Summer Sale- Special Discount Limited Time 65% Offer - Ends in 0d 00h 00m 00s - Coupon code: netdisc

PMI PMP Project Management Professional (2025 Version) Exam Practice Test

Page: 1 / 199
Total 1988 questions

Project Management Professional (2025 Version) Questions and Answers

Question 1

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

Options:

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Question 2

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

Options:

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team's workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Question 3

A project manager is managing the opening of a new office overseas. At the beginning of the project, possible delays due to legal permits are raised by one stakeholder. Subject matter experts (SMEs)

reassessed the concern and suggested assigning more time for this permit, and the change control board (CCB) agrees.

Which document should the project manager update first to document this change?

Options:

A.

Scope baseline

B.

Cost baseline

C.

Risk register

D.

Schedule baseline

Question 4

A business transformation project has a four-phase delivery plan. The project team has successfully delivered one phase of the project.

To further enhance team performance and empower team members, which two actions should the project manager take? (Choose two)

Options:

A.

Encourage team members to cross-check decisions with the project manager.

B.

Vet all of the decisions before execution.

C.

Allow team members to make limited decisions.

D.

Organize and assign team members to tasks where they have strengths.

E.

Support team members to make decisions in their areas of strength.

Question 5

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

Options:

A.

Inform team B of the dependency and ensure that the deliverable is planned.

B.

Make team Aa part of team B and ensure that the deliverable is ready.

C.

Request team B to immediately start this activity and deliver to team A.

D.

Ask team B to focus on their backlog and deliver based on their priority,

Question 6

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

Options:

A.

Make arrangements for the stakeholder to join the kick-off meeting virtually.

B.

Hold the kick-off meeting with the rest of the stakeholders to avoid a delay in the project.

C.

Change the kick-off meeting to a virtual meeting so all can attend at the same time.

D.

Reschedule the kick-off meeting for the following month so all can attend on-site.

Question 7

A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the

original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.

What should the project manager do to resolve this conflict?

Options:

A.

Give the project team time to work through the issues with the new supervisor.

B.

Ensure the new supervisor takes the lead when being challenged.

C.

Immediately remove the resource from the project team.

D.

Communicate with the resource on the roles and responsibilities of this project.

Question 8

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

Options:

A.

Define a risk management plan (or the new approach, as needed.

B.

Review the benefits realization plan to include the cost of the change.

C.

Define a project management plan for the new approach, as needed.

D.

Review the communications management plan to identity new stakeholders.

Question 9

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.

Request that all team members receive the newest quality standards training and review one another's work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Question 10

In a hybrid project, the project manager has identified a few stakeholders. According to the stakeholder matrix, the head of development has a high rating of power/influence and a high likelihood of conflict.

Which action should the project manager avoid?

Options:

A.

Escalating a conflict within the project

B.

Creating a new communication channel

C.

Giving special attention to this stakeholder

D.

Dismissing the stakeholder's opinions

Question 11

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.

What should the project manager do?

Options:

A.

Support the team in identifying the area of development and address the gap.

B.

Dissolve the team and include the team members in other existing teams.

C.

Identify the struggling team members and move them out of the team.

D.

Set up a clear expectation that the team is to deliver as in their previous projects.

Question 12

A project manager is preparing a large and complex international project. In order for the team to work well together in a virtual environment, the project manager needs to set up ground rules for good communication.

What should the project manager do first?

Options:

A.

Establish a communication channel.

B.

Create a communication protocol.

C.

Develop the stakeholder analysis.

D.

Distribute the risk register.

Question 13

A project manager is preparing a budget estimation for an international construction project. They decide to consult the project team members who are experienced in this type of project and are familiar with the local laws of the country.

Which budgeting approach would be the least risky for the project team to apply?

Options:

A.

Review historical data and provide parametric estimations for the activities, including local law restrictions.

B.

Use a top-down estimation and add contingencies to cover any future impacts regarding the legal context.

C.

Make a general estimation using a standard legal approach and then look to include early definitions.

D.

Discuss and compile the local information about laws to develop bottom-up estimations.

Question 14

A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.

How should the project manager handle the situation?

Options:

A.

Review validation and control procedures.

B.

Discuss reducing interruptions with the sponsor.

C.

Perform stakeholder requirements activities.

D.

Approach the sponsor about using an agile approach.

Question 15

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

Options:

A.

Reprioritize the backlog based on value and cost of delay divided by duration.

B.

Switch to a predictive approach to prevent any further delays to completion.

C.

Reprioritize the backlog based on story size and competence availability.

D.

Remove low-value items from the backlog to compensate for the higher cost.

Question 16

A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?

Options:

A.

Tell the supplier that they have an obligation to supply the raw material.

B.

Search for a new supplier that can deliver the same materials on time.

C.

Seek advice from the legal department and implement penalties.

D.

Assess the possible impact of the raw material shortage on the project.

Question 17

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?

Options:

A.

Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.

B.

Ensure that the project change log is up-to-date with the stories based on the missed requirements.

C.

Ensure that the project backlog has the features and stories prioritized correctly.

D.

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.

Question 18

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project

and the customer.

What should the project manager do?

Options:

A.

Ask the team member to submit a formal change request.

B.

Accept the suggestion as it has no impact on the project.

C.

Ask another team member to validate the impacts of the suggestion.

D.

Reject the suggestion and ask the team member to focus on executing the plan.

Question 19

A work package to configure new computer hardware is received, and a list of related project activities have also been identified. What should the project manager do?

Options:

A.

Define the project management plan.

B.

Estimate the resources needed for the activities.

C.

Consult subject matter experts (SMEs) to review the schedule.

D.

Estimate the cost of each activity.

Question 20

A project manager is working with a team that is demotivated and tired, as the project has been changing direction due to budget cuts from the sponsor.

What should the project manager do first?

Options:

A.

Meet with the team to define together a plan that would help them deliver despite the budget cuts.

B.

Work with the team to understand what can motivate them to try and complete the project.

C.

Remind the team of their commitment with the client and the need to adapt to the client's needs.

D.

Call the sponsor and ask for a meeting to clarify the scope before working any further on the project.

Question 21

A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market.

What should the project manager do to move forward with the project?

Options:

A.

Continue building the center as the farmers' group does not need to be consulted.

B.

Document a risk related to the impact that the farmers' group could bring to the project.

C.

Request that the project sponsor discuss compensation with the farmers' group for the lost business.

D.

Discuss the project objectives with all stakeholders, including the farmers' group, and review their requirements.

Question 22

A project manager is creating the quality management plan for deliverables with very precise requirements. The project manager is uncertain about how to create quality standards so the suppliers can show conformity when delivering the product.

Which two actions should the project manager take first? (Choose 2)

Options:

A.

Review the conformity management plan to ensure the requirements are clearly defined.

B.

Reference the quality management plans from old projects to determine if they apply to these deliverables.

C.

Add a conformity team member to inspect each deliverable upon receipt from the supplier.

D.

Evaluate industry standards of similar products to determine which apply to this project.

E.

Ask the suppliers to create a statement of conformity when the product is delivered.

Question 23

A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.

How should the project manager recognize high performance?

Options:

A.

Thank the team member privately to avoid conflict among the team members.

B.

Acknowledge the high-performing team member in the next team meeting.

C.

Choose a reward for the team member that aligns with their personal goals.

D.

Ask the sponsor to approve a bonus for the high-performing team member.

Question 24

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project

execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

Options:

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

C.

Ensured the stakeholder who was providing additional funds remained interested in the project.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

Question 25

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.

What should the project manager do next?

Options:

A.

Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.

B.

Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.

C.

Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.

D.

Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.

Question 26

A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team

interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Video conferencing

C.

Encrypted emails

D.

Chat conversations

Question 27

A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?

Options:

A.

Perform stakeholder engagement.

B.

Perform integrated change control.

C.

Update the quality management plan.

D.

Update the risk management plan.

Question 28

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.

Which estimation technique should the project manager recommend?

Options:

A.

Planning poker

B.

Parametric estimating

C.

Three-point estimating

D.

Analogous estimating

Question 29

In a project, one team member has been asking for directions and what actions to take on many tasks. As a result, the team member has performed slowly in project delivery.

What should the project manager do to help this team member?

Options:

A.

Assign another senior team member to coach the team member.

B.

Empower the team member to make decisions.

C.

Mentor the team member on a regular basis.

D.

Address the team member's performance accordingly.

Question 30

The project team members have finalized the technical specifications after their discussion with the machine manufacturers. However, it has been identified that the specifications are not aligned with the project management office (PMO). The project team members are confident about their choice of specifications.

What should the project manager do in this situation?

Options:

A.

Request a decision from the project sponsor.

B.

Give approval of the technical specifications.

C.

Ask the sponsor for additional funding to hire a senior subject matter expert (SME).

D.

Schedule a meeting with all of the subject matter experts (SMEs) to discuss.

Question 31

A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned

to work on the details and estimates as requested by the client.

What should the project manager do before sending the information to the client?

Options:

A.

Put the tasks with estimates in the backlog and clarify that the project will not need any reserves.

B.

Sequence the tasks with estimates and add standard risk reserves to use for software development.

C.

Analyze the tasks, provide estimates, include a prototype demo, and send to the client directly.

D.

Work with the team to understand their views and add the appropriate dependencies and risks.

Question 32

A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial

department that is being delayed for a later iteration.

What should the project manager do to clarify the situation?

Options:

A.

Create an executive board to review the product backlog and replan the next iterations.

B.

Clarify with the CFO that the prioritization process is based on business value.

C.

Request support from the CEO on how to deal with the situation.

D.

Increase the size of the team in order to match any prior expectations of the CFO.

Question 33

A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.

What should the project manager do?

Options:

A.

Meet with the project sponsor and key stakeholders to confirm that the information about the forecasted project value is accurate.

B.

Ask the organization to cancel the project because the project manager is unable to confirm that the project will deliver the forecasted value.

C.

Proceed with execution of the project whether the information about the forecasted value is right or not because the project is already approved.

D.

Develop scope alternatives to achieve the forecasted project value in the event that project benefits information is inaccurate.

Question 34

A project manager is assigned to a time-bound internal project on quality improvement. During project execution, the project manager observes that a specific team member is being isolated

by other team members.

Which three actions should the project manager take? (Choose three)

Options:

A.

Arrange and conduct team-building sessions to improve team effectiveness.

B.

Allow team members to resolve personal issues without involving the project manager.

C.

Get feedback from other team members to understand what led to this situation.

D.

Identify the isolated team member as a risk and document the situation in the risk register.

E.

Obtain feedback from the isolated team member to understand the situation.

Question 35

During a business review meeting, a key stakeholder raised a concern on the quality of deliverables and has now escalated the concern.

What should the project manager do first?

Options:

A.

Schedule a meeting with all team members to clarify and plan next steps.

B.

Discuss with the stakeholder and share a report on the deliverables.

C.

Discuss with the team and check all reports on the deliverables.

D.

Schedule a meeting with the stakeholder to clarify and plan next steps.

Question 36

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

Options:

A.

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Question 37

The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?

Options:

A.

Assign a project team member to document exchanged communication for future reference.

B.

Assign the project sponsor as the point of contact for all provider communication.

C.

Ensure that all project stakeholders participate in the scope definition meetings.

D.

Establish a common language of terms with which to communicate with the provider.

Question 38

A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.

What should the project manager do next?

Options:

A.

Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.

B.

Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.

C.

Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.

D.

Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.

Question 39

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?

Options:

A.

Suggest that the team member contact the IT department.

B.

Facilitate a priority resolution of the issue with the IT department.

C.

Update the issue log and escalate the problem to the product owner.

D.

Ask the other team members to step in and do the work.

Question 40

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted

a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After

3 days of work, the project manager completed two actions and spent US$80,000.

What should the project manager do next?

Options:

A.

As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions.

B.

Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension.

C.

As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions.

D.

Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project.

Question 41

Project progress meetings occur via virtual conference calls. In every project progress meeting, one team member continuously interrupts others during discussions. Other team members often have no opportunity to talk or complete their explanations.

What should the project manager do?

Options:

A.

Speak individually with the team members who do not participate in conversations.

B.

Manage time efficiently using the agenda and ask each participant to contribute.

C.

Speak individually with the team member who always disrupts the conversations.

D.

Start the meeting with a review of the ground rules, meeting objectives, and the agenda.

Question 42

A project has progressed significantly and is getting close to completion. The project manager observed that team members are no longer focused and have started arriving to work late.

What should the project manager do?

Options:

A.

Hold motivation sessions to keep team member morale high.

B.

Engage functional managers to secure roles for team members.

C.

Penalize team members who arrive to work late.

D.

Ask for replacement project team members.

Question 43

A project manager is leading a project that is kicking off next month. The project manager realizes that there are many stakeholders that need updates on different aspects of the project at different frequencies.

What should the project manager do first to ensure each stakeholder has the information they need?

Options:

A.

Develop a communications management plan that reflects the needs of the stakeholder community.

B.

Engage with each stakeholder to determine their information needs related to the project.

C.

Create a responsible, accountable, consulted, and informed (RACI) chart based on the stakeholders and their communications needs.

D.

Determine the most appropriate mechanisms to leverage when communications are necessary.

Question 44

A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

Options:

A.

Accept the client's observations and pay the penalties as per the project contract details.

B.

Investigate the client's project reports and proceed to negotiate the levying of any penalties.

C.

Inform the project director of the change and complete the project so as to not incur any penalties.

D.

Request for the recall of the project director to investigate the situation and negotiate potential penalties.

Question 45

An agile project is in its ninth of 10 iterations. The team is delivering the work as expected. In the planning session, the team identifies a dependency with another project in the organization.

What should the scrum master do in order to accomplish the iteration goal?

Options:

A.

Ask the product owner to collaborate with the other team about the dependency.

B.

Recommend that the product owner change the priority of the dependency.

C.

Initiate collaboration with the other project team working on the dependency.

D.

Ask a team member to interact with the other team to complete the dependency.

Question 46

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.

Ensure the client representative is involved in the estimation.

B.

Review the completion costs of similar projects.

C.

Ensure that a 20% contingency is included in the estimation.

D.

Review the lessons learned from similar projects.

Question 47

An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager

advises the product owner that some of the functional requirements are not aligned with the chief information technology officer's (CTO) strategy.

The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.

What should the project manager do?

Options:

A.

Advise the CTO about the possible impacts caused by the project.

B.

Influence the product owner to review the engagement needed from other stakeholders.

C.

Continue building the backlog since they are functional requirements.

D.

Review the organizational process assets (OPAs) for historical information from similar projects.

Question 48

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

Options:

A.

Solution architecture

B.

Product backlog

C.

