Weekend Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMI-PBA PMI Professional in Business Analysis Exam Practice Test

Page: 1 / 20
Total 200 questions

PMI Professional in Business Analysis Questions and Answers

Question 1

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

Options:

A.

Validate the requirements deemed important by the stakeholders.

B.

B. Obtain approval from engineering for partial testing of the requirements.

C.

Negotiate with the client to standardize the requirements.

D.

Assign a verification method to each requirement.

Question 2

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Options:

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Question 3

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

Options:

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Question 4

Which technique or tool is used to obtain acceptance of the delivered product?

Options:

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Question 5

Which of the following is a properly written requirement statement?

Options:

A.

The pot shall be lightweight and heat up quickly.

B.

The pot shall be usable in the oven or on the stove.

C.

The pot shall be manufactured in the following colors: yellow, red, brown, blue.

D.

The pot shall prominently display the company brand.

Question 6

Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

What could the business analyst have established to help manage this situation?

Options:

A.

Change control process

B.

Configuration management system

C.

Communication plan

D.

Sponsor signoff

Question 7

To reduce the amount of time and effort needed to create a product specification for a project, the business analyst plans to reuse:

Options:

A.

quantitative analysis.

B.

risk assessments.

C.

qualitative analysis.

D.

requirements.

Question 8

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.

Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?

Options:

A.

review with appropriate stakeholders

B.

A project management plan

C.

A risk plan

D.

A strategies and goals analysis

Question 9

Once the requirements are compared to internal and external quality standards, what should the business analyst do next?

Options:

A.

Set the priority of the requirements.

B.

Communicate the requirements to stakeholders.

C.

Ensure that the requirements are validated.

D.

Baseline the requirements.

Question 10

A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.

What would be the most viable technique to use in this scenario?

Options:

A.

A review of the solution prototype

B.

A brainstorming session

C.

A use-case development session

D.

A review of the previous version

Question 11

A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?

Options:

A.

Cost-benefit analysis

B.

Benchmarking

C.

Brainstorming

D.

Document analysis

Question 12

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Question 13

During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.

What should the business analyst have defined to avoid this?

Options:

A.

Communications approach in the business analysis plan

B.

Decision-making process in the project management plan

C.

Decision-making process in the business analysis plan

D.

Communications approach in the project management plan

Question 14

After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides

enough information to check if the requirement has been met.

Which of the following would work best in this case?

Options:

A.

User stories

B.

Functional specifications

C.

Flow chart

D.

Prototyping

Question 15

A business analyst is conducting a cost-benefit analysis of potential solution options. The stakeholders have indicated that the estimated growth rate is very important to them.

Which technique will allow the business analyst to determine this information?

Options:

A.

Payback period

B.

Net present value (NPV)

C.

Internal rate of return

D.

Return on investment (ROI)

Question 16

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

Options:

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Question 17

A business analyst has been asked to investigate a problem. This investigation will provide input towards developing a business case. The business analyst wants to first understand the company's current business processes.

Which technique should the business analyst use?

Options:

A.

Observation

B.

RAC! matrix

C.

MoSCoW

D.

User stories

Question 18

Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:

Options:

A.

the risk associated with the change is not evaluated.

B.

changes must still be documented and captured.

C.

a change control board should be established.

D.

changes can be applied without further managerial involvement.

Question 19

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

Options:

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Question 20

Which of the following is an example of a functional requirement?

Options:

A.

The system is able to require passwords.

B.

The system can be accessed from multiple locations.

C.

The system provides an user-friendly interface.

D.

The system can handle 3,000 user requests concurrently.

Question 21

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

Options:

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Question 22

A project that was going well for the last few months has encountered a situation—regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.

This could have been avoided if:

Options:

A.

the project team documented customer requests and obtained sign-off.

B.

a change control process for requirements and their statuses was followed.

C.

the project manager circulated the meeting minutes after the discussions with all the attendees.

D.

the customer met with regulatory authorities to verify that their requirements were also considered.

Question 23

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

Options:

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Question 24

Which tool provides combined functionality for business analysis and quality assurance activities?

Options:

A.

Functional specification tool

B.

Requirements traceability tool

C.

System use case modeling tool

D.

Solution quality assurance tool

Question 25

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

Options:

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Question 26

A company has launched a new online sales application and engaged a focus group to test how quickly the customer could place an order. The focus group also provided feedback on their satisfaction.

