Weekend Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Exam Practice Test

Page: 1 / 48
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 1

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options:

A.

Ask the project manager to work with the product owner to help generate clearer stories in the future.

B.

Develop guidelines to prevent future occurrences.

C.

During the retrospective, discuss the issue and create an action plan to avoid it in the future.

D.

Allow the team to devise a corrective action without external intervention.

Question 2

Members of an agile team are complaining that user stories are too large, taking multiple sprints to complete them. They say this way of working is becoming difficult to handle and it has been challenging to map relationships between stories. This situation is affecting the value delivery for the product owner.

What should the scrum master do to handle this situation?

Options:

A.

Separate large user stories.

B.

Apply work-in-progress limits.

C.

Organize user stories into epics.

D.

Replace user stories into features.

Question 3

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.

Question 4

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Question 5

During a retrospective the agile practitioner discovers that a team member's process improvement idea has worsened the outcome What should the agile practitioner do?

Options:

A.

Commend the team on trying the idea, then encourage discussion regarding alternatives.

B.

Ask a manager to direct the team on fixing the process

C.

Encourage the team to continue executing the idea to see if it improves

D.

Privately speak with the team member to convey that their idea worsened the outcome

Question 6

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes detailed design plan

D.

Product vision, business objectives, timeframes

Question 7

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen. What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Question 8

The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team's velocity drops.

Question 9

A project manager is leading a large agile project with multiple deliverables at each phase of completion. The project team has informed the project manager that the deliverables are completed per the team agreement.

Which agile practice should the project manager advise their team use to ensure deliverables are completed and ready for release?

Options:

A.

Requirements backlog and ready for release

B.

Acceptance criteria and release

C.

Definition of ready (DoR) and review

D.

Definition of done (DoD) and demonstrate

Question 10

A company president is concerned about the impact of a natural disaster on the company. How should management identify areas to apply its resources and mitigate potential impacts?

Options:

A.

Establish and keep an active risk register that includes mitigation strategies and a cost-benefit analysis.

B.

Establish and keep an active risk register based on qualitative risk analysis and expected losses.

C.

Have each development team post the highest risk development items on the information radiator.

D.

Avoid risk by splitting development teams into two locations to ensure knowledge continuity.

Question 11

Why is stakeholder engagement important for project success?

Options:

A.

To participate in establishing a shared vision as a member of the team

B.

To provide the acceptance criteria for the delivered items

C.

To propose implementation methods to the development team

D.

To evaluate the performance of the development team

Question 12

An agile leader notices that a team member is becoming very quiet and disengaged in meetings. What should the agile leader do to identify team members' personalities and motivators?

Options:

A.

Use the DISC framework with each team member.

B.

Use MoSCoW ratings to keep people engaged.

C.

Hire a SAFe coach to provide encouragement.0 Employ BDUF to help with providing structure to meetings

Question 13

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team's productivity.

How should the team leader exhibit servant leadership?

Options:

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments

Question 14

An agile lead is working on a project to build a new product that will bring substantial business value to a company. Company executives want to present the first release at an important industry fair the following month. The agile lead started the project the previous month, and the team planned the release to take 8 iterations. For the past 4 iterations, work has been performed as planned and on time. In the current iteration, however, one team member will be out for the remainder of the project. Without this team member, velocity would drop 30%.

What should the agile lead do to ensure the release will be on time for the fair?

Options:

A.

Reduce the scope of the release to meet the deadline.

B.

Deliver as many features as possible based on the new velocity.

C.

Extend the project timeline to accommodate the missing team member.

D.

Hire a new team member to replace the missing one.

Question 15

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities. How should the stakeholders ensure their objectives are met by product delivery?

Options:

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

Question 16

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate USS40.000 more than expected for the quarter. What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Question 17

For what is the MoSCoW method used?

Options:

A.

Estimating story size

B.

Prioritizing stories

C.

Validating a product

D.

Tracking progress

Question 18

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this.

What should the team do next?

Options:

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Question 19

All blockers are caused by some Impediments, but not all impediments are blockers. Which two scenarios should be considered blockers? (Choose two.)

Options:

A.