Statement of work (SOW)

D.

Business case

Question 49

A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.

What should the project manager do to ensure the project scope is completely defined?

Options:

A.

Ask the general manager to review every requirement to ensure all projects will deliver the requested products

B.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

C.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

D.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

Question 50

A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.

What should the project manager have done differently?

Options:

A.

Invited the customer to the daily meetings

B.

Helped the team redefine the MVP

C.

Changed the duration of iterations to deliver more value

D.

Validated the iteration goals with the customer

Question 51

A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.

What should the project manager do to manage this conflict?

Options:

A.

Arrange a team-building activity to foster understanding and open communication among the team members.

B.

Allow the team members to continue using their preferred communication tools and methods.

C.

Initiate a conversation with the team members individually to understand their situations regarding communication.

D.

Instruct the team members to adapt to the project's communication tools and methods.

Question 52

Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two

members are tense around each other and are taking everything personally.

What should the project manager do?

Options:

A.

Help the team members to resolve the conflict in a way that results in the best team performance.

B.

Offer a compromise that is acceptable to both team members, even if it may not be the best solution.

C.

Understand each team member's argument and select the one that results in less risk to the project.

D.

Send both team members to the human resources (HR) department for an acceptable resolution.

Question 53

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has

been working on this project for 6 months, and the morale of the team is low due to the schedule.

What can the project manager do to motivate the team?

Options:

A.

Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.

B.

Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.

C.

Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.

D.

Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.

Question 54

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

Options:

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

Question 55

A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.

What should the project manager do next?

Options:

A.

Reduce the quality and cost of other deliverables to allow additional budget for the items that were missed.

B.

Start the project and deal with these budget issues as they arise throughout the project life cycle.

C.

Add the missing budget items to the risk log and present them in the next project steering committee.

D.

Immediately discuss this with the project sponsor and request to revisit the budget to ensure its accuracy.

Question 56

A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager's organization, the client organization, and the local community.

What should the project manager do after identifying the stakeholders?

Options:

A.

Prioritize stakeholders from the client's organization and the local community.

B.

Prioritize stakeholders from the project manager's own organization.

C.

Prioritize the stakeholders that are more interested in the success of the project.

D.

Prioritize the stakeholders that may have more impact on the development of the project.

Question 57

A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.

What should the protect manager do?

Options:

A.

Perform quality control analysis.

B.

Perform root cause analysis (RCA).

C.

Perform trend analysis.

D.

Perform schedule analysis.

Question 58

A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was

being verified, it was found that the compliance part was not implemented in the project.

What should the project manager do next?

Options:

A.

Get an exception approval from the legal team.

B.

Request the team to implement the compliance.

C.

Ask the stakeholder to descope the compliance.

D.

Obtain approval from management and release.

Question 59

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?

Options:

A.

Contact the human resources (HR) department to find new resources to replace this critical resource.

B.

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.

C.

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.

D.

Discuss the resource management plan with the project team for effective utilization of critical resources.

Question 60

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?

Options:

A.

Negotiate a contract change with the subcontractor.

B.

Meet with the client to discuss the issue with the subcontractor.

C.

Inform the subcontractor that they must send the schedule.

D.

Tell the subcontractor to submit a draft schedule.

Question 61

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Defined the skill requirements more clearly in the scope statement.

B.

Asked the manager to follow the agreed-upon resource management plan.

C.

Conducted periodic reviews with the manager on resource availability.

D.

Consulted with the installation team on a regular basis to check for conflicts.

Question 62

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

Options:

A.

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.

B.

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.

C.

Meet with the project sponsor and key stakeholders to assess each deliverable's value to the organization and set execution priorities.

D.

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.

Question 63

A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.

What should the project manager do?

Options:

A.

Allow the most senior team member to make a decision and communicate the decision to the team members.

B.

Speak with the team members about their disagreement and seek clarity regarding the requirements.

C.

Ask for advice from the human resources (HR) department about how to handle the situation.

D.

Escalate to the change control board (CCB) and have them seek clarity on the requirements of the change.

Question 64

A government approved the construction of a river dam to enable year-round farming in a community. At the project kickoff meeting, a key stakeholder in the community disagrees with the location of the dam.

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan to confirm that all key stakeholders were consulted.

B.

Explain to the key stakeholder that final approval has already been obtained.

C.

Meet with the key stakeholder to review the stakeholder engagement plan.

D.

Schedule a meeting with all stakeholders to discuss the view of this key stakeholder.

Question 65

Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.

What should the project manager do?

Options:

A.

Assemble the entire project team to produce new flowcharts from current versions.

B.

Assemble and create teams of experts and stakeholders to update flowcharts to reflect current conditions.

C.

Raise a change request and ask the project sponsor to approve it so the flowcharts can be updated.

D.

Work with a consultant and the project sponsor to produce new flowcharts.

Question 66

The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).

What should the project manager do?

Options:

A.

Inform the stakeholders that the project goals are in the business case and change requests must be submitted.

B.

Secure approval from the most influential stakeholders on the project goals and the needed functionality.

C.

Host requirements gathering meetings where all of the stakeholders can identify their project goals until agreement is reached.

D.

Develop a list of project goals, secure sponsor approval, and then socialize them with the direct and indirect stakeholders.

Question 67

A project manager is trying to define a project time line despite having incomplete and ambiguous information on requirements and regulations. What should the project

manager do to finish planning?

Options:

A.

Review project documents to identify and eliminate uncertainties and inconsistencies.

B.

Execute a root cause analysis to discover the underlying factors that might lead to risks and issues.

C.

Perform an assumption and constraint analysis to provide more opportunities and remove limiting factors.

D.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis.

Question 68

Several components of an expensive manufacturing project have been returned by the customer. The customer is complaining that the quality of

the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that

quality has been maintained.

How should the project manager communicate with the customer to help assure them that the project has produced quality products?

Options:

A.

Show the customer the tolerance and control limits.

B.

Show the customer sample results from the current batch.

C.

Show the customer a sample history of quality.

D.

Show the customer the quality control measurements.

Question 69

During the execution of a construction project, one of the neighboring businesses is complaining that the current building height does not agree with the initial project plans. What should the project manager do first?

Options:

A.

Ask the neighbor to leave the site immediately because the site is on private property.

B.

Inform the neighbor that all of the project documentation has been approved.

C.

Inform the neighbor that the complaint will be escalated to the project sponsor.

D.

Ask the neighbor to submit a formal complaint about their concerns.

Question 70

Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.

How should the project manager approach the situation?

Options:

A.

Intervene in the deliberation process and weigh in on which approach would be better to use.

B.

Deliberate with the team moving the item to the product backlog and taking up the next item in the list.

C.

Stop the deliberation process and ask the team to take a vote using the nominal group technique.

D.

Allow the team to continue deliberating until the team reaches a consensus on the desired approach.

Question 71

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

Options:

A.

Request the additional work through governance.

B.

Meet with the stakeholder and explain that additional work cannot be added.

C.

Prioritize the additional work in the backlog.

D.

Collaborate immediately with the stakeholder to complete the additional work.

Question 72

A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.

What should the project manager do?

Options:

A.

Proceed with the direction given by the director for the regulatory liaison, as they are the subject matter expert (SME).

B.

Follow the CEO's directive, as they are the highest authority in the company and are the ultimate decision maker.

C.

Meet with the CEO and the director to discuss and register it as a major risk if agreement cannot be made.

D.

Schedule final testing activities in parallel with the regulatory approval activities to compensate for lost time.

Question 73

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

Options:

A.

Share a work performance report with the team member's supervisor.

B.

Assign a mentor to work with the senior team member.

C.

Speak with the senior team member to identify the difficulties.

D.

Collect feedback from all team members about team performance.

Question 74

A project manager with agile experience is part of an organization that is transitioning to agile. The project manager was assigned to the first agile project by the project management office (PMO). The PMO manager asked the project manager if an existing governance from a previous project would be suitable to use in the current agile project.

How should the project manager respond?

Options:

A.

This framework is not appropriate for agile.

B.

This is a learning experience for the agile team.

C.

An agile approach is easily adaptable.

D.

An agile approach is different.

Question 75

A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members

available who are qualified to complete the work.

What should the project manager do?

Options:

A.

Assess the team member's development requirements and arrange for the team member to receive training.

B.

Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.

C.

Work with the functional manager to determine an incentive for the team member to complete the project.

D.

Request a substitute for the team member with a new resource who is more skilled in system development work.

Question 76

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

Options:

A.

Have the team complete the technically complex story first.

B.

Work with the product owner to clarify and prioritize the backlog stories.

C.

Have the team complete the less complex story first.

D.

Work with the agile coach on the user stories to avoid conflict.

Question 77

A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the

next phase of funding closure.

What should the project manager do?

Options:

A.

Ensure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor.

B.

Submit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances.

C.

Create a detailed project report on successes and challenges for the project sponsor.

D.

Arrange a site visit to show the project sponsor the construction progress in person.

Question 78

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

Options:

A.

Work with the procurement team to find alternative options.

B.

Contact the vendor that supplied similar equipment for a previous project.

C.

Use the existing equipment and replace it later with the new equipment

D.

Ask the project sponsor to expedite the vendor selection process.

Question 79

Question # 79

An agile team has sized all of the features for the release. Using the table above, how many sprints will it take to complete this release if the team is expecting to have a

velocity of 10 story points per sprint?

Options:

A.

1

B.

95

C.

6

D.

4

Question 80

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

Options:

A.

Detail the reason for the project delay in the status report.

B.

Invite the stakeholders to discuss a mitigation plan.

C.

Take on some of the necessary work to minimize the impact.

D.

Register an issue and escalate it to the project sponsor.

Question 81

During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.

What should the project manager do?

Options:

A.

Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.

B.

Discuss the issue with the team so the product manager can understand the trade-offs.

C.

Suggest the team and product manager go with the faster approach, reducing the scope.

D.

Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor's guidance.

Question 82

A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?

Options:

A.

Talk to the team member to determine why their performance changed.

B.

Talk to the team member and a human resources (HR) representative.

C.

Talk to the team member's manager to provide more training.

D.

Talk to the project lead and ask them to allocate less demanding tasks.

Question 83

A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.

What should the project manager do?

Options:

A.

Modify the project schedule to accommodate the delays in the purchase of services.

B.

Request that the purchasing tasks be outsourced through an existing purchasing vendor.

C.

Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

D.

Ask the project team to keep developing other tasks that do not depend on the purchase of services.

Question 84

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

Options:

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Question 85

The team responsible for executing a work package asks the consultant to reconsider the initial project deliverables specified in the contract.

What should the project manager do in this situation?

Options:

A.

Carry out corresponding negotiations in the adjustments of outcomes.

B.

Agree with the consultant to continue without any adjustments.

C.

Pause the project until a satisfactory agreement between both parties is reached.

D.

Explain to the consultant that without adjustments, payment terms will be affected.

Question 86

During a requirements review session with a customer, a team member gets upset when questioned by the customer and responds angrily.

What should the project manager do next?

Options:

A.

Discuss with the whole team the root cause of this issue

B.

Meet with the team member to reset expectations

C.

Provide the team member with space to manage their emotions

D.

Follow up with the whole team to find the best approach

Question 87

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?

Options:

A.

Relocate the project to another country that is not shutting down.

B.

Evaluate the possibility of having another country complete the task.

C.

Identify additional team members who are able to complete the task.

D.

Determine if the project has built-in slack to remain on schedule.

Question 88

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the

critical path, and any delay would impact project completion.

What should the project manager do?

Options:

A.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

B.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

C.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

D.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

Question 89

A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.

What should the project manager do?

Options:

A.

Ask the new team member to focus only on development and not do the testing.

B.

Coach the new team member to conduct the testing the way it has always been done for this project.

C.

Schedule a meeting with the new team member to learn about the new method of testing.

D.

Request that the new team member do the testing the way it has always been done for this project.

Question 90

A project manager is finalizing the project charter and has invited the project sponsor and key stakeholders to confirm the project estimates. The project manager suggests adding a budget reserve to meet unforeseen risks, but the project sponsor disagrees.

What should the project manager do?

Options:

A.

Demonstrate that risky projects are subject to change so adding reserves to the budget is a necessity.

B.

Explain to the project sponsor and key stakeholders the need to add the reserve and get their buy-in.

C.

Seek key stakeholders' approval and finalize the budget with the reserve.

D.

Agree with the project sponsor and finalize the budget without the reserve.

Question 91

A project with a geographically distributed team is ending its first iteration out of eight. During the daily meetings, the project manager realizes that some team members are not engaging in the discussion.

What should the project manager do?

Options:

A.

Conduct a team activity to determine the reasons for this situation.

B.

Speak with the team to find a better time to hold the meeting.

C.

Ask the team members to speak during the meetings.

D.

Update the risk log and follow the team members' performance.

Question 92

A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.

What should the project manager do to engage the team?

Options:

A.

Have one-on-one meetings with team members to improve communication.

B.

Ask human resources (HR) for team-building recommendations.

C.

Schedule weekly team meetings to encourage collaboration.

D.

Invest in a virtual collaboration/colocation environment.

Question 93

A steering committee has asked the project manager to assist with the decision-making process between build versus buy delivery options. Which value metric should the project manager evaluate to respond to the steering committee's request?

Options:

A.

Impact value

B.

Expected monetary value (EMV)

C.

Net present value (NPV)

D.

Earned value (EV)

Question 94

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

Options:

A.

Facilitate a supportive level of engagement for this stakeholder.

B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C.

Perform a qualitative risk analysis using a probability and impact matrix.

D.

Ensure the key information is accurate and monitor the situation as the project progresses.

Question 95

A mandatory compliance requirement that will impact the project software is introduced during the execution phase of an iterative project. The team is aware of the compliance requirement.

What should the project manager do next?

Options:

A.

Update the product backlog item with this new requirement.

B.

Escalate the issue of project impact to the project sponsor.

C.

Escalate the issue of project impact to the product owner.

D.

Update the stakeholder register to include the requirement owner.

Question 96

An organization with a new project management office (PMO) team is now undergoing a restructuring. Additionally, there is a lack of communication from the PMO to the team members.

How should the project manager handle this situation?

Options:

A.

Meet the PMO team and explain the importance of communicating with the team members for project success.

B.

Request the PMO team share updates on the restructuring with the team members on an immediate basis.

C.

Set up a meeting with the PMO and project team to discuss and clarify questions related to restructuring.

D.

Inform the team that despite the new PMO and restructuring, the team will not change.

Question 97

A multicultural team is working on a project. After a few months of observation, the project manager realizes that two team members are not responding to the construction manager properly. The project manager spoke to the team members individually and found that both had cultural differences with the construction manager.

