work with the project team to assess the severity of each risk.

B.

Collaborate with the stakeholders on the communications management plan.

C.

Consult with team members to produce a Monte Carlo simulation diagram.

D.

Develop a mitigation strategy for each risk and update the risk register.

Question 620

A software development project was recently initiated. One of the project team members is regularly questioning the project’s risk response strategy. The team member vocalizes their doubts during the daily standup meeting to share concerns regarding how the project should handle risks.

What should the project manager do first?

Options:

A.

Utilize the daily meetings to respond to the concerns.

B.

Assign each concern to the appropriate team member.

C.

Meet with the individual to understand their concerns.

D.

Escalate the team member’s concerns to the project sponsor.

Question 621

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

Options:

A.

Escalate this issue to the project sponsor.

B.

Communicate the full details of the project activities to the stakeholder and solicit input.

C.

Analyze this stakeholder’s interest and impact.

D.

Share the summary of the project activities with the stakeholder and conclude the project.

Question 622

There are several dependent work streams in a project. Some of the project stakeholders feel that coordination among project team members and progress visibility are lacking.

What should the project manager do?

Options:

A.

Escalate the concerns to the project steering committee.

B.

Review and update the communications management plan.

C.

Organize a team meeting to review the project status.

D.

Discuss the concerns with the project sponsor.

Question 623

After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?

Options:

A.

Update the risk register and escalate it to the sponsor

B.

Assist the team in proposing a minimum viable product (MVP)

C.

Request the stakeholders to reduce the project backlog to finish on time

D.

Ask to increase the capacity of the team to deliver the project on time

Question 624

During a weekly project review, the project manager becomes aware that a senior stakeholder is not reviewing and approving documents in a timely manner. This is causing delays for several less experienced and junior team members.

How can the project manager resolve this issue?

Options:

A.

Discuss the approval process with the team members for future improvement.

B.

Review the project communication management plan and approval process with the stakeholder.

C.

Coach the junior team members on how to handle conflicts within the project.

D.

Ask the sponsor to meet with the stakeholder to have them review documents in a timely manner.

Question 625

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

Options:

A.

Register the risk and provide appropriate response options.

B.

Register the risk and prioritize the implementation strategy.

C.

Register the risk and escalate it to the procurement team.

D.

Register the risk and escalate it to the project sponsor.

Question 626

An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?

Options:

A.

Reduce the projects’ scope to meet the upcoming target dates.

B.

Crash the schedule from the delayed projects to meet upcoming target dates.

C.

Fast-track the delayed projects so they can meet upcoming target dates.

D.

Ask for project sponsor approval to revise the upcoming target dates.

Question 627

A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?

Options:

A.

Create a list of the tasks and send it to the project sponsor for review and approval.

B.

Develop a work breakdown structure (WBS) that decomposes the project deliverables into work packages.

C.

Schedule a meeting with the stakeholders to determine which tasks can be eliminated.

D.

Prepare a resource management plan that details all the resources needed to complete the tasks.

Question 628

The project team embraces and encourages open communication and collaboration. However, the project manager is used to an approach based on the chain of command and formal hierarchy.

What should the project manager do?

Options:

A.

Allow the team members to pick the model they are most comfortable with.

B.

Understand team concerns, organizational culture, and previous lessons learned.

C.

Discuss the situation with senior team members and make a collective decision.

D.

Obtain direction from the senior executive team and file a change request.

Question 629

A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?

Options:

A.

Evaluate the new proposal with the project team to determine if it is a more beneficial alternative

B.

Adhere to the issue response in the risk management plan as it is the agreed-on solution

C.

Implement the new proposal as soon as possible since it is cheaper and equally effective

D.

Ask the team member to write a formal email explaining the proposal and send it to the change control board (CCB)

Question 630

Shipping problems are impacting the supply chain worldwide, and the project ' s primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?

Options:

A.

Note the information but refrain from recording it as an issue because the project has not yet placed the order.

B.

Request the procurement team to find another vendor that has available stock of this equipment.

C.

Update the risk and continue to monitor developments by keeping in touch with the vendor.

D.

Request the vendor to provide specific information about the delivery delays before taking any action.

Question 631

A new project manager has been assigned to a recently approved project. The project has a multimillion-dollar budget and will require the purchase of expensive equipment. The project manager is aware that some purchase amounts require higher levels of approval. What should the project manager do to properly manage the purchase of equipment?

Options:

A.

Agree on a purchasing approval escalation method according to organizational governance

B.

Replace the most expensive equipment with cheaper ones to allow easier purchase approval

C.

Ask the organization to allow the project manager to approve all purchases

D.

Propose that the project sponsor approve all equipment that needs to be purchased

Question 632

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?

Options:

A.

Assign a business analyst to build detailed requirements so the project manager can estimate the project duration

B.

Explain that the team will build a production prototype model to help the customer visualize how the features should work

C.

Add extra time and resources to the estimating phase to accommodate the lack of requirements

D.