Due to frequent context switching, the daily 15-minute touchpoints last an hour even/ day, reducing the team's time to finish activities for the demonstrations.

B.

A developer is unable to work on their tasks within an iteration, because senior management is constantly pulling them into production incident analyses.

C.

The development team needed to urgently set up all the test data the previous week; however, due to a glitch in the system this will not be available until before the demonstration.

D.

The offshore testing team is pulled away at the last minute from a high-profile initiative and testing cannot be resumed until a new testing team is assigned.

E.

Performance issues in the testing environment, leading to a 2-day delay in implementing the code.

F.

The team has started working on the iteration, but the requirements artifacts are under review by the product owner.

Question 20

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during the meetings. What should the project lead do to encourage the team to express themselves?

Options:

A.

Organize separate meetings with each individual team member.

B.

Create a safe environment for discussions during meetings.C Emphasize rules that need to be respected during meetings

C.

Allow team members to talk when they feel comfortable without any pressure.

Question 21

During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team to do?

Options:

A.

Implement the story since the team is running behind schedule.

B.

Create a spike to finalize the story's technical approach.

C.

Transfer the story to a scrum team experienced in solving similar problems.

D.

Ask the product owner to reduce the story's priority and wait until more technical details are available.

Question 22

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the scrum master do?

Options:

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Question 23

A product owner obtains customer confirmation on product requirements and provides them to the team. After explaining the user stories, the product owner receives agreement for acceptance from the team. What should the team do next?

Options:

A.

Use agile estimation techniques to create a shared understanding of when the user stories will be completed.

B.

Agree upon development and testing activities for the user stories.

C.

Complete the user stories, and provide a demo for the product owner and customer.

D.

Complete the user stories, and hold a retrospective to discuss them.

Question 24

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered. What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team's estimated velocity.

Question 25

A newly formed scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments Emphasis is placed on how issues are resolved and the strategies for preventing them in the future Over time what will be the result of this approach?

Options:

A.

Kaizen

B.

Specific measurable, assignable, realistic and time-based (SMART) goals

C.

Key performance indicators (KPIs)

D.

Muda

Question 26

More details for a story are required before the upcoming sprint planning meeting What should the scrum master do?

Options:

A.

Email the product owner requesting detailed story specifications and wait for a response

B.

Gather the details from the team members before sprint planning

C.

Schedule a story grooming session with the product owner before sprint planning

D.

Conduct a planning poker session with the team

Question 27

While reviewing the sprint burn down during a stand up. The scrum team identifies that they have fallen behind Upon further discussion they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.

What should the scrum team do?

Options:

A.

For upcoming sprints, have QA team members ensure that their respective skill sets are considered when acceptingstones

B.

Have QA team members with the appropriate skill sets spend extra time to help the team succeed

C.

Ensure that QA team members who lack the appropriate skill sets sign up for training within the next few weeks

D.

Ask QA team members experienced with the new automation framework to cross-train the other QA members

Question 28

A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20 percent increase from previous iterations in the number of reported defects and change requests.

Since this is causing the product's value to decrease, what should the team do?

Options:

A.

Reevaluate the duration of the cycles, as faster cycles may allow for earlier detection of defects.

B.

Run a sprint to clear all reported defects before taking new stories.

C.

Change the control mechanism so that items are better tested before delivery.

D.

Increase the opportunities to confirm common understanding with the client.

Question 29

A global organization is migrating its IT infrastructure from traditional, physical assets to cloud-based assets. Agile concepts are new to the organization because it currently uses a predictive approach.

What should an agile coach do to facilitate a culture change to an agile approach?

Options:

A.

Develop and distribute a high-level summary of how agile offers greater benefit than predictive to mid-level managers and let them decide if it should be distributed to lower-level workers.

B.

Develop and distribute a high-level summary of competing vendors' product alignment and agile project execution to the product owner for approval.

C.

Develop and distribute a high-level summary of how agile offers greater benefits than predictive to all members of organization.

D.

Develop and distribute a high-level summary of how agile offers greater benefits than predictive to the organization's executive directors, and if executive directors agree with the summary, distribute it organization-wide.

Question 30

During the project initiation stage, a team has estimated story points for all user stories. When the project team explained the minimum marketable feature (MMF), however, they were not confident that the solution would actually work.