What should the project manager do to improve the situation?

Options:

A.

Ask the team members to tolerate the cultural differences as they have a different cultural background.

B.

Ask the construction manager to meet with the two team members to resolve the situation.

C.

Provide the construction manager with instructions on how to resolve the situation.

D.

Discuss the team members' concern with the construction manager and seek solutions.

Question 98

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

Options:

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.

B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.

C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.

D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.

Question 99

Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the

project manager support this team to succeed?

Options:

A.

Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.

B.

Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.

C.

Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.

D.

Work with the team members to define the overall objective and support them to engage around the goal.

Question 100

During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team's capacity and they will not be able to work on product feature development.

What should the project manager do?

Options:

A.

Invite technical stakeholders for backlog prioritization.

B.

Work on the features already prioritized by the product owner.

C.

Ask the sponsor for more resources to continue at the same pace.

D.

Add the technical debt tasks to the sprint backlog.

Question 101

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

Options:

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Question 102

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

Options:

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Question 103

In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.

What should the project manager have done to prevent this situation from occurring?

Options:

A.

Analyzed the sponsor's communication requirements.

B.

Confirmed that the portal is providing adequate information.

C.

Verified that the project team is following the communications management plan.

D.

Ensured the sponsor had the necessary skills to use the portal.

Question 104

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

Options:

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Question 105

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

Options:

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Question 106

In a construction project for a new building, the project manager decides to apply agile principles for the building foundation phase While evaluating the project schedule with the team, the project manager believes that the estimates are inaccurate. How should the project manager address this issue?

Options:

A.

Create a product backlog

B.

Perform sprint reviews with the team

C.

Assess the previous project velocity

D.

Reduce the story size by splitting stories

Question 107

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

Options:

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Question 108

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

Options:

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

Question 109

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

Options:

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Question 110

Match the project situation on the left to the meeting on the right where the situation could occur.

Question # 110

Options:

Question 111

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

Options:

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

Question 112

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

Options:

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Question 113

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Question # 113

Options:

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

Question 114

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

Options:

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

Question 115

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams through

mid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets

(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determined

the future state.

D.

Hired a third-party agile delivery team to do the implementation.

Question 116

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

Options:

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Question 117

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

Options:

A.

Assess the stakeholder's needs and communication style and propose a tailored approach with regular status reports and progress meetings.

B.

Invite the stakeholder to the regular "show and tell" sessions so the stakeholder is aware of project progress and feedback can be gathered.

C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.

D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.

Question 118

A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.

What is the next step for the project manager?

Options:

A.

Document the lessons learned and implement improvements in the next sprint

B.

Facilitate a daily standup with the team to track the implementation of changes

C.

Organize a demonstration of the changes in the enterprise system

D.

Request that all team members think of ideas to improve processes.

Question 119

The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors

What should the project manager do?

Options:

A.

Review the assumption log and project management plan for changes.

B.

Identify adequate change management tools to conduct the project

C.

Establish a change control board (CCB) with key stakeholders.

D.

Allow key stakeholders to make some changes to deliver the product faster

Question 120

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

Options:

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Question 121

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

Options:

A.

Attach a note to the project management plan about the team member

B.

Hold a project team meeting about the team member's contribution and take minutes

C.

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.

Send a communication to management recognizing the team member's contributions

Question 122

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

Options:

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Question 123

A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?

Options:

A.

Propose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.

B.

Document the request and escalate to upper management to consider a modification of the project charter.

C.

Agree on a predictive approach, but apply agile concepts under the project management umbrella.

D.

Ensure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.

Question 124

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?

Options:

A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project

B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes

C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

D.

Explain that distribution of important news can only be done using traceable communication methods

Question 125

A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager

schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?

Options:

A.

Accommodator

B.

Mediator

C.

Arbitrator

D.

Conciliator

Question 126

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

Options:

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

Question 127

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Question 128

A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?

Options:

A.

Understood the customer's company culture

B.

Updated the communications management plan

C.

Analyzed customer interest and engagement

D.

Scheduled weekly update meetings

Question 129

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team.to accelerate the iterations and avoid interruptions.

B.

Discuss the problem with the team and decide how to do the work together.

C.

Verify team performance and ask for improvement during daily standup meetings.

D.

Recommend that the project sponsor increases the budget to bring new resources.

Question 130

A product owner has an idea for a new product but is struggling to define the

features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?

Options:

A.

Assess the product roadmap to see if there is another product that is more suitable for the build.

B.

Develop a minimum viable product (MVP) for assessment from a select customer group.

C.

Commission a business analyst to research similar competitor products.

D.

Complete a work breakdown structure (WBS) to assess the cost of each feature

Question 131

A project manager is leading a new agile project. The requirements for the first sprint have been defined and the work is about to start.

What should the project manager do next?

Options:

A.

Assign the tasks to the resources based on their expertise.

B.

Ensure that the priority of each task is clear to the team.

C.

Ask the team to self-organize and manage the work assigned.

D.

Tell the team which task to focus on at the next daily standup.

Question 132

An agile project team is building a new product. The stakeholders require ongoing

illustration of project business value.

How should the project manager proceed?

Options:

A.

Prepare performance value reports for the business on an ongoing basis.

B.

Include demonstrations of the built portion of the product at the end of every sprint.

C.

Prepare a project report for the stakeholders and distribute it weekly.

D.

Confirm the minimum viable product (MVP) and demonstrate it to the business when it is ready.

Question 133

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

Options:

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

Question 134

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

Options:

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Question 135

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

Question # 135

Options:

Question 136

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Follow the organization's process and deliverables for predictive projects, even if

they compromise the agility and performance of the project.

B.

Use the risk register to document all of the compliance vulnerabilities generated by

the project so that all decisions are well documented and approved by stakeholders.

C.

Meet with the project management office (PMO)/compliance entity to work on

process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Question 137

A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.

What should the project manager do?

Options:

A.

Report the violation to the change control board (CCB) and seek comprehensive

approval for these modifications.

B.

Update the change management plan to define the level of control required for

these types of modifications.

C.

Ask the quality control team to evaluate the modifications, but take no action

because the associated quality risks are insignificant.

D.

Request the engineering team to update the specifications to reflect the modifications made by the contractor.

Question 138

In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain

What should the project manager do?

Options:

A.

Make sure the analyst has regular pairing meetings with the other team member throughout task execution

B.

Ask the analyst to use skills to develop the tool, then move development to another team member

C.

Enroll the analyst in a capacity-building program and keep this analyst assigned to the task

D.

Recognize the analyst's concerns and reassign the task to another team member

Question 139

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

Options:

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Question 140

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

Options:

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Question 141

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

Options:

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.

Question 142

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

Options:

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

Question 143

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

Options:

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Question 144

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

Options:

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Question 145

A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.

How can the project manager convey these benefits to the stakeholders?

Options:

A.

Rebaseline the project schedule to show the current status of the project.

B.

Create a benefits management plan mapped to the organization's strategic objectives

C.

Perform a project cost-benefit analysis for the stakeholders

D.

Update the deliverables map against the agreed-upon project requirements

Question 146

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

Options:

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Question 147

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

Options:

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Question 148

A project manager for a large project's agile team is developing new workflows to meet changing business needs. As the second sprint is running, the product owner and agile team begin to receive more details that impact the scope change of running items. The agile team

requests a change in the sprint goals and sprint backlog items.

What should the project manager do?

Options:

A.

Create a parallel sprint to deliver the additional items.

B.

Guide the agile team to add the new scope to the product backlog.

C.

Pause the sprint to allow time to include the new items.

D.

Moderate the expectations for sprint quality.

Question 149

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.

How should the project manager address this situation?

Options:

A.

Negotiate payment after all project migration is completed

B.

Sign a single agreement for the whole project

C.

Use fixed-price increments as user stories are completed.

D.

Confirm payment after each project retrospective

Question 150

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

Options:

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Question 151

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

Options:

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Question 152

The project sponsor requested technical specifications for a project-related component. The project sponsor does not have the authorization to see the specifications, but insists on seeing them.

What should the project manager do first in this situation?

Options:

A.

Meet with the project sponsor as soon as possible to discuss the matter further

B.

Update the issue log to make the project team aware and to develop a strategy

C.

Create a stakeholder engagement plan to help the team formulate a response

D.

Provide the specifications to the project sponsor with some information removed

Question 153

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

Options:

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Question 154

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

Question # 154

Options:

Question 155

A project leader of an agile team realizes that one team member is unmotivated, which is affecting the whole team. What should the project leader do to improve the situation?

Options:

A.

Invest in developing the team's emotional intelligence.

B.

Ask the unmotivated team member to take a short leave.

C.

Reduce the number of daily and retrospective meetings.

D.

Send the unmotivated team member to another team.

Question 156

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

Options:

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

Question 157

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then share

it with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agile

approach in the upcoming project.

C.

Make a request to human resources for new team members who have agile

experience.

D.

Ask the project sponsor to change the approach back to predictive as that is the

team’s strength.

Question 158

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

Options:

A.

Distributed a detailed quality management plan to the key stakeholders.

B.

Included the final report during the closing phase to ensure common understanding.

C.

Identified key stakeholders and included all of them in project agreement discussions.

D.

Performed project reporting according to the communications management plan.

Question 159

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

Question # 159

Options:

Question 160

A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.

How should the project manager handle this situation?

Options:

A.

Discuss the company culture with the supervisor to clarify expectations.

B.

Review the overall organizational culture of the company again.

C.

Request that the new supervisor be assigned to another project.

D.

Explain to the workers that they need to listen to the supervisor.

Question 161

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?

Options:

A.

Email all stakeholders with the objectives of the project and ask for feedback.

B.

Wait for a date when all required attendees can be available onsite.

C.

Run separate meetings to accommodate everyone's schedule.

D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.

Question 162

A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.

Which action should the project manager take?

Options:

A.

Empower team members to participate in decision-making and take ownership of actions.

B.

Implement a flexible work schedule policy to eliminate the time zone problems among stakeholders.

C.

Encourage team members to network so that they know each other's cultural backgrounds.

D.

Provide a relaxed work schedule policy and encourage team members to work from home.

Question 163

A project manager is attending a progress meeting with a client The client requests a design change which might potentially add value to the project What action should the project manager take?

Options:

A.

Accommodate the change request to serve the client's needs

B.

Consult with team members and allow them to make a decision

C.

Convince the client not to make changes to the project

D.

Make transactional decisions focusing on the project goals

Question 164

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?

Options:

A.

Call for a team meeting to identify the root cause for the declining performance

B.

Estimate the baseline impacts and submit a change request.

C.

Implement compression techniques to bring the project back on track.

D.

Review the resource management plan and organizational assets

Question 165

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

Options:

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

Question 166

At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.

What should have been done to avoid this situation?

Options:

A.

The acceptance criteria should have been properly defined in the contract

B.

The client requirements should have been clearly defined in the contract

C.

The Manage Quality process should have been appropriately conducted

D.

The project manager should have reviewed the standard industry defect rate

Question 167

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

Options:

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Question 168

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

Options:

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Question 169

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

Options:

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

Question 170

During a sprint planning meeting, a stakeholder is told that their requirement is in progress and on track for the final product to be ready in the next two sprints. The stakeholder is very satisfied with the timeline and gives their full support to the agile team. After the meeting, the project sponsor calls the project manager about a large requirement they want the team to work on right away as it has significant

business value. What should the project manager do?

Options:

A.

Call the stakeholder to tell them that the final product schedule must be extended due to this last minute, urgent request.

B.

Perform an impact analysis and share the overall schedule impact before deciding on a new priority.

C.

Reject the new requirement from the sponsor as this is going to impact the delivery of the stakeholder's final product.

D.

Ask the product owner to prioritize the new request from the sponsor and ask the team to work on it immediately.

Question 171

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.

What should the project manager do?

Options:

A.

Create a training schedule for the new team member to follow over the next few weeks.

B.

Escalate the inquiry to the team member's functional manager.

C.

Clarify the relevance of reviewing the documentation on the intranet.

D.

Ask a senior team member to help the new team member navigate through all the documentation.

Question 172

A key team member shared confidential information about another team member with management, a practice that is against ethical standards. During a team meeting, some of the team members requested that the key team member be removed from the team.

What should the project manager do next?

Options:

A.

Contact the human resource (HR) department for a solution.

B.

Speak with the key team member to clarify the situation.

C.

Conduct a meeting with the team to deliberate on a decision.

D.

Suspend the team member until further notice.

Question 173

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

Options:

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Question 174

Having managed a similar project while working with previous stakeholders, a

project team decided to use the same report format they used in the earlier project.

However, stakeholders new to the project are not fully comprehending the status of the

project based on the reports that are being circulated.

How should the project manager address this concern moving forward?

Options:

A.

Add the issue to the issue log and determine the corrective action.

B.

Create a fishbone diagram to determine the root cause for the misunderstanding.

C.

Employ Monitor Communications techniques, which may eventually trigger changes to the communications management plan.

D.

Share the communications management plan and remind all stakeholders of the agreed-upon reporting templates.

Question 175

A company has hired a vendor to deliver a scope of work and assigned a project

manager to oversee the project. The vendor advised that they completed the scope

successfully and is asking for approval.

What should the project manager do in response to this request?

Options:

A.

Obtain approval from the project sponsor.

B.

Update the project management plan and mark the milestone as completed.

C.

Ask the vendor to validate the agreement for any deviations.

D.

Set up a meeting with stakeholders to validate and confirm acceptance of the deliverables.

Question 176

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

Options:

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

Question 177

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

Options:

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Question 178

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope What should the project manager do to improve the stakeholder's engagement?

Options:

A.

Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements

B.

Update the project backlog and discuss it with the key stakeholder

C.

Update the project charter and discuss it with the key stakeholder.

D.

Discuss the project scope statement with the key stakeholder and build prototypes

Question 179

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

Options:

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer's needs

D.

Allocate resources to work on the new feature immediately to complete the request

Question 180

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Question 181

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

Options:

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

Question 182

In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.

What should the project manager do?

Options:

A.

Consider cultural differences among stakeholders.

B.

Conduct an integration meeting among all stakeholders.

C.

Schedule communication training for management-level stakeholders.

D.

Understand how political aspects can affect the project.

Question 183

Due to a recent budget reduction, two team members were released from an agile

team. The customer is still expecting early results for the project.

Which two actions should the project manager take to align customer expectations? (Choose

two)

Options:

A.

Ask the agile team to review the updated sprint velocity with the customer.

B.

Ask the product owner to review the prioritized backlog with the customer.

C.

Ask the agile team to review and update the quality management plan with the

customer.

D.

Review the impediments log with the customer.