Raise a risk that scoping and estimating will be delayed if the customer cannot approve requirements

Question 633

A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?

Options:

A.

Schedule a conference call with the project team.

B.

Schedule meetings with individual members.

C.

Send email communications to all members.

D.

Distribute the progress report and risk register.

Question 634

A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes.

What should the project manager have done to avoid this issue?

Options:

A.

Delegated the quality assurance (QA) tasks to the team lead.

B.

Ensured that the new team member had access to the quality management plan.

C.

Obtained external training in quality assurance (QA) for the new team member.

D.

Made sure that the new team member understood all of the requirements.

Question 635

An increment was delivered to the customer at the end of a sprint. The customer complains that the product does not meet the expected quality and will require some rework. What should the project manager do next?

Options:

A.

Review the evidence of the quality assurance (QA) activities performed.

B.

Perform an analysis of the impact caused by the required rework.

C.

Include time in the next increment for quality assurance (QA) inspections.

D.

Confirm with the customer the expected quality in the next increment.

Question 636

A project manager has been tasked with developing a project schedule with fully detailed requirements. The project manager reaches out to subject matter experts (SMEs) for their initial thoughts on task duration. The project manager is concerned when these estimates appear to differ significantly. What should the project manager do to help with the estimate development?

Options:

A.

Ask the SMEs to hold up cards that show their estimate, discuss the highest and lowest estimates, and then estimate again.

B.

Recommend using an iterative approach, with a focus on estimates, that the SMEs agree with.

C.

Use historical information to help guide the estimates that were proposed by the SMEs.

D.

Escalate to the project sponsor and explain the differences in the estimations coming from the SMEs.

Question 637

A project manager has been informed by a vendor that a shipment with supplies needed for the project will be delayed by six weeks. What should the project manager do first?

Options:

A.

Find another vendor to deliver the required supplies on time

B.

Ask the procurement manager to resolve the issue with the vendor

C.

Document this as a risk and define a risk response plan

D.

Treat the risk as an issue and launch the risk response plan

Question 638

A project manager is leading a highly visible project initiative. A few weeks after the kickoff, the project manager starts to receive requests for updates from various stakeholders.

What should the project manager do?

Options:

A.

Explain to the stakeholders that they must request project updates from the project sponsor.

B.

Schedule a meeting with relevant stakeholders to review the project communications plan.

C.

Invite all project stakeholders to join the daily standup meeting to ensure they are informed.

D.

Remove those stakeholders from the project since they may negatively affect the goals of the project.

Question 639

A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved and developers have started work on the final application. What should the project manager do next?

Options:

A.

Be firm with the stakeholder, since they would push through any unreasonable requirement

B.

Document the stakeholder ' s requirements and validate those requirements by engaging stakeholders more often

C.

Inform the stakeholder that little can be done at this time, since core development has begun and the project must be delivered on time

D.

Inform the stakeholder that the requirement will be included in the next deliverable cycle

Question 640

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately.

How should the project manager approach the software development life cycle with this customer?

Options:

A.

Raise a risk that the scoping and estimating phase of the project will be delayed if the customer cannot deliver an approved set of requirements.

B.

Add extra time to the estimating phase of the project as well as additional resources to accommodate the lack of requirements.

C.

Assign a business analyst to build a detailed set of requirements with the customer so the project manager can properly estimate the project duration.

D.

Explain to the customer that the team will build a production prototyping model to help the customer visualize how the additional features should work.

Question 641

A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when the project deliverables are considered complete.

How should the project manager respond?

Options:

A.

Items are considered complete when they satisfy the definition of done (DoD).

B.

The scrum master will approve the user stories that are complete.

C.

Backlog items are considered complete when the product owner approves the demo.

D.

At the end of each sprint, the outcome is considered ready for production.

Question 642

A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed.

What should the project manager do?

Options:

A.

Negotiate revised timelines with the project sponsor.

B.

Revise the project schedule with the customer.

C.

Discuss the situation with the project team member.

D.

Schedule a meeting with the project team to address timelines.

Question 643

A project manager notices that a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories.

What should the project manager do first?

Options:

A.

Escalate the issue to the stakeholder’s functional manager.

B.

Increase the sprint duration to accommodate the additional work.

C.

Conduct a root cause analysis before addressing the issue.

D.

Cancel the one-on-one sessions and obtain the information via email.

Question 644

During project implementation, a critical performance issue is identified by team members.

What should the project manager do?

Options:

A.

Work with the project stakeholders to address the performance issue.

B.

Review the tender requirements on the related performance issue.

C.

Pass the performance issue to subject matter experts (SMEs) to handle.

D.

Submit a change request to handle the performance issue.

Question 645

A company is engaged in a transformation journey, and the project manager for this endeavor is new to the project. During one of the project status update meetings, a key stakeholder, who is also the project manager’s functional manager, is dissatisfied with the work in progress and points to the project manager.

What should the project manager do?

Options:

A.

Show the functional manager that the progress is on time based on the schedule.

B.

