Labour Day Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Exam Practice Test

Page: 1 / 21
Total 208 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 1

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables: however, issues arise when the deliverables are integrated. What should the agile practitioner do?

Options:

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

Question 2

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value C. Recommend cancelling the current iteration and plan the change request into the next iteration.

C.

Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Question 3

What can a team use to prioritize stories?

Options:

A.

MoSCoW method

B.

Planning poker technique

C.

Weighted average calculation

D.

INVEST scale

Question 4

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

Options:

A.

Invited end customers to attend the stand ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Question 5

During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

Options:

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can. and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Question 6

A product owner obtains customer confirmation on product requirements and provides them to the team. After explaining the user stories, the product owner receives agreement for acceptance from the team. What should the team do next?

Options:

A.

Use agile estimation techniques to create a shared understanding of when the user stories will be completed.

B.

Agree upon development and testing activities for the user stories.

C.

Complete the user stories, and provide a demo for the product owner and customer.

D.

Complete the user stories, and hold a retrospective to discuss them.

Question 7

An agile project manager notices that the product owner manages team members' day-to-day tasks in a way that distracts them from their core responsibilities. In addition, the team believes that their questions on product backlog prioritization are not being answered on time.

What should the agile project manager do?

Options:

A.

Discuss and address this in the iteration retrospective.

B.

Let the product owner know it is the project manager's responsibility to drive a team's tasks.

C.

Discuss the roles and responsibilities of the project team with the product owner

D.

Ask the product owner to work extra hours to answer the team's questions

Question 8

During a retrospective the agile practitioner discovers that a team member's process improvement idea has worsened the outcome What should the agile practitioner do?

Options:

A.

Commend the team on trying the idea, then encourage discussion regarding alternatives.

B.

Ask a manager to direct the team on fixing the process

C.

Encourage the team to continue executing the idea to see if it improves

D.

Privately speak with the team member to convey that their idea worsened the outcome

Question 9

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

Options:

A.

It ensures a consistent level of detail is available in the project schedule

B.

It prevents a wasteful buildup of requirements inventory that may never be processed

C.

It provides a concrete definition of project scope, cost and duration

D.

It allows the team to lock down the stories to be included in a release

Question 10

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.

What should the agile coach do?

Options:

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Question 11

Question # 11

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Question 12

The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status and a demo of all the stories to the business. What should the product owner have done differently?

Options:

A.

Demonstrated only the completed stories and seek stakeholder feedback

B.

Presented the budget situation and review the cost variance

C.

Reviewed the test results to gam confidence from the stakeholders

D.

Presented a demo of all the stones including the work in progress stories

Question 13

A team is creating a highly marketed, time-sensitive product. The agile coach is concerned that anything other than exceptional quality will result in bad publicity for the company. What should the agile coach ensure that developers do?

Options:

A.

Establish pair programming partners, and regularly perform peer reviews.

B.

Perform demos at the end of each iteration.

C.

Send coding to the quality assurance (QA) team upon completion.

D.

Demonstrate each feature to the client as soon as coding is complete.

Question 14

A team member is stressed due to a heavy workload, while other team members have some slack in their schedules How should the team lead address this?

Options:

A.

Inform management and suggest that additional resources may be required

B.

Discuss the issue with the team in the daily stand up meetings

C.

Meet personally with the stressed team member to brainstorm ways to better manage their time

D.

Begin tracking the stressed team member's tasks in a separate backlog for additional analysis and reporting

Question 15

A product owner new to the role is very enthusiastic about an agile project with an energetic team What should be done first to ensure successful delivery of the product?

Options:

A.

Hold a meeting with the team and the product owner to develop the team charter working agreement, guiding principles and product vision

B.

Ask the product owner to create the project vision and charter, and then discuss the guiding principles with the team

C.

Hold a meeting during which the team can present the project charter high-level project plan, and team values to the product owner

D.

Send the product owner to formal product-owner training where the product owner can learn how to create a product vision

Question 16

An agile practitioner wants to communicate the effect of technical debt on the project What should the practitioner do?

Options:

A.

Post and discuss rises in the burn down chart

B.

Adjust story points to account for technical debt

C.

Log technical debt as an impediment

D.

Add refactoring tasks to all stories

Question 17

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

Question 18

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

Options:

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Question 19

Midway through a project the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project

What should the product owner do next?

Options:

A.

Obtain approval from the change control board to discontinue the component

B.

Ask the team to continue developing the component

C.

Ask the team to discontinue developing the component

D.

Request the sponsor's formal approval to discontinue the component

Question 20

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options:

A.

Ask the project manager to work with the product owner to help generate clearer stories in the future.

B.

Develop guidelines to prevent future occurrences.

C.

During the retrospective, discuss the issue and create an action plan to avoid it in the future.

D.

Allow the team to devise a corrective action without external intervention.

Question 21

An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?

Options:

A.

Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Question 22

An agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.

What should the agile team do?

Options:

A.

Demand frequent product reviews by the product owner

B.

Continuously work with the product owner to do backlog refinement and product reviews

C.

Have the product owner provide detailed requirement specifications to ensure the proper features are delivered

D.

During the planning session, ensure the team is committed to deliver within the specifications

Question 23

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Question 24

During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team to do?

Options:

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story's technical approach.

C.

Transfer the story to a scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story's priority and wait until more technical details are available.

Question 25

The agile team disagrees with the business stakeholders on completing some epics What could help eliminate misunderstandings?

Options:

A.

Agree on requirements with all stakeholders

B.

Begin planning every four iterations

C.

Consider previous sprint demo feedback when planning the next sprint

D.

Include the reasons for the project in the contract

Question 26

During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?

Options:

A.

Positively acknowledge the list and share it with management

B.

Immediately have the team implement the initiatives

C.

Help the team choose one or two initiatives for immediate implementation

D.

Ask the team to choose and implement the most complex initiative

Question 27

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope the team plans to work only on spike user stories for the next three sprints

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints.

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after all

spikes are executed

Question 28

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design and delivery plans.

What should the agile practitioner do?

Options:

A.

Provide all information requested by the stakeholder

B.

Set expectations regarding the appropriate level of details requested during this stage

C.

Inform the stakeholder that no detailed documents are provided using agile practices

D.

Ask the team to supply the information to the stakeholder

Question 29

During a daily stand up, the tester engages the developer in a discussion about what will be tested during unit testing versus regression testing. What should the scrum master do?

Options:

A.

Ask the tester and developer to discuss it after the meeting, since it is not a part of the daily stand up.

B.

Encourage the discussion to resolve impediments.

C.

After the meeting, escalate this issue to the tester's supervisor to ensure that this does not reoccur.

D.

Ask more questions about the testing techniques to obtain clarification on team efforts for quality improvements.

Question 30

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

Options:

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

Question 31

A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface. What should the team have done to improve retrospective outcomes?

Options:

A.

Invited subject matter experts (SMEs)

B.

Conducted problem detection to determine root causes

C.

Measured and reported the outcome of improvement actions to the team

D.

Kept track of all current issues in a log. and then reviewed their progress at the end of every iteration

Question 32

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options:

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Page: 1 / 21
Total 208 questions