E.

Send a detailed project management plan to the customer.

Question 184

A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.

Which evaluation practice should the project lead use to obtain accurate usage data?

Options:

A.

Send out a questionnaire to all users regarding the most useful features.

B.

Embed a feedback form into the system for users to respond.

C.

Interview a sampling of users to obtain the usage data.

D.

Build the functionality in the software to collect the operational usage data.

Question 185

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

Options:

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team's agile maturity.

D.

Support the team members' growth and development.

Question 186

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Review the work allocation and reassign some tasks to shorten the critical path.

B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

D.

Keep the task assignments unchanged since the project management plan has been approved.

Question 187

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

Options:

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Question 188

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

Options:

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

Question 189

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

Options:

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team's communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

Question 190

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

Options:

A.

Monitor the interactions between the vendor and infrastructure manager going forward.

B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.

Escalate the issue to the sponsor so appropriate action can be taken.

D.

Instruct the vendor to correct the problem without additional arguments.

Question 191

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

Options:

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

Question 192

A labor union contract negotiation is delaying the completion of a project to build

a new manufacturing plant. Because the labor contract was due for renewal this year, the

project manager documented the negotiation process as a risk to the project. The project

was about to start the first phase of equipment installation at the plant when the negotiation began.

How should the project manager address the situation?

Options:

A.

Meet with the project team to determine options for risk mitigation.

B.

Log the issue and follow the planned actions in the risk response plan.

C.

Acquire contract resources and submit a change request for the cost impact.

D.

Escalate the issue to the steering committee to ask for mitigation support.

Question 193

Close to the end of a project, a customer claims that some deliverables have not

been met and starts initiating change requests. What should the project manager do next?

Options:

A.

Refer to the requirements traceability matrix.

B.

Revise the project scope baseline.

C.

Escalate the change request to the project sponsor.

D.

Review the approved project charter.

Question 194

A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.

What is the first thing the project manager should do"?

Options:

A.

Include the requirement into the project and schedule it as soon as possible

B.

Inform the project sponsor about the situation and request assistance

C.

Evaluate the impact that the inclusion of this new requirement will have on project performance

D.

Inform the stakeholder that it is impossible to add new requirements to an approved project scope

Question 195

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

Question # 195

Options:

Question 196

An agile team is working on a product deliverable in an organization that is transforming itself to quickly respond to change. The finance

team is requesting a project budget for the new product.

What should the team do to address this request?

Options:

A.

Work with the finance team to transition to incremental budgeting.

B.

Request the finance team to allocate a budget based on historical data.

C.

Provide the budget to the finance team for only the planned increments.

D.

Extrapolate the budget based on the current cost performance index (CPI).

Question 197

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

Question 198

The portfolio management office wants to cut costs by suspending some ongoing

projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio

management office has not backed down on their plan.

What should the project manager do to continue the project?

Options:

A.

Meet with the project team and revise the project goals.

B.

Update the project charter to make it align with organizational strategy.

C.

Demonstrate the project alignment to the organizational strategy.

D.

Escalate the issue with the project sponsor to request support.

Question 199

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?

Options:

A.

Update the issue log.

B.

Perform a qualitative risk analysis.

C.

Perform a root cause analysis.

D.

Implement a risk response plan.

Question 200

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

Options:

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Question 201

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Question 202

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

Options:

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Question 203

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

Options:

A.

Resource breakdown structure

B.

Work breakdown structure (WBS)

C.

Team charter

D.

Project charter

Question 204

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

Options:

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Question 205

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

Options:

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Question 206

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

Options:

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

Question 207

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

Options:

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Question 208

A company has transitioned and is now delivering projects using a hybrid approach

instead of a predictive approach. The distributed project team's knowledge of agile is varied.

The project manager feels this new methodology will impact the timely delivery of the project.

What should the project manager do?

Options:

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk.

B.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update.

C.

Plan for training on agile tools and techniques used in the defined hybrid methodology

for consistent application by all team members.

D.

Use the predictive approach for team members who are not knowledgeable in agile project delivery practices.

Question 209

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

Options:

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Question 210

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline

B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change

C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline

D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline

Question 211

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

Options:

A.

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.

Update the acceptance criteria documentation to clearly reflect what was approved.

C.

Review the new requirement and update all the stakeholders accordingly.

D.

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Question 212

A project manager has been asked for performance feedback regarding one of the team members The project manager would like to gather additional input from the project team because there are no metrics in place for evaluating employee performance.

What should the project manager do next?

Options:

A.

Evaluate demonstrated task accountability

B.

Determine the appropriate approach

C.

Analyze team member influence

D.

Identify levels of decision-making authority

Question 213

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.

B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.

C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,

D.

Determine what methods the team has been trained on and utilize those methods for the project.

Question 214

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

Options:

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Question 215

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Question 216

A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.

What should the project manager do next?

Options:

A.

Escalate the issue to the purchasing department for review.

B.

Evaluate the procurement contract to determine the agreed-upon specifications.

C.

Hire a company in country B to perform a quality check before shipment.

D.

Add an additional task to cut the received part according to the specifications,

Question 217

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Question 218

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Question 219

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Question 220

A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.

What should the project manager do?

Options:

A.

Share project documentation in a repository with exclusive access.

B.

Schedule weekly knowledge-sharing sessions with key stakeholders.

C.

Send periodic emails to senior management with the latest project updates.

D.

Keep project artifacts up-to-date and accessible to all stakeholders.

Question 221

A large and complex program in an agile environment has experienced an increase in

escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.

What should be done to resolve this issue?

Options:

A.

Invite the client and product owner to all planning, review, and retrospective meetings.

B.

Accept the escalations and manage them so the working relationship with the client is

not impacted.

C.

Review and clarify roles, responsibilities, and the governance model at the next sprint

review meeting.

D.

Invite the product owner to attend all Scrum meetings and define the governance model

and escalation path.

Question 222

A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.

What should the project manager do to support the team?

Options:

A.

Create a change request to extend the project's duration and costs.

B.

Provide feedback to the team using project performance evaluations.

C.

Escalate the impact on the schedule to the project sponsor.

D.

Include buffer time in the schedule to absorb future delays.

Question 223

A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs

How should the project manager ensure the work continues smoothly?

Options:

A.

Postpone the required work on the project until school holidays begin

B.

Advise the school to close (or the duration of the project work

C.

Continue the work as planned and inform the school when the project team arrives on-site

D.

Liaise with the school to include nonworking project hours during school start and finish times

Question 224

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

Options:

A.

Strive toward continuous improvement

B.

Work together daily as a team

C.

Only share suggestions at the end of the sprint

D.

Follow the sprint planning

E.

Send communications to the entire team

Question 225

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

Options:

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Question 226

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager's decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Question 227

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

Options:

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Question 228

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

Options:

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk of

being noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurity

requirements.

Question 229

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.

Reviewed the project management plan

B.

Created a detailed operations manual

C.

Increased support hours for the hours of operation

D.

Involved operations stakeholders during planning

Question 230

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Options:

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Question 231

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Options:

A.

Allow the most senior team members to decide the time that works for the team.

B.

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.

Discuss the lack of dedication with the team member and their functional manager.

D.

Remove the team member from the project team to be fair to the other members.

Question 232

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

Options:

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Question 233

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

Options:

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

Question 234

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

Options:

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Question 235

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

Options:

A.

Ask the team member to learn the new system as on-the-job training

B.

Issue a change request to extend the project schedule

C.

Escalate the team members performance to the project sponsor

D.

Assign an experienced resource to support the team member

Question 236

What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?

Options:

A.

Hire employees who specialize in agile approaches so they can better contribute to

projects.

B.

Assign employees to agile projects so they can quickly adjust to the new approach.

C.

Train all employees in agile approaches.

D.

Shift the way the company views, reviews, and assesses employees.

Question 237

A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in

one of the project teams.

What should the project manager do?

Options:

A.

Apply a root-cause analysis on the data breaches.

B.

Ensure that all team members complete the training.

C.

Redesign the training courseware to make it interesting.

D.

Retrain the team members responsible for the breaches.

Question 238

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Question 239

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Question 240

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Question 241

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations

B.

Encrypted emails

C.

Videoconferencing

D.

Chat conversations

Question 242

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.

B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.

C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.

D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,

Question 243

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Question 244

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

Options:

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

Question 245

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

Options:

A.

Submit a change request to adapt the objectives of the project to the current situation

B.

Ask the scrum master to refine the user stones to improve the team members' understanding

C.

Find and provide training to the project team members who do not have the required skills

D.

Extend the duration of standup meetings to include skill transference from trained to untrained members

Question 246

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

Options:

A.

Use compression techniques to break down the scope and assign the scope pieces to

different vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any project

risk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to support

development.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Question 247

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Question 248

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

Options:

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Question 249

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

Options:

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Question 250

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

Options:

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Question 251

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

Options:

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Question 252

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

Options:

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Question 253

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

Options:

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

Question 254

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.

Advise the teams to follow the company’s existing project management approach.

B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.

C.

Let a senior team member select the approach that is appropriate.

D.

Insist the teams both follow either a predictive or agile approach.

Question 255

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

Options:

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Question 256

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)

Options:

A.

Confront the people causing the stress directly with the aim of finding amicable solutions

B.

Seek support from the project management office (PMO) on addressing issues affecting the project

C.

Discuss the possible actions with the project sponsor

D.

Avoid the people causing stress and request a transfer as soon as possible

E.

Talk to the human resources (HR) manager about these concerns

Question 257

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

Options:

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Question 258

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

Question # 258

Options:

Question 259

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Question 260

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Question 261

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to

take action in advance to ensure the project succeeds.

What should the project manager do?

Options:

A.

Evaluate the project risk and add external experts to address the potential risks.

B.

Inform the project sponsor about the risk and try to convince them to withdraw from the project.

C.

Continue executing the project as planned and add more resources if they are required.

D.

Review the lessons learned on similar projects so that they do not fall back into the same pattern.

Question 262

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

Options:

A.

The functionality is delivered early; therefore, more value is delivered.

B.

The team productivity is higher; therefore, more value is delivered,

C.

The cost is reduced: therefore, the total value delivered is higher.

D.

The risk is significantly reduced; therefore, more value Is delivered.

Question 263

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.

B.

Use a single communication medium such as video teleconferencing to limit confusion.

C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.

D.

Send frequent updates via email to each stakeholder because this is an information technology project.

Question 264

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

Options:

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Question 265

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

Options:

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Question 266

A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?

Options:

A.

Check the change management plan

B.

Document the issue in the scope management plan.

C.

Conduct a team brainstorming session to resolve the issue

D.

Check the quality management plan

Question 267

A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.

What should the project manager do?

Options:

A.

Ask senior management to communicate with these departments.

B.

Hire a project management consultant to help resolve the issue

C.

Convince senior management to introduce rewards to resisting departments.

D.

Understand the user concerns and revisit the stakeholder engagement plan

Question 268

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

Options:

A.

Meet with the team to discuss compliance concerns

B.

Review the organizational process assets (OPAs) for compliance topics

C.

Review the compliance strategy and version history

D.

Meet with the project sponsor to discuss their compliance concerns

Question 269

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

Options:

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Question 270

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

Options:

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team's manager to get extra hours from the team

Question 271

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Question 272

What should an agile lead do lo ensure their team is set up for success?

Options:

A.

Pay attention to team dynamics and understand that coaching is done simultaneously at an individual and whole-team level

B.

Schedule sprint meetings and coaching sessions to discuss project-related information

C.

Plan quarterly informal meetings or team bonding sessions to encourage the team to work together

D.

Document team tasks and challenges in order to understand when to step in and help a member of the team

Question 273

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?

Options:

A.

Add resources to activities

B.

Conduct serial activities on tasks

C.

Increase the number of standup meetings

D.

Perform tasks in parallel

Question 274

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

Options:

A.

Accept the feature.

B.

Determine if the feature is within the scope.

C.

Submit a change request! for the feature.

D.

Reject the feature.

Question 275

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

Options:

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Question 276

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Options:

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Question 277

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

Options:

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Question 278

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire

B.

Transactional

C.

Transformational

D.

Charismatic

Question 279

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

Question 280

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

Options:

A.

Allow the sponsor to determine how long the planning phase should last.

B.

Allow the client ta determine how long the planning phase should last.

C.

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.

Explain that more features can be planned in upcoming Iterations and begin building the product.

Question 281

A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.

What should the project manager do next?

Options:

A.

Engage with the functional manager to discuss details to obtain the required support.

B.

Request a teleconference meeting with the sponsor to submit a change request to allow the development team to conduct testing.

C.

Discuss testing requirements at the weekly project meeting to negotiate the best approach to test software.

D.

Send an email to the procurement specialist to negotiate with a company that specializes in software testing.

Question 282

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

Options:

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Question 283

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

Options:

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Question 284

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Question 285

A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.

What should the project manager do?

Options:

A.

Inform the stakeholder that they must level their knowledge with other stakeholders.

B.

Update the risk register with the potential impact and apprise the steering committee.

C.

Inform the project management office (PMO) that the team will use a predictive approach for this project.

D.

Allocate time to mentor the stakeholder in the selected project approach.

Question 286

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

Options:

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Question 287

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.

Ask the team to work on the complaint raised by the clients.

B.

Escalate the issue raised by the clients to the project sponsor,

C.

Develop a solution with the team to identify the inventory level.

D.

Work with the team and the product owner to define the next steps.

Question 288

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

Options:

A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Question 289

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Question 290

A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications

What should the project manager do?

Options:

A.

Schedule a meeting with all stakeholders to understand what went wrong and who should be held responsible

B.

Review the requirements traceability matrix with the team lead and the client to adequately resolve the issue

C.

Meet with the client and discuss the project deadlines

D.

Seek approval for more time for rework and resolve the issue

Question 291

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Question 292

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

Options:

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Question 293

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

Options:

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

Question 294

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

Options:

A.

Follow the risk management plan.

B.

Reduce the team effort utilization.

C.

Look for cost-saving opportunities.

D.

Submit a change request to add to the management reserve.

Question 295

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

Question # 295

Options:

Question 296

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Options:

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact to

the project value.

Question 297

During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.

What should the project manager do?

Options:

A.

Review the procurement documentation and modify requirements as needed.

B.

Study the new regulations with the team and evaluate if there is any impact on the

project variables.

C.

Update the contingency plan to take this issue into account.

D.

Meet with the stakeholders to update the risk register and risk management plan.

Question 298

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

Options:

A.

Instruct the team members involved to resolve the issue among themselves

B.

Discuss the issue with the steering committee to determine the proper course of action.

C.

Coordinate a video conference with the offending team member to resolve the issue

D.

