Labour Day Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMI-PBA PMI Professional in Business Analysis (PMI-PBA) Exam Practice Test

Page: 1 / 20
Total 199 questions

PMI Professional in Business Analysis (PMI-PBA) Questions and Answers

Question 1

The following requirement was included in a business requirements document: “An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized.” What should be done with this business requirement?

Options:

A.

It should remain because it specifies the reason why the business requirement is needed.

B.

It should be removed because it does not state how often the data should be synchronized.

C.

It should be revised because it states a solution to the problem rather than the business need.

D.

It should remain because it specifies the type of data and the source system.

Question 2

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

Options:

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Question 3

The requirements baseline is ready for sign-off when the requirements are:

Options:

A.

complete, clear, verified, and adopted.

B.

consistent, analyzed, complete, and validated.

C.

justified, clear, consistent, and verified.

D.

clear, consistent, complete, and validated.

Question 4

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.

Who should the business analyst contact to review the testing results and get approval to proceed with deployment?

Options:

A.

The tester identified in the testing strategy

B.

The person identified in the RACI matrix

C.

The project manager identified in the project charter

D.

The project sponsor identified in the scope document

Question 5

Which of the following techniques is used to identify ambiguous or unverifiable requirements?

Options:

A.

Fishbone analysis

B.

Resource checklist

C.

Traceability matrix

D.

Team peer review

Question 6

A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.

Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that

those issues are resolved?

Options:

A.

A Interviews

B.

Process modeling

C.

Estimation

D.

Problem tracking

Question 7

The business analyst is in the process of implementing a solution for a customer. The team is having difficulty confirming if certain requirements have been met.

What could have caused this issue?

Options:

A.

The test engineer has not properly communicated requirements to the team.

B.

Not all stakeholders were involved during requirements elicitation.

C.

Acceptance criteria for the requirements were not measurable.

D.

Requirements were not adequately reviewed with the project sponsor.

Question 8

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

Options:

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Question 9

Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s)

versioning?

Options:

A.

Statement of work

B.

Project plan

C.

Problem or opportunity statement

D.

Traceability matrix

Question 10

Once the requirements are compared to internal and external quality standards, what should the business analyst do next?

Options:

A.

Set the priority of the requirements.

B.

Communicate the requirements to stakeholders.

C.

Ensure that the requirements are validated.

D.

Baseline the requirements.

Question 11

A type of requirements document that would be the most valuable to a database administrator would be:

Options:

A.

a data flow diagram.

B.

a business process diagram.

C.

an entity relationship diagram.

D.

an object diagram.

Question 12

Which of the following actions will contribute most to the success of the initial stage of the project?

Options:

A.

Interview stakeholders to clearly define the problem.

B.

Document the requirements and obtain sign-off.

C.

Establish the change control process of the project.

D.

Define the acceptance criteria required during the acceptance phase.

Question 13

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

Options:

A.

Validate the requirements deemed important by the stakeholders.

B.

B. Obtain approval from engineering for partial testing of the requirements.

C.

Negotiate with the client to standardize the requirements.

D.

Assign a verification method to each requirement.

Question 14

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

Options:

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Question 15

The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.

What should the team do to reduce the risk of rework?

Options:

A.

Ask the project sponsor to prioritize the requirements.

B.

Organize a new elicitation workshop.

C.

Perform a Pareto analysis on the requirements.

D.

Validate the requirements before continuing with development.

Question 16

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Question 17

What are some of the components of a requirements management plan?

Options:

A.

Requirements definition, functional and non-functional requirements, and decision-making process

B.

Requirements work plan, requirements definition, and traceability matrix template

C.

Requirements work plan, prioritization process, and traceability matrix template

D.

Requirements definition, requirements attribute template, and traceability matrix template

Question 18

A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.

Which key factor drives the selection of business analyst activities to be included in the project?

Options:

A.

Communication plan

B.

Project life cycle

C.

Return on investment (ROI)

D.

Payback period

Question 19

A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project: the ordering process takes too long and often ends in incorrect orders.

What step should the business analyst take next?

Options:

A.

Schedule a requirements gathering sessions with the manager of the ordering department.

B.

Request information on the current ordering process and compare it with other companies.

C.

Identify testing resources to support the implementation.

D.

Select the software to implement and start working with the technical resources.

Question 20

How can a SWOT analysis help when deciding between several possible options to address a business problem?

Options:

A.

It can help the product owner to determine opportunity cost of not choosing an option.

B.

It can help the stakeholders to determine how to avoid the threats of each option.

C.

It can help the project sponsor to determine the valuation of each option.

D.

It can help the stakeholders identify the strengths and weaknesses of each option.

Question 21

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

Options:

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Question 22

A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?

Options:

A.

Conduct a formal or informal review of the requirements.

B.

Create and maintain an audit history log of changes to requirements.

C.

Provide a defect tracking log for review.

D.

Send an email requesting approval of requirements.

Question 23

A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

Options:

A.

verify that the test case is incorrect.

B.

let the users decide if the test result 1s acceptable.

C.

change the requirement according to the test result.

D.

ask the tester to perform the test again.

Question 24

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

Options:

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Question 25

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

Options:

A.

Project schedule and cost baseline

B.

Requirements traceability matrix

C.

Requirements attributes table

D.

Sequence diagram

Question 26

An organization is in the process of replacing its current system. The business analyst is charged with ensuring that all current connections to other systems remain functional after the upgrade.

What analysis should the business analyst conduct to facilitate a successful migration?

Options:

A.

Document

B.

User interface

C.

Interface

D.

Systems

Question 27

A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper," "Customer," and "Agent." These user groups

categorize stakeholders with similar needs and create a detailed narrative.

Which technique did the business analyst use for evaluating the solution's acceptance criteria?