What can the team do to better manage this situation?

Options:

A.

Deliver the minimum marketable feature (MMF) to customers for feedback.

B.

Write acceptance criteria for each business requirement to conduct proper testing.

C.

Develop test cases based on user stories.

D.

Ask the customer to provide acceptance criteria before developing the user stories.

Question 31

The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.

What should the junior team member do?

Options:

A.

Speak to the agile lead about the concerns.

B.

Follow the agile lead's instructions.

C.

Increase the time worked to meet objectives.

D.

Speak to all team members about the concerns.

Question 32

In an adaptive environment, project managers use their skills and expertise to help the team adapt to changing circumstances and deliver to their stakeholders. While some agile practitioners may argue that the role of a project manager is not needed in self-organizing teams, pragmatic agile practitioners and organizations recognize that project managers can add benefit in many situations. The key difference is that their roles and responsibilities may look somewhat different in an adaptive environment.

What are some of the practices a project manager can bring to an adaptive environment?

Options:

A.

Building a collaborative decision-making environment with key stakeholders, teams, and sponsors.

B.

Ownership of detailed project planning, user histories, retrospectives, showcases and metrics board

C.

Ensuring agile values and principles are adopted by all teams involved in delivery of the project.

D.

Developing the project charter, writing the project plan, and following the achievement of all milestones.

Question 33

A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing it's teams.

What strategy should be employed to re-organize the teams?

Options:

A.

All the teams from both products should be simultaneously called together and allowed to completely self-manage

B.

Teams that worked on similar components in the separate products should be combined to minimize disruption andcapitalize on synergies

C.

After grouping individuals by role multi-discipline teams should be created that are comprised of one member from eachrole

D.

Features should be prioritized and then teams should be organized around those priorities

Question 34

Question # 34

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

Options:

A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.

Increase the commitment to 48 story points to push the team toward higher performance.

D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.

Question 35

During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework.

To help the team gain confidence, what should the agile practitioner suggest?

Options:

A.

Develop a spike

B.

Create an Ishikawa diagram

C.

Perform a pre-mortem analysis.

D.

Complete a variance and trend analysis

Question 36

A team developing application software is working in pairs. A project manager notices that important information is sometimes not shared among team members, leading to delays in the development process.

What should the project manager do to improve team performance and eliminate any communication impediments?

A For new pairs of developers based on the years of expertise and project management Knowledge

B. Use task boards so the team can keep track of the work done and future implementation planning.

C. Schedule in-person meetings at the end of each iteration, allowing team members to share knowledge and experience.

D. Seek expert judgment and a new collaboration model that will strengthen team cohesiveness.

Options:

Question 37

An agile project manager is leading an international project involving a global team consisting of members from very different cultures, countries, and time zones. The agile project manager is aware that similar projects with distributed teams have led to serious conflicts.

What should the agile project manager do to promote trust and collaboration?

A Talk with the human resources (HR) department to select team members with similar backgrounds to eliminate conflict

B. Collocate for team building to promote collaboration to build trust and improve communication.

C. Promote a project charter with the project vision and purpose to help align the team.

D Promote a team charter with a set of norms rules and agreements to facilitate the work

Options:

Question 38

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Question 39

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure

B.

Description of all features' functions and an estimate of their cost

C.

Priority list of desired features and functions

D.

Comprehensive schedule of immediate deliverables

Question 40

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.

What can an agile practitioner conclude about team A and team B's estimates?

Options:

A.

Team B has underestimated scope compared to team A.

B.

Team A is more confident in delivering velocity than team B.

C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.

Both teams have estimated the project to be of same size.

Question 41

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Question 42

What should a product owner do when a new stakeholder is complaining that they are not receiving the relevant financial data regarding the project.

Options:

A.

Work with the scrum master to give the stakeholder access to the related information radiator

B.

Invite the stakeholder to the next sprint planning session so they can ask questions of the team

C.

Ask the team to prepare the requested data in the next iteration

D.

Direct the stakeholder to the project team so they can provide more data

Question 43

An agile team notices that the same problems continue to occur during multiple iterations Several team members have suggestions to fix the problem.