Reassign the offending team member to a different project

Question 299

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

Options:

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for the

decision.

Question 300

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

Options:

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Question 301

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

Options:

A.

Modeling directive leadership

B.

Modeling commanding leadership

C.

Modeling adaptive leadership

D.

Modeling servant leadership

Question 302

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Options:

A.

Ask human resources (HR) to coordinate another activity.

B.

Reassess the team situation and provide a proper solution.

C.

Inform HR about the situation and ask for support.

D.

Meet with the team to explain that conflicts must be addressed and solved.

Question 303

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

Options:

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Question 304

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

Question # 304

Options:

Question 305

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed

What action should the project manager take?

Options:

A.

Escalate the issue from the IT team to management and get the validation prioritized

B.

Work with the IT team to prioritize the validation and release of the new features

C.

Deliver the features when the IT team is able to validate them

D.

Request the IT team to immediately release the product and then validate the features

Question 306

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

Options:

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives

B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders

C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project

D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable

Question 307

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

Options:

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Question 308

A project manager finds out that the required project status reports have not been

filled out by most team members. These status reports are urgently needed to compile a

comprehensive status report for the project sponsor.

What should the project manager do to address this situation?

Options:

A.

Reprimand the team members who did not fill out the status reports.

B.

Justify the team members' behavior to the project sponsor.

C.

Quickly put together a report that will satisfy the project sponsor.

D.

Discuss the issue with the team members at fault.

Question 309

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

Options:

A.

Add the stakeholder details into the periodic reports and update the project management plan

B.

Invite the stakeholder to all future project review meetings and update the project management plan

C.

Update the project management plan with the new information and inform all of the relevant stakeholders

D.

Meet with the stakeholder to better understand their expectations and update the stakeholder engagement plan

Question 310

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

Options:

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

Question 311

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

Question 312

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

Options:

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Question 313

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

Options:

A.

Identify how the proposed changes will benefit the project in relation to the business

case.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on a

lengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Question 314

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions when

needed.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders

ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all

unavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders to

make decisions.

Question 315

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

Options:

A.

Reviewed the risk register to identify a response plan for the audit

B.

Assigned a project team member to ensure all project documentation was updated

C.

Updated the project management plan regularly and had it securely shared with all stakeholders

D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders

Question 316

A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted

What should the project manager do?

Options:

A.

Request stakeholders who understand the technology.

B.

Recommend a change in technology to senior management.

C.

Plan to conduct informal sessions with the stakeholders.

D.

Include the issue in the Issue log and escalate to senior management.

Question 317

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

Options:

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

Question 318

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Explain the impact of the scenario to the project team member.

B.

Remove the project team member from all future meetings.

C.

Talk to the client privately to highlight the situation.

D.

Recommend a performance improvement plan to the project team member.

Question 319

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Question 320

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

Options:

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.

Question 321

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?

Options:

A.

Review the communications management plan with the team members.

B.

Remind the team members to follow the team charter.

C.

Motivate the team members to speak freely in the meeting.

D.

Arrange a team-building activity to involve all team members.

Question 322

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal and

external resource requirements.

B.

Commit each team member's time and deliverables and aim for overall project

completion.

C.

Continue the project implementation without the site engineers to ensure the schedule

is maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Question 323

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

Options:

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

Question 324

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.

Question 325

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

Options:

A.

Document this information in the risk management plan.

B.

Develop a contingency plan to prepare for possible risks.

C.

Continue executing the project using expert judgment.

D.

Review the lessons learned registers from the previous projects.

Question 326

During project execution, an important stakeholder threatens to withdraw support

for the project, citing a lack of transparency and accountability in the way the project is being

executed. What should the project manager do to handle this situation?

Options:

A.

Approach the stakeholder to address the concerns.

B.

Consult the risk management plan.

C.

Escalate the issue to the project management office (PMO).

D.

Refer the stakeholder to the project sponsor.

Question 327

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

Options:

A.

Clarify expectations by explaining the company culture with the supervisor.

B.

Ask senior management to move the supervisor to a different project.

C.

Revisit the company's organizational culture.

D.

Instruct the employees to listen to the supervisor.

Question 328

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.

Replace the team member immediately to maintain a good relationship with the

functional manager.

B.

Discuss the issue with the functional manager to understand the reason for the

complaint.

C.

Support the team member and provide documentation to the functional manager

proving their performance.

D.

Protect the team member and ask the project sponsor to minimize any external

interruptions.

Question 329

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

Options:

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Question 330

A project team has been together for a long time and has been led by three different

project managers. Lately, the performance of one of the team members has been declining

and has affected the project delivery.

What should the current project manager do to ensure that team performance is improved and

sustained?

Options:

A.

Liaise with the functional managers to replace the team member.

B.

Engage with the team member and draw up a development plan.

C.

Organize quarterly team-building events.

D.

Request that a new team member be added to the team

Question 331

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Question 332

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?

Options:

A.

Compare the achieved results to the contract requirements.

B.

Make the final payment as the project is completed.

C.

Transfer the remaining variances and close the project.

D.

Escalate to higher management to expedite the approval.

Question 333

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

Options:

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Question 334

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

Options:

A.

Update the risk register and implement the approved risk response plan for quality

deviations.

B.

Identify the resources that were responsible for the deliverable and request a team

development plan.

C.

Update the issue log, identify the involved stakeholders, and assign resources to the

corrective actions.

D.

Submit a change request to update the project quality requirements for the involved

project deliverable.

Question 335

A project manager is asked to implement a hybrid approach that will replace a predictive approach on an upcoming project How should the project manager adjust their responsibilities accordingly?

Options:

A.

Become a servant leader by supporting team collaboration and removing impediments

B.

Delegate coordination activities to the product owner so the project manager can locus on managing collaboration

C.

Request a scrum master to focus on the collaboration while the project manager focuses on the coordination

D.

introduce new communication tools to the project team members

Question 336

A protect manager is struggling to obtain participation from key stakeholders who do not usually attend project meetings What should the project manager do1?

Options:

A.

Distribute the communications management plan

B.

Reschedule meetings lo align with the stakeholders' availability

C.

Escalate the issue to senior management

D.

Set clear meeting expectations by sharing agendas in advance

Question 337

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

Options:

A.

Provide mentoring for the key team members on agile practices and support the team

with training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rules

stated in the document.

C.

Replace the key team members with new resources who are already aware of the agile

mindset.

D.

Provide directions to the team members on how to accelerate the company's

transformation, bringing the project back on track.

Question 338

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

Options:

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Question 339

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

Options:

A.

Ask the team to assess whether the product specification can be expressed in user

stories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities to

deliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for the

project due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for the

project in order to participate in iterative planning and reviews.

Question 340

A project manager who Is new to an organization is given data that include information related to both project team members and stakeholders. Among other items, this information includes each stakeholder's current role, previous and current projects in which they participated, and their level of organizational influence.

In what type of analysis should the project manager use this information?

Options:

A.

Regression analysis

B.

Stakeholder analysis

C.

Qualitative risk analysis

D.

Decision tree analysis

Question 341

When a project manager is trying to determine a leadership style to use on a project what should they consider?

Options:

A.

Number of tasks on the protect

B.

Culture of the organization

C.

Project timeline

D.

Experience of the project manager

Question 342

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

Options:

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location's regulatory

requirements.

D.

The project manager must follow their employer's organizational process assets

(OPAs).

Question 343

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.

A team whose members work independently and are the best subject matter experts

(SMES)

B.

A team whose members have more general aptitudes but like to work individually

C.

A team whose members have different skill sets and are spread out geographically

D.

A team whose members have more general aptitudes and can collaborate on different tasks

Question 344

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

Options:

A.

Change the project scope and seek approval to exclude this town from the overall

project.

B.

Engage with the town's authorities to discuss the reason for the change in commitment

and agree on a solution.

C.

Instruct the team to move to the next town and continue the project to avoid further delays.

D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Question 345

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

Options:

A.

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively

B.

Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training

C.

Make sure all stakeholders have access to the system and know where to find project artifacts

D.

Send the project schedule via email to the stakeholders who need that information

Question 346

A project is on its sixth iteration out of seven. Select the two points where the team is

performing better than expected. (Choose two.)

Question # 346

Options:

Question 347

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.

Engage the project team In implementing and Improving key aspects of the standup meetings.

B.

Ask the product owner to remove team members who do not comply with standup meeting rules.

C.

Send a daily retrospective report to all team members instead of holding standup meetings.

D.

Include a daily brainstorming session In the standup meetings to resolve pending Issues.

Question 348

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

Options:

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Question 349

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

Options:

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Question 350

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

Options:

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project manager

directly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to be

involved.

Question 351

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

Options:

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Question 352

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

Options:

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Question 353

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

Options:

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

Question 354

An international client contacted a software development company to build out a

software product, and an agile project manager was assigned. At one of the review meetings,

the client complains that a feature mentioned at the initial debriefing was not implemented.

What should the project manager do?

Options:

A.

Include the mentioned feature in the prioritized requirements list.

B.

Assign a team member to immediately start working on that feature.

C.

Review the original project documentation to confirm.

D.

Treat it as a change request and assess the effect on the project's goals.

Question 355

A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?

Options:

A.

Refer to the project charter

B.

Review the project resource matrix

C.

Assess the stakeholder register

D.

Update the communications management plan

Question 356

Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?

Options:

A.

Remove one of the team members

B.

Identify the issues between the team members and guide them toward a resolution

C.

Warn the team members about their behavior

D.

Train the team members on communication techniques and interpersonal behavior

Question 357

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

Options:

A.

Refer to the stakeholder engagement plan.

B.

Set up a conference call for all stakeholders.

C.

Refer to the communications management plan.

D.

Send an email to all stakeholders.

Question 358

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

Options:

A.

Project owner

B.

Agile leader

C.

Agile team

D.

Product owner

Question 359

A project manager is appointed to manage an infrastructure project that spans

across several countries, including different time zones within a subregion. It is likely that most of the project team members will never meet, but they will have to collaborate to ensure deliverables are met.

What should the project manager do to ensure good collaboration between the remote project team members?

Options:

A.

Discuss the concerns with the project sponsor and modify the project charter to include

more budget for interactions.

B.

Plan a communication method and allow the project team members to virtually interact.

C.

Create a social media group platform for the team to create a supportive environment.

D.

Set the ground rules and identify a contingency plan in the risk register.

Question 360

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

Options:

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Question 361

Throughout an entire project, the project manager took notes at every meeting with

team members. These notes provided useful insights from key stakeholders, which later

resulted in increased value to the project. The project manager thought it would be helpful to

keep these notes as a future reference for other project managers within the organization.

Where should the notes be located?

Options:

A.

Lessons learned

B.

Organizational process assets (OPAs)

C.

Enterprise environmental factors (EEFs)

D.

Project management plan

Question 362

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

Options:

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

Question 363

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

Options:

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Question 364

A project manager is leading a major water pipeline project and realizes midway into

the project that the project completion date is not achievable. Local farmers who rely on the

water for irrigation may be affected due to the delay. The project manager is afraid of their

displeasure and reaction, which will affect the project.

How should the project manager plan the communication to the stakeholders?

Options:

A.

Document and accept this risk and communicate this decision to the project sponsor.

B.

Collect feedback from the farmers and keep the information within the project team.

C.

Deliver the information to the stakeholders with the project management office's (PMO)

assistance.

D.

Propose a solution to the stakeholders and communicate it to the local farmers.

Question 365

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

Options:

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Question 366

The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?

Options:

A.

Schedule a time to negotiate a trade-off regarding the quality of the product with the customer

B.

Meet with the risk manager to identify potential threats related to the schedule delay.

C.

Set up a meeting with the project sponsor and submit a change request to the scope of the product

D.

Start the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations

Question 367

A key resource is newly assigned to a project. The project manager and the resource

did not get along well in a previous project. This resource is needed to ensure the completion

of a major component for the project.

What should the project manager do?

Options:

A.

Work on resolving the differences with the key resource and building a good working

relationship to ensure project success.

B.

Monitor the key resource closely throughout the project, but do not let the project

sponsor know about the conflict.

C.

Request that the key resource's functional manager work directly with the resource

during the project.

D.

Discuss this with the project sponsor and request that this key resource be replaced on

the project.

Question 368

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

Options:

A.

Update the project management plan in order to get back on track.

B.

Ensure the team receives continuous feedback from customers users.

C.

Submit a change request to adjust the project scope.

D.

Ensure the team understands all additional project requirements.

Question 369

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

Options:

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working as

expected.

Question 370

A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad

What should the project manager do next?

Options:

A.

Communicate to the whole team the decision to relocate team members abroad and the implications of doing so in the next project status meeting

B.

Communicate individually with the affected team members to negotiate the decision and confirm their willingness to relocate

C.

Communicate the decision to the human resources (HR) department so they can direct the project team members to be sent abroad

D.

Communicate to the affected team members' manager and schedule a meeting to discuss the details of this assignment

Question 371

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.

Identified and reported the issue

B.

Monitored and controlled the issue

C.

Identified the appropriate response and had it implemented

D.

Communicated any identified action to impacted stakeholders

Question 372

A customer asks the project manager about opportunities to create business value.

What should the project manager do first in order to provide the customer with an appropriate

response?

Options:

A.

Examine the business value throughout the project.

B.

Ask the team to organize a spike to identify more value.

C.

Meet with the product owner to review the backlog.

D.

Meet with the sponsor to review the business case.

Question 373

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

Options:

A.

Discuss the issue with the project sponsor and request extra time and budget to obtain

the component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to the

performance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) and

relevant stakeholders to identify alternatives to address the problem.

Question 374

A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?

Options:

A.

Deliver to the receiving manager on time, who can then make a knowledge transfer to

their team.

B.

Inform the project sponsor of the two-week delay and replan activities to minimize

delays.

C.

Request that the receiving manager issue a change request to prolong the project by

two weeks.

D.

Issue an internal change request to secure the resources for an additional two weeks.

Question 375

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

Options:

A.

Ask an external technical leader to provide input and plan the sprint.

B.

Remove the items from the product backlog since the size couldn't be estimated.

C.

Make the decision about the backlog items based on what makes more sense.

D.

Facilitate the discussion so that the team members can reach a consensus.

Question 376

A project selection committee is shortlisting projects for the coming year. Which selection criteria should the project manager recommend?

Options:

A.

Projects with the least duration

B.

Projects that maximize the business value

C.

Projects with maximum revenue generation

D.

Projects with the least associated risks

Question 377

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Question 378

A project team is facing challenges understanding how to deliver a project's scope.

A senior subject matter expert (SME) from the organization's global office is in town for 1 week.