Admit that the functional manager is right and promise to rectify the situation immediately.

C.

Schedule a one-on-one meeting with the functional manager to prove the project is on time.

D.

Listen carefully and show understanding of the growing needs of the functional manager.

Question 646

A project manager is leading a project with a risk management plan detailing strategy and actions if any of the identified risks become an issue. One of the identified risks becomes an issue, but the project manager acknowledges that the response considered in the risk management plan may not be the best.

What should the project manager do?

Options:

A.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand.

B.

Submit a change request to perform a different issue response than what is registered in the risk management plan.

C.

Escalate the issue to the project sponsor and register the new risk response in the project documents.

D.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan.

Question 647

A project lead conducted coordination meetings to estimate the budget and confirm the timeframe for a new project. Due to internal resource challenges, outsourcing some activities could be implemented during execution. What should the project lead ensure before submitting the project for a stage gate review to receive the needed investment?

Options:

A.

Add a percentage for management reserve

B.

Conduct a retrospective with all involved stakeholders

C.

Initiate a recruitment plan to explore the market situation

D.

Align with relevant stakeholders on the procurement strategy

Question 648

During the team’s daily meetings, the project manager notices that some team members are consistently experiencing blockers due to communication issues and misunderstanding process directions.

How should the project manager proceed in this situation?

Options:

A.

Hold coaching sessions to further educate these team members.

B.

Take the current velocity into account for the next iteration planning.

C.

Request that these team members improve their performance.

D.

Instruct the team members on how to remove project obstacles.

Question 649

An experienced project manager has recently joined a jeopardized project. The project is being impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot add a new vendor, and the project must be completed within a maximum of 90 days as agreed.

What should the project manager do?

Options:

A.

Reach out to the vendor to determine a plan to get the project back on track.

B.

Review lessons learned from previous projects and take action accordingly.

C.

Request that the vendor provide the servers on time, as penalties may be applied.

D.

Wait until the project deadline is reached in order to use the contingency funds.

Question 650

An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?

Options:

A.

Request the vendor to provide the servers on time as penalties may be applied

B.

Wait until the project deadline is reached in order to use contingency funds

C.

Reach out to the vendor to determine a plan to get the project back on track

D.

Review lessons learned from previous projects and take action accordingly

Question 651

A project manager is leading a hybrid project in which one technical team executes tasks using an agile approach, while a second team executes other tasks using a predictive framework. These teams are struggling to cooperate effectively, and several delays have occurred in transmitting information and coordinating activities.

What should the project manager do?

Options:

A.

Ask the agile team to establish the working rules for both project teams.

B.

Meet with senior team members of both project teams to establish the working rules for the project.

C.

Ask the predictive team to establish the working rules for both project teams.

D.

Meet with the project sponsor to establish the working rules for the project and inform both project teams.

Question 652

A project manager recently took over an ongoing project. Within a few weeks on the project, the project manager discovers that there are continuous change requests from different project end users. What is the probable cause for this?

Options:

A.

Undefined change control process

B.

Unidentified project risks

C.

Improper work breakdown structure (WBS)

D.

Incomplete requirements

Question 653

An agile project team is working on a large project involving multiple cross-functional teams in different geographical locations. Some team members are not clear on the next tasks.

Which strategy should the project lead implement to help the team?

Options:

A.

Review the prioritized backlog with the project team.

B.

Review the action items with the respective project team members.

C.

Review the project objectives at the next team meeting.

D.

Review the work scope with the functional managers and their teams.

Question 654

A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?

Options:

A.

The interdependencies between the deliverables

B.

The business continuity plan of the deliverables

C.

The stakeholder engagement plan

D.

The user stories and story points

Question 655

A project team has been tasked with delivering robotics to automate a manufacturing line. The technical teams are all in place and have the technical information needed to build and install the robots. What other factors should be considered when planning this project?

Options:

A.

Software, security, and infrastructure.

B.

Industry standards and research.

C.

Safety and organizational culture.

D.

Financial and market conditions.

Question 656

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.

What should the project manager do next?

Options:

A.

Meet with the stakeholder to understand what is causing the delays.

B.

Discuss the need to influence this stakeholder with the sponsor.

C.

Facilitate a brainstorming session to find potential workarounds.

D.

Capture this in the issue log and escalate it to the project sponsor.

Question 657

A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?

Options:

A.

Invite all stakeholders to status meetings.

B.

Identify and categorize the stakeholders.

C.

Interact individually with the stakeholders.

D.

Recognize the diversity of the stakeholders.

Question 658

During the planning phase of a project, there is one activity for which duration and cost cannot be estimated. A project team member recalls that this activity was performed previously in another project in the company.

What should the project manager do so the project can move forward?

Options:

A.

Advise the team to estimate the activity individually, then validate it as a team.

B.

Consult artifacts from the other project to benchmark the activity.

C.

Work backwards from the deadline to estimate the project activity.

D.

Engage people from the other project team to complete the activity.

Page: 1 / 220
Total 2196 questions