What is the proper agile approach to handle this?

Options:

A.

Hold frequent retrospectives and share the responsibility for making changes

B.

Understand that this is the nature of innovative business and strive to work harder

C.

Collect team member feedback and discuss them privately with the product owner

D.

Conduct a team-building exercise to increase trust among the team members

Question 44

A product owner concludes that the majority of a project's value can be delivered by completing only the first half of the prioritized backlog. What should the product owner do next?

Options:

A.

Remove the second half of the backlog, and communicate their decision in the next backlog grooming meeting

B.

Reprioritize backlog items to future iterations

C.

Work with the team to deploy the first half of the backlog to ensure that value is realized

D.

Meet with project stakeholders to review the backlog and determine if the scope should be adjusted

Question 45

An agile project manager observes that the Scrum team is falling behind on the completion of a particular sprint. What should the agile project manager do?

Options:

A.

Facilitate by providing directions to the team about how they can get back on track.

B.

Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.

C.

Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.

D.

Understand the impediments and facilitate issue resolution to enable the team to succeed.

Question 46

How can a project team effectively work toward a common goal and communicate as they scale and expand to build a new business-critical platform, given that they have been responsible for a small customer-facing product with little complexity over the past 2 years?

Options:

A.

Daily coordination meeting

B.

Instant messaging tools

C.

Web conferencing

D.

Work collaboration platform

Question 47

An agile practitioner becomes a Scrum Master on an established Scrum team. After introductions, what should the agile practitioner do?

Options:

A.

Coach team members to improve functional specialties and increase overall velocity.

B.

Identify where team processes misalign with accepted Scrum practices.

C.

Facilitate the identification of problems or issues and help the team resolve them.

D.

Review the backlog to ensure that it is prioritized, refined, and properly tasked.

Question 48

A team member does not understand what the project risks are or the impact that they could have. How should an agile leader communicate risks in a way that the team will understand?

Options:

A.

Create a RAG chart (responsible, accountable, consulted, informed) that identifies who is accountable for each risk.

B.

Create a Gantt chart that includes slack to accommodate for unknowns.

C.

Create a communications management plan that details who is responsible for communicating risks.

D.

Create a risk burndown chart showing the reduction of risks overtime.

Question 49

A project is starting and the type of work is complex and suitable for agile in assessing the team members, it appears that co-location would be a challenge.

What should the agile practitioner do?

Options:

A.

Select and implement collaboration tools to augment team interactions

B.

Provide each geographical area with their own product owner and divide the work between the teams

C.

Increase the number of requirements documents and ensure they are clearly communicated

D.

After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Question 50

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

Options:

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Question 51

During mid-sprint changes, an agile facilitator meets with the executive and development teams. During the meeting, executive team members resolve conflicts, and on their own initiative, review the iteration charts to discuss changes to the iteration's functional goal.

What practice is the agile facilitator implementing?

Options:

A.

Building openness and transparency on the project's health and status

B.

Facilitating conflict resolution among executive team members

C.

Using active stakeholder involvement to build features in an incremental and iterative approach

D.

Seeking continuous feedback from executive team members

Question 52

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

Options:

A.

High-risk and high-value

B.

High-risk and low-value

C.

Low-risk and low-value

D.

Low-risk and high-value

Question 53

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?

Options:

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

Question 54

An agile team is working on a new product and is behind with their deliverables for the quarterly release. The team discovers new issues during each iteration. They start working on the critical issues and sometimes forget to update the backlog. This leads to confusion, delays, and occasional rework.

How should the agile practitioner improve the team’s productivity?

Options:

A.

Work with the team to ensure that both the product and iteration backlogs are up to date.

B.

Work with the team to ensure that the release backlog is in sync with the product backlog.

C.

Work with the team to ensure that the iteration and release backlogs are kept up to date.

D.

Work with the team to ensure that the product backlog is always kept up to date.

Question 55

During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach What should the scrum master do?

Options:

A.

Discourage the team member from deviating from the plan and document the request during the retrospective

B.

Encourage the team member to research the issue and present the findings during the retrospective

C.

Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases

D.

Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important.

Question 56

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.

What should the agile coach do?