What should the project manager do to benefit from the SME's presence?

Options:

A.

Ask the SME to review the scope for alignment with the project charter.

B.

Organize a mentoring session with the team and the SME.

C.

Meet with the SME to discuss the current challenges the team is facing.

D.

Review the project scope statement with the SME.

Question 379

In a software project using an agile approach, there have recently been work

overruns. After assessing the situation, the project manager concluded that the overruns are

occurring because of insufficiently refined product backlog items.

What should the project manager do to correct this issue?

Options:

A.

Work with the sponsor to revise the product vision.

B.

Create a definition of ready (DoR) for the backlog items.

C.

Discuss the issue with the service request manager.

D.

Refine the product backlog items with the stakeholders.

Question 380

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

Options:

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Question 381

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

Options:

A.

Ensure that the whole team is appropriately recognized and organize a project farewell

party to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and save

them in the organization's project management information system (PMIS).

C.

Archive all the project documents following the organization's accepted practices so

the documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult to

undertake because the current project is not yet complete.

Question 382

A project manager has been assigned lo an important agile project During protect execution, a vendor was approved to produce the project deliverables. What should the project manager do to ensure project continuity between the vendor and the team?

Options:

A.

Request that the vendor provides a manual with all required knowledge

B.

Implement retrospectives with the vendor to gather the required knowledge

C.

Submit a change request to extend the vendor's contract to provide formal training for the team

D.

Conduct daily knowledge transfer standups to ensure that the team is properly trained

Question 383

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

Options:

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Question 384

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

Options:

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Question 385

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution

B.

Call a team meeting to discuss team members' strengths and weaknesses

C.

Establish rules and regulations for team members with consequences if the goals are not reached

D.

Establish team behavior and develop an understating of how to work together

Question 386

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Question 387

A project manager is in the process of creating a strengths-based team and is

organizing a series of workshops to identify and document the strengths of each project team

member. During this session, there are multiple team members who are not actively

participating. These meetings are becoming futile due to a lack of participation.

What should the project manager do?

Options:

A.

Have a one-on-one discussion with each team member to emphasize their individual

talents.

B.

Document the behavior of the team members and highlight it during their performance

reviews.

C.

Identify the team members who are not participating and reprimand them.

D.

Explain the benefits of the approach and the effects of positive psychology.

Question 388

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

Options:

A.

Increase the overall project duration to account for the inexperienced team members

on the project.

B.

Ensure planning has accounted for replacing team members in new project roles who

do not deliver on project goals.

C.

Assess the training requirements and ensure time for professional development

training by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team members

assigned to the project.

Question 389

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

Question # 389

Options:

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Question 390

An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.

What should the agile leader do?

Options:

A.

Reassign the task to another team member and require the team member to complete training

B.

Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint

C.

Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.

D.

Speak directly with the team member about improvements and commit to an agreed-upon time frame.

Question 391

A company has decided to investigate the feasibility of a new product. The project manager is in charge of validating the customer requirements. What should the project manager do to gam customer feedback?

Options:

A.

Have the product owner create product documentation

B.

Have the team create a minimum viable product (MVP).

C.

Have the marketing department create a survey

D.

Have the team create a prototype with all features

Question 392

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

Options:

A.

Implement a project newsletter so the different team members can be informed about

the progress of each project.

B.

Combine all of the small projects into one big project so the team can collaborate

better as one big team.

C.

Facilitate communication promoting a Scrum of Scrums so the different teams are

aware of the dependencies and progress.

D.

Make sure that each individual project schedule is aligned with the common deadlines.

Question 393

A project manager notices that the response action for an identified issue is insufficient for solving the problem What should the project manager do next?

Options:

A.

Include the issue in the risk register and update the team

B.

Document the continuing issue and failed solution

C.

Inform the stakeholders about the failure and update the issue log

D.

Meet with the project team to find another solution

Question 394

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

Options:

A.

Perform stakeholder engagement with the virtual team

B.

Add status reports to the communications management plan

C.

Convene an on-site meeting for both of the teams

D.

Add status report creation as a product backlog item

Question 395

In the planning phase, a project manager receives identified risks from the sponsors

and subject matter experts (SMEs) and wants to develop a risk response strategy for them.

What should the project manager do first?

Options:

A.

Perform a risk reserve analysis.

B.

Assign allocated budget to cover key risks.

C.

Agree on the criteria to prioritize risks.

D.

Assign a risk responsibility to each team member.

Question 396

A team member is openly criticized by others during a standup meeting for failing to

complete yesterday's tasks. What should the agile coach do first to address the situation?

Options:

A.

Emphasize the ground rules and then focus on today's activities and impediments.

B.

Let the discussion go on as it is important that the team is clear on priorities for the

day.

C.

Address the team members involved during the next sprint retrospective.

D.

Avoid the discussion by referring to the team charter.

Question 397

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

Options:

A.

Communicate the situation to the team and plan for the necessary training and coaching arrangements

B.

Report the situation back to upper management and request to have the scope changed

C.

Plan to hire more experienced team members and lay off a few of the existing team members.

D.

Communicate the situation to the customer and inform them about potential delays in delivery.

Question 398

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

Options:

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Question 399

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

Options:

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Question 400

A project manager is managing a government project that targets the development of

small businesses in remote towns. The project team is having difficulty conducting

entrepreneurship training in some of the targeted towns because the local municipal

governments will not authorize the training. As a result of the delay, project implementation is at risk.

What is a probable reason for this?

Options:

A.

The project should have constructed training centers in the remote towns.

B.

The project did not identify and engage the correct stakeholders.

C.

The project should have representatives in all the remote towns.

D.

The project did not fully engage the project sponsor.

Question 401

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification

B.

Promote the team member to product owner to leverage the new knowledge with the clients

C.

Provide an incentive to team members who begin using the new tool on this project.

D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team

Question 402

A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end

What action should the project manager take to motivate the project team’s performance?

Options:

A.

Send a formal notice to team members instructing them to maintain performance

B.

Hire a few temporary team members to help with the additional work

C.

Award certificates of appreciation to encourage the team

D.

Inform the team about the delivery pressure from the project sponsor

Question 403

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

Options:

A.

Communication training

B.

Negotiation training

C.

Emotional intelligence training

D.

Agile training.

Question 404

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

Options:

A.

Speak with peers about the need for a project charter

B.

Develop the project charter and send it for approval

C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities

D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan

Question 405

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)

Options:

A.

A lot of discussions that yield no results or possibly too many results

B.

A lack of direction and motivation for the team in the workshop

C.

Lessons learned from other teams to not be considered

D.

Time management plan for the retrospective workshop to not be updated

E.

A focus on the negative and a disinterest in further improvements

Question 406

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?

Options:

A.

Add an entry in the risk log

B.

Implement the changes

C.

Review target benefits.

D.

Improve the team's velocity

Question 407

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low-level risks remain

What should the project manager do now?

Options:

A.

Reduce the priority of project risks as all remaining risks are low-level

B.

Notify stakeholders that all high-level risks have been resolved

C.

Reevaluate identified risks and update the risk register

D.

Reclassify low-level risks as high-level risks

Question 408

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) -> stops working and crashes the system

1.500 rpm (rate-per-minute) -> warns of max rate allowed

1.400pm (rate-per-minute) -> reduces the power and brakes the engine

Which of the following statements is correct?

Options:

A.

0 1,600 rpm is a project risk,

1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,

1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and

1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.

1,500 rpm is a project issue and 1,400 rpm is a project risk.

Question 409

A project manager is implementing a new software system Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes

What should the project manager have done at the start of the project to prevent this resistance?

Options:

A.

Created a communications management plan that outlined the method of communicating to stakeholders.

B.

Ensured that the company culture encourages changes before accepting the project

C.

Encouraged leadership to discuss the change with departments that are typically resistant to change

D.

Involved stakeholders from all levels of the company so everyone understands the change

Question 410

During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?

Options:

A.

Include stakeholders during daily standup meetings to monitor progress.

B.

Validate acceptance criteria with stakeholders prior to backlog refinement

C.

Avoid including stakeholders in iteration reviews.

D.

Create a requirements traceability matrix and distribute it accordingly

Question 411

During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.

What should the project manager do to prioritize this critical impediment?

Options:

A.

Solve the issue for the team member.

B.

Perform a brainstorming session to address the issue and add the solution to the sprint.

C.

Escalate the issue to the software vendor for technical resolution

D.

Coach the team to come up with their own solution and add it to the next sprint

Question 412

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond’

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced

B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework

C.

Record the issue in the issue log and escalate the conflict to the project sponsor for

assistance

D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews

Question 413

A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?

Options:

A.

Analyze the quality requirements.

B.

Plan quality management

C.

Continually survey the quality of the deliverable

D.

Set up quality policies and procedures

Question 414

A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)

Options:

A.

Use the project's contingency budget

B.

Create a change request with the scope of the new internal projects.

C.

Influence the client to initiate a new project.

D.

Create a work breakdown structure (WBS) of the new scope with the internal projects

E.

Manage the quality of the delivery

Question 415

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

Options:

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Question 416

A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.

What should the project manager do next?

Options:

A.

Consult with the project sponsor to discuss a cost increase

B.

Acquire approval for an exception to the implementation of the new regulation.

C.

Get approval for the additional budget from the steering committee

D.

Meet with subject matter experts (SMEs) to assess the impact to objectives

Question 417

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?

Options:

A.

Identify the problem's root causes and define the ground rules with all project team members to minimize interferences

B.

Hire a coach to help all project teams to improve their abilities to solve problems on

their own.

C.

Reunite with the project team members affected and tell them not to reduce the team's capacity

D.

Recommend to the project team members that they should improve their planning

and make their stones smaller

Question 418

An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right

Question # 418

Options:

Question 419

A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members

What is the cause for this communication gap?

Options:

A.

The project sprint board has not been updated

B.

Daily standup meetings were not held or enforced

C.

The project status dashboard has not been updated

D.

The communications management plan has not been developed

Question 420

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)

Options:

A.

Ask the team members to analyze the impact of including this regulation

B.

Ask the stakeholders about the priority of this regulation

C.

Ask the product owner to include the requirements in the product backlog

D.

Ask the security department for details about regulations

E.

Ask the team members to include the requirements in the next iteration

Question 421

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

Options:

A.

Select a predictive development life cycle based on the team's experience

B.

Determine the most appropriate life cycle approach for the project

C.

Register all requirements into a backlog for further detailed analysis.

D.

Split the requirements, put them into two separate projects, and apply different approaches

Question 422

An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team

What should the project manager do?

Options:

A.

The project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs

B.

The project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team

C.

The project manager should allow the resources to periodically choose on which team they would like to work.

D.

The project manager should indicate that the team members have already been assigned to a team through workforce optimization

Question 423

A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.

What should the project manager do?

Options:

A.

Prepare and submit a status report to the steering committee to update performance monitoring

B.

Determine the data to be monitored during the project as well as the expected performance and targets.

C.

Update the communications management plan to consider performance review meetings with the project stakeholders

D.

Conduct reviews with stakeholders to discuss the potential benefits the approach may have to the project

Question 424

A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project

What should the project manager have the project team update to ensure proper communications to stakeholders?

Options:

A.

Project management plan

B.

Stakeholder engagement plan

C.

Stakeholder register

D.

Communications management plan

Question 425

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

Options:

A.

Address the lack of performance by coaching the new team member

B.

Discuss options to improve performance with the resource manager

C.

Provide performance feedback as part of the retrospective ceremony.

D.

Request a more efficient replacement resource from the project sponsor

Question 426

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change

B.

Ask the product owner to review the product backlog

C.

Ask the team members to analyze the impact of this change

D.

Ask the sponsor to approve the change request

E.

Ask the team members to include the change in the next iteration

Question 427

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

Options:

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Question 428

A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?

Options:

A.

Plan a working session focusing on the scope, vision, and mission of the initiative

B.

Start developing the project management plan based on a previous project template from the project management office (PMO).

C.

Conduct benchmarking to determine the business viability of the initiative

D.

Conduct an impact analysis of the new initiative to determine how the project should be rolled out

Question 429

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register

What should the project manager do?

Options:

A.

Assign the documenting task to a project team member

B.

Ask the SME to document and capture the occurrence.

C.

Request the SME to wait until the project closure phase.

D.

Take ownership of documenting this information

Question 430

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

Options:

A.

Develop the resource management plan and ensure adequate training

B.

Replace the current project team members

C.

Outsource the task to be completed by a specialized vendor.

D.

Update the issue log to account for the lack of team member qualifications

Question 431

A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget

Which two actions should the project manager take initially to resolve this problem? (Choose two)

Options:

A.

Check the risk register for a prepared response to a resource being suddenly unavailable.

B.

Check if the team member's activities are sufficiently documented to facilitate handover

C.

Check the project's responsibility assignment matrix (RAM) to determine which activities will be affected

D.

Reassign responsibilities across the remaining members using the available float for training.

E.

Obtain the project sponsors support to replace the team member on leave

Question 432

A company's CEO has just returned from a conference on the use of artificial intelligence (Al) and would like the project manager to implement this technology in the organization What should the project manager do first?

Options:

A.

Start developing a business case.

B.

Start a strengths, weaknesses, opportunities and threats (SWOT).

C.

Engage stakeholders and allocate resources

D.

Gather requirements from stakeholders

Question 433

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

Options:

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Question 434

A project manager is acting as a scrum master in a hybrid project and is dealing with a conflict between team members What strategy should be used to handle this conflict?

Options:

A.

Sort conflicts into two groups: positive and negative

B.

Place conflicts into categories: structural and interpersonal.

C.

Place conflicts on a shared conflict list and ensure it is visible

D.

Review conflicts during daily Scrum so they are handled in a timely manner

Question 435

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)

Options:

A.

Conduct a stakeholder analysis.

B.

Reinforce team communication.

C.

Update the project management plan with the new timeline

D.

Adopt an incremental approach

E.

Leverage work between team members

Question 436

A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities

How should the stakeholder be engaged in the project?

Options:

A.

Keep the stakeholder informed and consult with them based on their needs

B.

Involve the stakeholder in governance and decision making

C.

Consult with the stakeholder and increase their level of interest

D.

The stakeholder needs to be made aware of the project progress

Question 437

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

Options:

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change is

acceptable

Question 438

A project manager has been appointed to a multimillion-dollar project The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support

What approach should the project manager take?

Options:

A.

Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project

B.

Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs

C.

Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk.

D.

Host a project team meeting, then update the risk register and the project management plan

Question 439

A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork

What should the project manager do to improve morale?

Options:

A.

Identify the wants and aspirations of the team

B.