Which metrics tool should the business analyst use to record the results?

Options:

A.

Business completion

B.

Sales and marketing

C.

Customer

D.

Focus group

Question 27

A business analyst is working with the project manager, company auditors, and project stakeholders to determine whether formal signoff should be required for the project. For which reason would the business analyst recommend formal signoff to the group?

Options:

A.

The industry is unregulated.

B.

The project impact is contained within a small department of the company.

C.

Errors in the product could result in financial solvency.

D.

The organization follows an iterative project life cycle.

Question 28

A company is awarded a contract to design and build a custom product. The contract references a detailed technical specification. What is the best action to take to ensure the design meets customer requirements?

Options:

A.

Create a system requirements verification matrix to trace the design to the technical requirements and include verification methods.

B.

Conduct a one-on-one interview with each member of the technical team to ensure that they understand the customer's specification.

C.

Generate a design package for the product and ask the customer to verify that the design meets his or her technical needs.

D.

Develop a test plan to verify that the product meets the performance requirements in the technical specification.

Question 29

A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?

Options:

A.

Meet with the stakeholder and discuss timeline impact.

B.

Refer changes to the project manager.

C.

Define requirements baseline and implement a change control process.

D.

Implement only the original requirements.

Question 30

A project's requirements baseline is established and approved. A stakeholder then submits a new requirement through the change control process.

How can the business analyst determine the impact on existing requirements?

Options:

A.

Perform a stakeholder analysis.

B.

Review the requirements traceability matrix.

C.

Use time-boxing to defer the new requirement.

D.

Update the use case documentation.

Question 31

A business analyst has elicited, documented, and verified the requirements, discovering that there are not enough resources to deliver all the requirements. Which technique should the business analyst employ to rectify the issue?

Options:

A.

Hold a brainstorming workshop to build the rationale for the requirements.

B.

Perform traceability to find out where the requirements originated.

C.

Survey stakeholders on their likes and dislikes about the requirements.

D.

Ask stakeholders to vote on the requirements.

Question 32

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

Options:

A.

Brainstorming

B.

Interviewing

C.

Prototyping

D.

Surveying

Question 33

The business analysts have concluded a requirements elicitation workshop. They now need to define rationale for each requirement.

Which of the following pairs of items would be important to include in the rationale?

Options:

A.

Reasons and assumptions

B.

Product vision and operational relationships

C.

Stakeholder impact and design decisions

D.

Functional relationships and work breakdown structure code

Question 34

A project team delivers a solution based on the approved requirements and is confident that it meets the defined acceptance criteria.

What should the business analyst do to obtain signoff?

Options:

A.

Contact the sponsor.

B.

Contact the stakeholder who provided the majority of requirements in the traceability matrix.

C.

No signoff is necessary.

D.

Refer to the RACI matrix to identify who is responsible for signoff.

Question 35

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.

Which is a possible reason why the requirement was not implemented?

Options:

A.

The requirements management plan was not updated with the change.

B.

The scope management plan was not updated with the change.

C.

The requirements traceability matrix was not updated with the change.

D.

The schedule management plan was not updated with the change.

Question 36

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

Options:

A.

prepare a test procedure for the product to discuss at the requirements review.

B.

start designing the product to impress the customer with the amount of progress achieved early in the project.

C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.

D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.

Question 37

The best way to ensure the integrity of requirements is to:

Options:

A.

implement version control, maintain a history of requirements changes, and track the status of each requirement.

B.

use a requirements management tool, measure requirements volatility, and maintain a history of requirements changes.

C.

establish a change control board, track the status of each requirement, and use a requirements management tool.

D.

establish a requirements baseline, establish a change control board, and label each requirement uniquely.

Question 38

The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents. Which course of action should the business analyst take to minimize the risk of misunderstanding?

Options:

A.

Plan a peer review of the requirements specification.

B.

Ask the development teams for a formal acceptance of the requirements specification.

C.

Write a data dictionary that accompanies the requirements specification.

D.

Hold a workshop with the development teams to explain the details of the requirements specification.

Question 39

A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.

Which model should the team employ to ensure the most effective representation of analysis boundary?

Options:

A.

Data flow diagram

B.

Context diagram

C.

State diagram

D.

Entity relationship diagram

Question 40

A business analyst is discussing the acceptance criteria for a new measurement system with the operations manager. The operations manager is particularly concerned about the accuracy of the new system because mistakes in data measurements could be extremely costly to fix.