Options:

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Question 57

An organization wants to increase value delivery in its agile projects. What should the agile teams do?

Options:

A.

Perform analysis and development work, but no testing because that should be managed by another specialized team.

B.

Master available technology and tools to provide informative dashboards to the stakeholders.

C.

Work with product owners and turn product backlog items into potentially shippable product increments.

D.

Complete projects by their deadlines and share the budgets upfront with project sponsors.

Question 58

How can an agile project manager ensure that all stakeholders have a clear understanding of the release plan by the end of a release planning meeting? (Choose two.)

Options:

A.

Stated understanding of the release goal

B.

Complete vision of the end product

C.

Timeline of the project

D.

List of the user stories that will be part of the next releases

E.

Complete roadmap of the next iterations

Question 59

Early in a project stakeholder analysis is performed: however, an organizational restructure redefines key roles What should the project team do?

Options:

A.

Note the changes to the restructure and roles that affect team activities

B.

Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements.

C.

Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project

D.

Obtain a copy of the redefined key roles to update the stakeholder analysis

Question 60

A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope What should the scrum master do?

Options:

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

Question 61

An agile team is preparing a release plan for a project. What information will the team need to complete this plan?

Options:

A.

Amount of work needed to complete a single user story

B.

Amount of work that can be accomplished by each team member

C.

Amount of work that can be accomplished in an iteration

D.

Amount of work that can be accomplished by the entire team

Question 62

The product owner is very concerned about work not being completed and tested before a hard release date. What can the agile team do to mitigate this risk?

Options:

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Question 63

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release. What should the team do?

Options:

A.

Conduct frequent demos and obtain feedback from users throughout the development of the next release

B.

Inform senior management that since the product was successfully released, the project is considered delivered and should be closed

C.

Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity

D.

Implement a better definition of done to ensure that continuous integration processes are managed effectively

Question 64

An agile team is working well together, but productivity has been flat. What can the project leader do to help them improve performance?

Options:

A.

Review the burndown chart to identify ways to increase efficiency.

B.

Chair a weekly team retrospective focusing on identifying areas for continuous improvement.

C.

Ask a senior manager to initiate a root-cause analysis.

D.

Identify team key performance indicators (KPIs) and create positive incentives when targets are achieved.

Question 65

A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?

Options:

A.

Assign agile roles within the team and conduct training for each role to provide understanding of the agile methodology.

B.

Organize training and development workshops to help all stakeholders to form a shared understanding of agile practices.

C.

Plan a transformation to agile delivery methods for senior leadership before starting project implementation.

D.

Apply only agile methods and practices for specific deliverables of the work and assign this work to experienced agile team members.

Question 66

During a retrospective meeting, a team develops a large list of initiatives All will have a positive impact and improve team performance What should the agile coach do next?

Options:

A.

Positively acknowledge the list and share it with management

B.

Immediately have the team implement the initiatives

C.

Help the team choose one or two initiatives for immediate implementation

D.

Ask the team to choose and implement the most complex initiative

Question 67

After seeing the planned features (or an upcoming release, a customer notes that a vitally important and complex one is missing. The team estimates that this feature significantly exceeds its average velocity. How can this issue be resolved?

Options:

A.

Break down the feature into smaller parts, and commit to completing the minimum viable product.

B.

Complete the iteration to which they have already committed, and include the feature in the next release.

C.

Change the planned features lo include only the vitally important one.

D.

Extend the iteration to complete the feature.

Question 68

An executive notices a kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?

Options:

A.

Cover up the kanban board every time the project team is not actively updating it.

B.

Demonstrate how the kanban board is necessary for assiqninq proper ownership for the work that has been done.

C.

Explain that the kanban board enables the team to complete the work and increases transparency on work that is not done.

D.

Remove the kanban board immediately and place it in a location where it is not visible.

Question 69

An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and reviewed the user stories related it.

What should the agile team do next?

Options:

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Question 70

During the advanced stages of implementing a complex design, an agile practitioner realizes that the architecture is not scalable for user requirements. The architect suggests a workaround that is minimally adequate but may cause some performance issues.

What should the agile practitioner do?

Options:

A.