Build team connections and emotional bonds

C.

Forge consensus through team participation.

D.

Set goals and push the team to achieve the goals

Question 440

After the project charter's approval the project manager needs to work on detailed project requirements, constraints and assumptions with stakeholders However, not all of the stakeholders are immediately available for a meeting in the short term.

What should the project manager do in order to gather the information needed from stakeholders?

Options:

A.

Email, call, or meet with each stakeholder separately to obtain their input

B.

Conduct a meeting to build the project management plan with the stakeholders who are available

C.

Escalate to the project sponsor that not all stakeholders are available for a meeting

D.

Meet with the project management team to build the project management plan before consulting stakeholders

Question 441

At the end of a meeting a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project What should the project manager do in this situation?

Options:

A.

Develop a work plan for the project team member with the help of the resource manager

B.

Advise the functional manager and the project team member to review the resource management plan

C.

Tell the functional manager and the project team member to review the project

charter

D.

Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member

Question 442

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

Options:

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Question 443

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

Options:

A.

Encourage all team members to use a virtual workspace

B.

Ask the team to send emails with detailed task progress

C.

Talk to the team member about their engagement and take appropriate action.

D.

Reassign the work to a resource who participates in the daily calls

E.

Report the team member’s poor performance to the functional manager

Question 444

During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?

Options:

A.

Ask upper management for more funds and update the project budget

B.

Revise the project scope accordingly to cope with the budget changes

C.

Update the risk register and project log. and manage the budget closely.

D.

Submit a change request to accelerate the project as requested

Question 445

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

Options:

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Question 446

After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

Options:

A.

Share the customer feedback with the project team

B.

Follow the meeting agenda and make a list of the next deliverables

C.

Document this feedback in the meeting minutes.

D.

Start planning how to improve the dates of next deliverables

Question 447

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

Options:

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan

B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels

C.

Consult the resource management plan for an appropriate response

D.

Continue with existing sprint plans to ensure some of the scope will be delivered

Question 448

An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project

What should the project manager do?

Options:

A.

Train the team on the new regulations as requested by management

B.

Get commitment from the team to include all of the required regulations

C.

Ask the project sponsor to add more time to the project.

D.

Share with participants the need to focus only on product functionality

Question 449

A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two)

Options:

A.

Revisit the team's discussion on team behaviors and norms

B.

Report to the project manager about the new team member’s behavior

C.

Coach the new team member to improve engagement with the team.

D.

Force the new team member to participate in activities that are considered easy

E.

Facilitate an open discussion on all ideas and perspectives

Question 450

In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product

What should the project manager do?

Options:

A.

Add this risk to the risk register and monitor it according to the risk management plan

B.

Escalate this to higher management and ask for help to resolve the issue.

C.

Impose the delivery dates on the software team leader and notify the functional manager about the situation

D.

Ask the software team leader to use a predictive approach and commit to a delivery date

Question 451

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

Options:

A.

Raise a change request to immediately implement the printing module component.

B.

Escalate this issue to the project sponsor immediately

C.

Ask the project team to conduct a quality audit of the printing module components.

D.

Meet with the project team to understand the issue and define actions.

Question 452

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule

What can the project manager do to move the team to the norming phase?

Options:

A.

Plan social activities to help foster stronger interpersonal relationships and identify shared goals.

B.

Speak with the project sponsor about changing the team composition

C.

Figure out who is behind the issues and apply progressive disciplinary techniques.

D.

Show the team the schedule impact of their communication issues and encourage them to put their differences aside

Question 453

During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?

Options:

A.

Defined the expected agile team contribution in the creation of the backlog.

B.

Assessed the capabilities of the agile team and planned for the required training

C.

Defined the team ground rules and shared project vision.

D.

Communicated project vision and sprint goals clearly to the team

Question 454

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

Options:

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

Question 455

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

Options:

A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Question 456

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

Options:

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

Question 457

The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources

What strategy should the project manager use in order to keep delivering value in a restricted environment?

Options:

A.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance

C.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

D.

Restrict the project scope only to basic critical features and run the project with the current staffing level until all of the budget is consumed

Question 458

A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points

Which team is performing better?

Options:

A.

Team A as they have calculated fewer story points than team B.

B.

Team B as they have calculated more story points than team A

C.

The team that completes the most stories selected from the sprint backlog

D.

The team with the least amount of defects in their deliverables

Question 459

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

Options:

A.

Contact the team member's functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Question 460

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

Options:

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

Question 461

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?

Options:

A.

Issue log

B.

Project management plan

C.

Risk management plan

D.

Risk register

Question 462

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

Options:

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Question 463

While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined The actual invoice payments received have also been late and were outside of the contracted payment schedule Recent invoices have only been partially paid

What should the project manager do?

Options:

A.

Add nonpayment to the issue log and keep tracking payments

B.

Hold a meeting with the client to address the issue

C.

Review past projects for payment-related lessons learned

D.

Conduct a meeting with the project team to update the procurement management plan

Question 464

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?

Options:

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

Question 465

A company is using a predictive approach for the development of a particular component as defined in the scope management plan Due to regularly changing regulatory requirements, the development team has requested to utilize agile approaches

What should the project manager do about the development team's request"?

Options:

A.

Escalate the request for additional financial resources

B.

Forward the request to the project management office (PMO) to amend the organizational process assets

C.

Ask the project sponsor to obtain approval for implementation of the new approach

D.

Analyze the requirements that will need to be addressed under the requested method

Question 466

At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?

Options:

A.

Project audit

B.

Lessons learned

C.

Organizational process assets

D.

Procurement audit

Question 467

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

Options:

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

Question 468

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

Options:

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

Question 469

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?

Options:

A.

Execute it as a Scrum project

B.

Execute it as a predictive project

C.

Execute it using the same approach as the reference project

D.

Execute it as a project with stage gates

Question 470

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done

What kind of leadership style should the project manager use at this stage?

Options:

A.

A directive style that makes decisions for the group to reach early outcomes

B.

A leadership style that coaches people who want help and fosters greater team collaboration

C.

A passive leadership style that allows the team to self-organize until the norming stage is reached

D.

A democratic style that uses techniques where majority opinion prevails

Question 471

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?

Options:

A.

Seek expert legal advice on the interpretation of the clauses in the contract

B.

Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned

C.

Close the project and hand over the deliverables to the client

D.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects

Question 472

A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?

Options:

A.

Ask the project sponsor for assistance in getting the budget back on track

B.

Meet with the project team to analyze the actual cost to determine deviations

C.

Inform the stakeholders that the project will be finished over budget.

D.

Issue a change request including the analysis to increase the budget

Question 473

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible

What should the project manager use to identify the risks?

Options:

A.

An analysis of shared risks between parties

B.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

C.

Expert judgment

D.

A risk value assessment

Question 474

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

Options:

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Question 475

A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful

What should the project manager do in this scenario?

Options:

A.

Develop a business case with assumptions for the new model

B.

Develop a communications management plan to inform the employees about the new business model

C.

Adopt an iterative rollout approach that delivers the highest business value earlier

D.

Develop a detailed sprint plan with clear deliverables

Question 476

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?

Options:

A.

Revisit the communications management plan and make necessary adjustments

B.

Revisit the scope management plan and note this as a risk

C.

Schedule a meeting with the product owner and finance team to agree on course corrections

D.

Continue developing based on the project management plan and address the issue post delivery

Question 477

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee

B.

Functional managers

C.

Board of directors

D.

Advisory team panel

E.

Chief executive officer

Question 478

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

Options:

A.

Review the project scope and negotiate with the contractor

B.

Refuse the offer as it is included in the initial project scope

C.

Review the project costs and communicate this to the project sponsor

D.

Submit a change request to approve the offer

Question 479

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?

Options:

A.

Ask the human resources director to appoint a senior team leader

B.

Inform the project sponsor about the possible delay

C.

Directly manage the project team to avoid project delays

D.

Provide mentoring to the newly appointed team leader

Question 480

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

Options:

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Question 481

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

Options:

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Question 482

A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter

What should the project manager do?

Options:

A.

Modify the baseline of the project for minor impact changes to the project scope

B.

Use a focus group and brainstorming sessions to gather more details about the project scope

C.

Register the changes in the configuration management plan and send it to the change control board (CCB).

D.

Explain to the sponsor that these requests could endanger the schedule and cost of the project

Question 483

A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.

Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck

Question # 483

Options:

Question 484

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

Options:

A.

Organize regular meetings with all of the deployment teams to share issues and solutions

B.

Propose that some of the teams delay deployments in their countries

C.

Ask the project sponsor to appoint new managers for the deployment teams

D.

Ask each deployment team to provide a very detailed schedule and action plan

Question 485

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed

Which two actions should the project manager take? (Choose two)

Options:

A.

Convince the customer to leave the second milestone in place and not change it.

B.

Escalate the issue to upper management to resolve the problem and suggest a plan.

C.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

D.

Ask the customer for their priorities regarding the requirements for the second milestone

E.

Tell the customer that moving the milestone has a very high impact on the cost of the project

Question 486

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

Options:

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Question 487

A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget

What should the project manager do next?

Options:

A.

Request a replacement resource

B.

Perform a cost-benefit analysis

C.

Implement risk responses

D.

Perform Integrated Change Control

Question 488

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?

Options:

A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve

B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.

C.

Get confirmation from management that the team member has enough experience

to build software without quality control

D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project

Question 489

One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?

Options:

A.

Start an audit of the vendor's processes and procedures

B.

Review lessons learned from previous projects with this vendor

C.

Make a detailed analysis on vendor issues during the project

D.

Execute a contingency plan to address the issue with the vendor

Question 490

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

Options:

A.

Networking

B.

Emotional intelligence

C.

Conflict management

D.

Influencing

Question 491

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?

Options:

A.

Request to use the management reserve to keep the schedule

B.

Mitigate risks associated with the workaround to avoid project delays

C.

Proceed with the approved risk response plan.

D.

Discuss the options with the client as part of the change control process

Question 492

One of a project manager’s team members is continuously improving This team member has been a role model and mentor to others in the organization

How should the project manager acknowledge this team member’s commitment?

Options:

A.

Send this person to a meeting to negotiate the scope with the client

B.

Appreciate this team member’s performance throughout the project life cycle

C.

Promote this team member to a coaching role after this project is completed

D.

Document it in the team member’s end of year performance review

Question 493

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to

compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Question 494

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

Options:

A.

Modify the communications management plan to account for regional differences

B.

Conduct cultural awareness seminars

C.

Hold a virtual meeting to discuss the political environment.

D.

Conduct a multigenerational management training session

Question 495

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

Options:

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Question 496

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

Options:

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

Question 497

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders The project manager has been assigned and is now in the project planning phase

What item(s) should the project manager develop first?

Options:

A.

A product backlog and identification of the features to be delivered

B.

A business case and scope document

C.

A communications management plan that addresses the team's needs

D.

A risk management plan to incorporate known risks

Question 498

A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?

Options:

A.

Include the executives in team retrospectives

B.

Train the executives on agile practices

C.

Negotiate with the executives and agree on a process.

D.

Request that the executives use agile practices

Question 499

An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework

What should the project manager do in this situation?

Options:

A.

Include impediment resolutions during daily standup meetings

B.

Perform a root cause analysis during the standup meetings

C.

Create a dedicated sprint to solve the obstacles with the team

D.

Promote collaboration to help remove the obstacles for the team

Question 500

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?

Options:

A.

Schedule a meeting with all stakeholders to extend the project deadline

B.

Replace the vendor with a new vendor who can offer the component on time

C.

Add an item to the next status review to make stakeholders aware of the vendor issue.

D.

Review and update the issue log and determine if any alternative components can be offered

Question 501

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

Options:

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

Question 502

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

Options:

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Question 503

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

Options:

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Question 504

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Question 505

A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the

project?

Options:

A.

Confer with team members.

B.

Review with security experts.

C.

Schedule regular project audits.

D.

Discuss with the customer.

Question 506

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

Options:

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

Question 507

A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members

on the team who have more experience with similar tasks.

What should the project manager do?

Options:

A.

Ask one of the more experienced team members to support the team member with the task.

B.

Reassign the task to one of the more experienced project team members for a faster completion of the assigned task.

C.

Ask the experienced team members to produce a manual on how to complete the task.

D.

Inform the project management office (PMO) of the issue and request a replacement for the less experienced team member.

Question 508

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

Options:

A.

Use the team's connections with international colleagues to get early warnings on future changes.

B.

Keep the focus on the priority items while the change goes through the change control process.

C.

Reject the change request since it may negatively impact the project's performance.

D.

Implement the change request as soon as possible to avoid accumulating new scope.

Question 509

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

Options:

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

Question 510

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to

ensure the community members are up to date on project progress?

Options:

A.

Share project updates when requested by the stakeholders.

B.

Share project updates through regular community meetings.

C.

Share the annual reports virtually and in the local newspapers.

D.

Share the project reports with the sponsor to inform community members.

Question 511

A project manager works in an organization that embraces using different project approaches. The project manager's current project uses a

predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams

are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current

impediments.

What should the project manager do?

Options:

A.

Ask the members to be more proactive and share ideas with each other.

B.

Set up a daily virtual meeting with the development team.

C.

Plan a monthly virtual meeting to align and to review the plans.

D.

Review the issue with the project sponsor and ask for support.

Question 512

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Question 513

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Question 514

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

Question 515

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Question 516

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Question 517

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience

performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work,

B.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product

C.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Question 518

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

Options:

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Question 519

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

Options:

A.

Determined the appropriate type of incentive for key team members

B.

Conducted frequent monitoring on key team members’ performance during project execution

C.

Distributed the monetary incentive according to the team members’ individual performance

D.

identified the underperforming team members and asked the human resources (HR) department to replace them

Question 520

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the

company’s competitive advantage. What should the project manager do?

Options:

A.

Reject all requested changes and bypass the company's change control process.

B.

Encourage the project team to add premium features to impress the client.

C.

Start the process to include the new features of the product on the next iteration.

D.

Allow all requested changes and bypass the company's change control process.

Question 521

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.

Finish to start

B.

Start to start

C.

Start to finish

Question 522

A learn member has a sudden emergency that may last for several days. There are no other team members who can cover their tasks and job duties. What should the project manager do to address this concern?

Options:

A.

Hold an emergency project team meeting to discuss the situation.

B.

Ask the human resources (HR) manager for an external replacement.

C.

Log the situation in the issue log.

D.

Update the key stakeholders on the issue.

Question 523

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

Options:

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Question 524

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

Options:

A.

Tell the client about the chance for the potential delay.

B.

Work with the project team to evaluate the potential delay.