Which of the following is the best strategy to define the appropriate acceptance criteria?

Options:

A.

Quantify the risks associated with the measurement errors and update the risk register.

B.

Ask the operations manager to formally accept the requirements documents.

C.

Plan a training session for the new system before it is handed over to the operations manager.

D.

Clearly define the maximum acceptable error rate for the new system.

Question 41

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.

Who should the business analyst contact to review the testing results and get approval to proceed with deployment?

Options:

A.

The tester identified in the testing strategy

B.

The person identified in the RACI matrix

C.

The project manager identified in the project charter

D.

The project sponsor identified in the scope document

Question 42

A key component of the business analyst's role during acceptance testing is to:

Options:

A.

execute all acceptance tests on behalf of the user community.

B.

delegate execution of acceptance testing and defect identification to users.

C.

act as a resource only when users encounter difficulties while performing tests.

D.

assist the quality assurance department by defining acceptance criteria.

Question 43

A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

Options:

A.

Distribution of project changes

B.

Requirements status during the project development cycle

C.

Number of requirements approved vs. number of requirements rejected

D.

Number of requirements tested and approved

Question 44

The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.

Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid

recommendation?

Options:

A.

Gap

B.

Risk

C.

Cost-benefit

D.

SWOT

Question 45

The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?

Options:

A.

Majority

B.

Plurality

C.

Consensus

D.

Unanimity

Question 46

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

Options:

A.

Prototyping

B.

Surveys

C.

Document analysis

D.

Decision tree

Question 47

The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan, yet the client does not agree that it meets the specification.

What could have caused this?

Options:

A.

The product was not adequately tested in accordance with the test plan.

B.

The requirements matrix did not adequately track back to client requirements.

C.

Requirement changes were not properly identified in the project charter.

D.

The product design was not properly reviewed by the quality department.

Question 48

The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.

Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

Options:

A.

Weighted matrix, process flow, and organizational chart

B.

Stakeholder register, decision tree, and capability matrix

C.

Traceability matrix, context diagrams, and scope document

D.

Decision trees, weighted matrix, and context diagrams

Question 49

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

Options:

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Question 50

A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?

Options:

A.

Storyboard

B.

Project charter

C.

Business case

D.

Survey

Question 51

A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.

What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will

need to have a discussion about the budget?

Options:

A.

Selected project life cycle

B.

Business analysis deliverables to be produced

C.

Type of elicitation activities to be conducted

D.

Decision on the type of models to be used

Question 52

A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.

The business analyst tells the stakeholder that the requirement status was changed to "deferred ”

What could have prevented the stakeholder from being surprised about the status change?

Options:

A.

The status should have been communicated to the requirement’s source.

B.

The status should have been reviewed prior to project launch.

C.

The status should have been communicated to all project stakeholders.

D.

The status should have been updated in the traceability matrix.

Question 53

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

Options:

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Question 54

The business analyst has been assigned to a project involving a low number of stakeholders. Which technique should be used to elicit requirements?

Options:

A.

Survey

B.

Interview

C.

Document analysis

D.

Interface analysis

Question 55

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

Options:

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Question 56

Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

Options:

A.

PEST analysis

B.

B. Force-field analysis

C.

Feasibility analysis

D.

Gap analysis

Question 57

What are some of the components of a requirements management plan?

Options:

A.

Requirements definition, functional and non-functional requirements, and decision-making process

B.

Requirements work plan, requirements definition, and traceability matrix template

C.

Requirements work plan, prioritization process, and traceability matrix template

D.

Requirements definition, requirements attribute template, and traceability matrix template

Question 58

Which tool is the most appropriate to aid in development of measurable and actionable requirements for a new project?

Options:

A.

Network diagram

B.

Use case diagram

C.

Entity relationship diagram

D.

Activity-on-node diagram

Question 59

How can a SWOT analysis help when deciding between several possible options to address a business problem?

Options:

A.

It can help the product owner to determine opportunity cost of not choosing an option.

B.

It can help the stakeholders to determine how to avoid the threats of each option.

C.

It can help the project sponsor to determine the valuation of each option.

D.

It can help the stakeholders identify the strengths and weaknesses of each option.

Question 60

A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?

Options:

A.

Multivoting

B.

MoSCoW

C.

Time-boxing

D.

Budget analysis

Page: 1 / 20
Total 200 questions