Options:

A.

Stakeholder analysis

B.

Job analysis

C.

Persona analysis

D.

Risk analysis

Question 28

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

Options:

A.

Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

B.

Ask for more resources to manage this change and justify these additional resources with the value the change will give to

the company.

C.

Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.

D.

Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and

priorities with stakeholders.

Question 29

Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

What could the business analyst have established to help manage this situation?

Options:

A.

Change control process

B.

Configuration management system

C.

Communication plan

D.

Sponsor signoff

Question 30

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

Options:

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Question 31

Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?

Options:

A.

Decision tree

B.

Functional decomposition

C.

Expected monetary value

D.

Weighted criteria

Question 32

The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.

Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid

recommendation?

Options:

A.

Gap

B.

Risk

C.

Cost-benefit

D.

SWOT

Question 33

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

Options:

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Question 34

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

Options:

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Question 35

A business analyst is documenting the acceptance criteria to support a minor modification in a user portal. The analyst submits the criteria for review, but it is deemed incomplete and returned.

What could have caused the documentation to be returned?

Options:

A.

The analyst did not include the scope document in the acceptance criteria paperwork.

B.

The analyst failed to gather any baseline information.

C.

The analyst performed forward and backwards traceability.

D.

The analyst utilized user stories as a requirements document tool.

Question 36

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

Options:

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Question 37

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Question 38

A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.

What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will

need to have a discussion about the budget?

Options:

A.

Selected project life cycle

B.

Business analysis deliverables to be produced

C.

Type of elicitation activities to be conducted

D.

Decision on the type of models to be used

Question 39

A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new

functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create

project plans, schedule meetings, and provide meeting minutes.

In the scenario above, what is the role of the technical staff and testing team from Company A?

Options:

A.

Accountable

B.

Consult

C.

Responsible

D.

Inform

Question 40

The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?

Options:

A.

Which stakeholders have the most influence?

B.

Which functional areas are impacted?

C.

How is the organizational chart structured?

D.

What is the business need?

Question 41

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

Options:

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Question 42

When determining the value of a business case, which tool or technique should be used?

Options:

A.

Variance analysis

B.

Cost-benefit analysis

C.

SWOT analysis

D.

Feasibility analysis

Question 43

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Options:

A.

Evaluate the solution against the project charter.

B.

Conduct user acceptance testing.

C.

Evaluate the solution with the sponsor(s).

D.

Conduct performance testing.

Question 44

A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may

face monetary penalties.

What should the business analyst do next?

Options:

A.

Obtain approval from the project manager.

B.

Define the project scope.

C.

Follow the change control process.

D.

Update the requirements.

Question 45

When modeling processes or analyzing tasks, business rules can be uncovered by asking about:

Options:

A.

tasks that overlap with each other.

B.

work that may be performed out of sequence.

C.

reasons for choosing a particular course of action.

D.

task transitions that hinder organizational performance.

Question 46

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Options:

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Question 47

A business analyst has been assigned to a project to implement a new phone system for a customer call center. The business analyst will need to create a business case.

Which of the following components will the business analyst use as input to the business case?

Options:

A.

Project timeline

B.

Project scope

C.

Product scope

D.

Work breakdown structure

Question 48

The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.

Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

Options:

A.

Weighted matrix, process flow, and organizational chart

B.

Stakeholder register, decision tree, and capability matrix

C.

Traceability matrix, context diagrams, and scope document

D.

Decision trees, weighted matrix, and context diagrams

Question 49

When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?

Options:

A.

Stakeholder register

B.

RAC! matrix

C.

SWOT analysis

D.

Stakeholder management plan

Question 50

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Question 51

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

Options:

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Question 52

Which of the following would be the best practice in product validation?

Options:

A.

The measurement of the requirement should be based on the average of two or more evaluations.

B.

There should be two separate measurements for evaluating each functional requirement.

C.

Two or more testers should test the product using the same test cases so that their evaluations are consistent.

D.

The evaluation criteria should be the same as what was used to measure the requirement.

Question 53

For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?

Options:

A.

System analysis

B.

Dependency analysis

C.

Risk analysis

D.

Interface analysis

Question 54

What should the business analyst do during the first steps of a project?

Options:

A.

Identify stakeholders and their interests.

B.

Identify the classes of users and their requirements.

C.

Align the sponsor expectations along the project goals.

D.

Evaluate the sources for requirements and prioritize them.

Question 55

Which tool provides combined functionality for business analysis and quality assurance activities?

Options:

A.

Functional specification tool

B.

Requirements traceability tool

C.

System use case modeling tool

D.

Solution quality assurance tool

Question 56

Midway through the requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identify the requestor.

What should the business analyst have documented?

Options:

A.

Sponsor approval in the requirements traceability matrix

B.

The source in the RACI matrix

C.

Roles and responsibilities in the RACI matrix

D.

The source in the requirements traceability matrix

Question 57

A firm implements SharePoint and the business analyst creates the requirements to develop a business analysis repository. In the requirements, the analyst describes a detailed workflow that includes appropriate stakeholders receiving email notifications of certain

activities. The SharePoint team needs to know which activities should trigger the notification workflow.

Which workflow trigger should the business analyst incorporate?

Options:

A.

Any change to the requirements matrix

B.

Changes to test cases traced to requirements

C.

Change through project life cycle

D.

Changes to stakeholder memberships

Question 58

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

Options:

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Question 59

Several interviews with stakeholders to develop an inventory management system in a new architectural environment have revealed a significant concern about system and architectural stability. In which tool should the business analyst include this attribute to ensure that the requirement meets the acceptance criteria?

Options:

A.

Stakeholder satisfaction survey

B.

Interface analysis

C.

Process modeling

D.

Sectiead Traceability matrix

Page: 1 / 20
Total 199 questions