C.

Do not disclose the likelihood of a delay as it is yet to happen.

D.

Ask the project sponsor to inform the client in the next update.

Question 525

A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.

What should the project manager do to ensure all team members participate in daily meetings?

Options:

A.

Analyse the team members' influence levels and schedule a training on the importance of daily standups and the time-bound feature of the meetings.

B.

Require all team members to attend the daily review meetings as they ate requested by the project sponsor.

C.

Inform the functional manager and replace (earn members who cannot join the daily progress meetings.

D.

Review the influence of each team member, call the team members with the highest influence to a meeting, and convince them to join the daily standups.

Question 526

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Options:

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Question 527

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?

Options:

A.

Set up a meeting with the team to discuss and determine the project's challenges.

B.

Propose a revised project schedule to the sponsor as the delays have affected the time lines.

C.

Schedule a meeting with the sponsor to express the team's frustrations about the data.

D.

Meet with the data suppliers to explain the critical timing requirements of the project.

Question 528

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Options:

A.

Request marketing to launch an advertising campaign for the product that is currently in stock.

B.

Update the project management plan, factoring in furloughs of the assembly team to reduce expenses.

C.

Explore if the materials could be supplied locally and obtained on time.

D.

Meet with the engineering team to manufacture the materials in-house.

Question 529

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Question 530

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Question 531

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change

requests issued due to the nature of the project.

What should the project manager do?

Options:

A.

Add a fixed number of change requests allowed by the client on the project baseline.

B.

Request sponsor approval for all change requests to reduce the number of changes.

C.

Initiate the number of iterations to reduce the number of change requests.

D.

Reduce the number of approvers required to implement a change request.

Question 532

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that communications were sent to all stakeholders when requirements change

B.

Ensured procurement contracts were able be canceled when situations like this arise

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured changing stakeholder needs and requests were properly monitored

Question 533

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Question 534

A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.

When will the project manager be able to provide the requested information?

Options:

A.

During the planning phase, when processes for scope definition and activity duration and sequencing will be performed

B.

As soon as possible, as project delays can be significantly avoided when a schedule is developed early

C.

Close to the end of the project, as the forecasts will be more accurate and most risks will already be mitigated

D.

In the initiation process, as it happens concurrently with the project contract and project charter creation

Question 535

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

Options:

A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Question 536

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

Options:

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Question 537

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

Options:

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

Question 538

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

Options:

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

B.

Maintain the same task allocation structure to avoid any disruption in the project team.

C.

Move the developer to another team and look for a replacement developer.

D.

Request that all quality assurance tasks be allocated to the new resource.

Question 539

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

Question 540

A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.

What should the project manager do?

Options:

A.

Send out daily emails with the project status and task lists to all team members.

B.

Meet daily with the project team and include a monthly report on the risks and issues.

C.

Distribute a project newsletter that includes any project changes and required project information.

D.

Encourage collaboration on a daily basis, facilitating different communication channels.

Question 541

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

Options:

A.

Personas

B.

Power influence grid

C.

Power user grid

D.

Salience model

Question 542

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Ignore the obstacle and present the partial solution to the customer

C.

Focus on generating business value despite the obstacle

D.

Make changes to reprioritize the backlog because of the obstacle.

Question 543

A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly

requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes

of a request. Both of them are equal in seniority and both report to the same functional manager.

How should the project manager proceed?

Options:

A.

Update the communications management plan and the stakeholder engagement plan.

B.

Escalate the issue to the functional manager and explain the situation to them.

C.

Negotiate a mutually agreeable feedback cycle with acceptable timelines.

D.

Refer the lead project manager to the communications management plan.

Question 544

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

Question # 544

Options:

Question 545

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?

Options:

A.

Focus on the implementation of a software as a service (SaaS) solution for the customer.

B.

Specify the scope and features to be deployed in the contract clearly.

C.

Work very closely with the customer and third parties to meet their needs.

D.

Change the marketing and product management definitions to meet stakeholder needs.

Question 546

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

Question # 546

Options:

Question 547

A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.

What should the project manager do to keep the team performing as effectively as possible?

Options:

A.

Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance,

B.

Transition the team from an agile approach to a predictive approach for better performance cantral.

C.

Provide the team with virtual collaboration software and training on the software to minimize disruption,

D.

Evaluate project performance and step in if performance decreases to. an unacceptable level,

Question 548

In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have

most likely caused this communication breakdown?

Options:

A.

The sprint review meetings were not held regularly.

B.

The daily standup meetings were not consistently attended.

C.

The project manager failed to develop a communications management plan.

D.

The weekly project status reports were not published regularly.

Question 549

A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures

What should the project manager do?

Options:

A.

Follow the Perform integrated Change Control process and submit a change request

B.

Ask the team members to draft a justification before processing the reimbursements

C.

Update the project management plan with the incurred costs

D.

Review the budget and allocate funds for the reimbursements

Question 550

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.

What should the project manager do in this situation?

Options:

A.

Engage the functional managers to describe the project's impact to the team members directly.

B.

Provide team members with specific and clear instructions on the project objectives and tasks.

C.

Communicate the project's impact and plans to engage the project team throughout the project.

D.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

Question 551

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

Options:

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.

A hybrid approach will allow the project manager to revise the product specifications.

D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Question 552

At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.

What should the project manager do in the future to avoid this situation?

Options:

A.

Create better plans to test the functionality in more detail.

B.

Review the definition of done (DoD) with the product owner.

C.

Include previous sprint defects and close them in the actual sprint.

D.

Get approval from the product owner on the user stories.

Question 553

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

Options:

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Question 554

In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The

discussion has intensified and the team members are not able to agree.

What should the project manager do next?

Options:

A.

Remove one of the team members from the project to improve team dynamics.

B.

Make a decision based on expert judgment as a project manager.

C.

Consider the view of each team member about the issue in order to reach consensus.

D.

Remove both team members since they are not productively adding to the team.

Question 555

A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?

Options:

A.

Assign the challenging tasks to the team member.

B.

Ask the product owner to assign the challenging tasks.

C.

Reprioritize the challenging tasks to future sprints.

D.

Coach the team member to pick up the challenging tasks.

Question 556

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?

Options:

A.

Allow the agile team to decide what they are able to deliver in each iteration

B.

Ask the team for additional feedback and add tasks to the task board,

C.

Hold a brainstorming session to identify the root cause of the complaints.

D.

Document the customer's complaints and critical issues in the issue log.

Question 557

A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?

Options:

A.

Submit a change request to transfer the risk to a third party in case it becomes an issue.

B.

Remove the user stories associated to that risk and avoid the impact to the project deliverables.

C.

Assign a qualified team member to be the risk manager for the project.

D.

Ask the team to monitor the risk and provide an alert if it becomes an issue.

Question 558

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

Options:

A.

Escalate the problem to the product owner.

B.

Ask the PMO to review the framework

C.

Request the PMO to define a new framework.

D.

Plan a brainstorming session with the project team

Question 559

In a marine construction project, the project manager is informed by the marine authority that the work permit will not be issued until certain environmental reinforcement work has been completed. After reviewing the project management plan, the reinforcement work is not included in the project scope.

What should the project manager do?

Options:

A.

Organize a meeting with the team and update the work breakdown structure (WBS).

B.

Raise this issue, and review and update the progress report for the next monthly project meeting.

C.

Start the organization's change control process via a change request.

D.

Communicate with an officer in the environmental protection department to check if it is necessary.

Question 560

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

Options:

A.

Establish the team ground rules and share them with the team for strict adherence.

B.

Copy the ground rules established by another project and provide them to the teams.

C.

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.

D.

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Question 561

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to

water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Question 562

An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.

What should the project manager do to manage business concerns and expectations before starting the project?

Options:

A.

Meet with the project finance team to measure market variations and product impact.

B.

Direct the project team to estimate user stories in greater detail.

C.

Ask the product owner to prioritize the backlog items based on the return on investment (ROI).

D.

Request that the project team develop a release plan and roadmap for the project.

Question 563

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.

B.

Invite the product owner to future demonstrations where they can provide feedback.

C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.

D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.

Question 564

In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?

Options:

A.

Ask the team to focus only on the goal, not on ad hoc meetings.

B.

Coach the project owner about the implications of unplanned meetings.

C.

Discuss the issue with the project owner at the retrospective meeting.

D.

Escalate the situation to management because it is affecting the team.

Question 565

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

Options:

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance

regulations.

B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Question 566

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

Options:

A.

Forming

B.

Mourning

C.

Storming

D.

Norming

Question 567

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Question 568

A project manager is working with several junior engineers on a project. The project manager noticed that when the junior engineers are asked questions, they defer te more senior team members on the team for answers. Having worked with the junior engineers on another project, the project manager knows they are capable of making these minor decisions correctly.

This uncertainty from the junior engineers is now slowing progress.

‘What should the project manager do?

Options:

A.

Update the risk register to reflect the possible impact of the projects slower progress,

B.

Ensure the junior engineers make decisions within a certain responsibility level and commit to it,

C.

Remove the junior engineers from any decision-making activity until further trained.

D.

Pair senior engineers to shadow the junior engineers and correct them throughout.

Question 569

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource's refusal?

Options:

A.

Speak directly with the resource.

B.

Communicate with their supervisor.

C.

Organize a team meeting.

D.

Speak with their colleague.

Question 570

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

Options:

A.

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.

B.

Work with the local government to build the profiles of employees that will be working in the store.

C.

Work with the organization's legal department to identify local regulations to ensure project compliance.

D.

Work with the organization's project management office (PMO) to build a project team of residents located in the city.

Question 571

A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)

Options:

A.

Keep the team engaged and focused on the project's direction.

B.

Encourage the team to do a brainstorming session and provide a mitigation plan.

C.

Focus on the resource management plan and track project progress,

D.

Set a clear vision for the project and ensure it is visible to all stakeholders.

E.

Organize a team-bonding activity and invite an external manager to speak to the team.

Question 572

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

Options:

A.

Focus the discussion on recovery and ways to get back on track.

B.

Act in a way to highlight the criticality of the situation.

C.

Punish the team member for providing negative data that will affect the team's morale.

D.

Thank the team member for raising this issue, log it, and move on to the next topic.

Question 573

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Question 574

A project manager is managing a complex project with a high number of artifacts. Some of the stakeholders are having issues accessing the artifacts. How should the project manager address this situation?

Options:

A.

Ensure that the project artifacts are kept up-to-date and shared with the stakeholders.

B.

Invite the stakeholders to the daily standup to clarify any questions about the project artifacts.

C.

Escalate the stakeholders' project artifacts concerns to the project management office (PMO) for resolution.

D.

Send an agile report to the stakeholders, which includes the list of the project artifacts.

Question 575

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Question 576

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

Options:

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Question 577

A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.

What should the project manager do?

Options:

A.

Plan a training session for the new team members not familiar with the system.

B.

Communicate the rules and criteria to the team members through email.

C.

Work only with the team members familiar with the system

D.

Document which rules and criteria the new team members are not familiar wit

Question 578

A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.

How should the project manager proceed?

Options:

A.

Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals

B.

Include the feasibility activities in the prefeasibility study and apply for a change of scope and budget.

C.

Obtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved

D.

Secure approval of the prefeasibility study before proceeding with the feasibility activities.

Question 579

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

Options:

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Question 580

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

Options:

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.

B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex

items.

C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.

D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define

the project scope.

Question 581

During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask

the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.

How should the project manager address this situation?

Options:

A.

Seek help from experts to support the team member in fixing the problem.

B.

Facilitate a session to reach an agreement with the team as a whole.

C.

Negotiate with the customer a delay in the project delivery.

D.

Accept the team's request to reassign the team member.

Question 582

A project manager is assigned to an organizational transformation project. The company typically defines individual performance plans at the beginning of the year, and functional managers conduct feedback reviews at the end of the year. The transformation project team members are concerned that the work they are doing for this project is not aligned with the work included in their individual performance plan for the year.

What should the project manager do?

Options:

A.

Meet with the functional managers to align the expected frequency and results reporting for the team members.

B.

Provide performance feedback to the learn members' functional managers at the end of the year.

C.

Assure team members that this project is a high priority for the company and they will be evaluated accordingly.

D.

Request to be made responsible for the performance plans of those on this project team

Question 583

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

Options:

A.

Schedule a high-priority meeting with the project stakeholders to discuss the issue.

B.

Initiate a change request to obtain additional funds from the management reserve.

C.

Meet with the project team and customer to brainstorm about potential solutions.

D.

Collaborate with the relevant stakeholders on implementing the risk response plan.

Question 584

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

Options:

A.

Dedicate the next sprint to completing the missing details.

B.

Apply fast-track techniques to work on the missing details in parallel,

C.

Continue iterating and monitoring quality aspects sprint by sprint.

D.

Create a new risk entry for the delay in the risk management plan.

Question 585

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

Options:

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver

value incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the

project.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end

of the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

Question 586

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.

Risk register information

B.

Higher-level activities completed

C.

Milestones status report

D.

Resource breakdown structure (RBS)

Question 587

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

Options:

A.

Move the task to the next sprint.

B.

Ask the team member to bring up the concern in the next daily meeting.

C.

Send an email explaining the issue to all team members.

D.

Reassign the task to another team member.

Question 588

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

Options:

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

Question 589

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

Options:

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project's purpose, mission, and vision.

D.

Carry out the product backlog creation.

Question 590

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

Options:

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

Question 591

A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.

Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)

Options:

A.

Schedule regular meetings with the key stakeholder to provide updates and receive feedback,

B.

Share weekly status reports with detailed information about the project and team performance.

C.

Submit performance reports and task assignments to keep the stakeholder informed.

D.

Promote an adaptive and transparent environment where the team can easily communicate with the stakeholders.

E.

Provide training to the team on emotional intelligence and status reporting techniques.

Question 592

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

Options:

A.

Invite the stakeholders to the retrospective meetings.

B.

Invite the stakeholders to the sprint review meetings.

C.

Hold a meeting every 2 weeks with the stakeholders.

D.

Negotiate by sending an informative email to stakeholders.

Question 593

In a project, one core team member tends to do all the work and ensures all tasks are completed. This core team member is soon leaving the project, which may make the project vulnerable.

What should the project manager do?

Options:

A.

Ensure the activities of this team member are distributed across the project team.

B.

Assess a mechanism for knowledge transfer among the team members.

C.

Motivate the team member to stay by providing them with incentives.

D.

Ask human resources (HR) to counsel the team member to balance the workload.

Question 594

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

Options:

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Question 595

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Question 596

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?

Options:

A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.

B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.

C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.

D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.

Page: 1 / 199
Total 1988 questions