Tell the team that this is unacceptable for the upcoming project.

B.

Implement the workaround since performance issues can be addressed in the next iteration.

C.

Calculate the cost of redoing the architecture and seek management approval.

D.

Brainstorm with the team to identify a solution.

Question 71

Question # 71

A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).

How many sprints will be needed to complete the entire backlog?

Options:

A.

15

B.

16

C.

17

D.

18

Question 72

Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?

Options:

A.

Understand the physical and virtual communication needs of the team and plan agile events based on the majority of the team members' needs.

B.

Escalate with senior management and ensure that everyone on the project team is physically colocated for all planned agile events.

C.

Invest in technology-collaboration tools to enable effective communication and ensure a common understanding of the scope, issues, and solutions.

D.

Recognize the different communication styles of the stakeholders and take a vote on the best approach that will work for the team.

Question 73

An agile team provides feedback that user stories include insufficient details to understand the requirements. What should the agile practitioner do?

Options:

A.

Coach the product owner to update only the acceptance criteria.

B.

Instruct the agile team to fix the user stories during the next retrospective.

C.

Facilitate a user story workshop with the agile team.

D.

Inform the product owner's manager that the work items provide insufficient detail.

Question 74

A product owner adds user stories to the backlog on a daily basis. The stories are vague requests, and the product owner expects the details to be clarified once the team works on the prioritization list.

How should the team members address this challenge so that the prioritization meeting does not become a brainstorming session?

Options:

A.

Ask the product owners to invite a subject matter expert (SME) to the meeting so the prioritization meeting will be more effective.

B.

Ask the product owner to review their items with the product owner's teammates before adding user stories to the backlog.

C.

Ask the product owner to schedule a meeting with a subject matter expert (SME) to review items before adding user stories to the backlog.

D.

Ask the product owner to review the stories with the scrum master before the prioritization meeting takes place.

Question 75

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

Options:

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

Question 76

A new project starts and team members are pooled together to execute it. The team works together and moves from the forming stage into the storming stage. However, potentially destructive conflicts are now arising.

What should the agile coach do to develop members into a high-performance team?

Options:

A.

Teach the team how to work comfortably in chaos.

B.

Provide strong facilitation and conflict-resolution guidance.

C.

Allow the team to resolve issues on their own.

D.

Observe each team member and advise them on team relationships.

Question 77

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.

What should the product owner do to resolve this?

Options:

A.

Ask the development team to address the issue since it is in their domain.

B.

Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.

C.

Meet with the team and stakeholders to address rework and rewrite stories as needed.

D.

Cancel the current sprint, and meet with stakeholders to reassess the project's validity.

Question 78

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Question 79

An agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.

What should the agile team do?

Options:

A.

Demand frequent product reviews by the product owner

B.

Continuously work with the product owner to do backlog refinement and product reviews

C.

Have the product owner provide detailed requirement specifications to ensure the proper features are delivered

D.

During the planning session, ensure the team is committed to deliver within the specifications

Question 80

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Question 81

On an agile project, some of the development team is struggling to understand how the tasks and user stones fit into the overall product. How should this be addressed?

Options:

A.

Review the iteration goals and have the team each describe the work to create shared understanding

B.

Create a story map for the minimal viable product (MVP) functionality

C.

Capture this as a task in the retrospective and ensure there is more detail provided at the next planning session

D.

Have the product owner explain the product vision and review the release plan with the team

Question 82

HOTSPOT

Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). Organizations need to realize that the major financial gains from agile project management will result from the practice of what? (Select answer from dropdown)

Question # 82

Options:

Question 83

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

Options:

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Question 84

A newly formed team is struggling to work together and agree on how to complete tasks in the upcoming sprint. What should the scrum master do to support the team?

Options:

A.

Resolve the disagreement for the team as a servant leader.

B.

Encourage the team to continue trying to resolve their disagreements.

C.

Advise the team on the correct course of action to avoid disagreements.

D.

Remove the team members that are in disagreement to ensure unity in the team.

Question 85

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

Options:

A.

Value stream mapping

B.

Long-term Lean planning

C.

Business process modeling

D.

Planning poker

Question 86

An agile team is planning the next iteration for a product release that has accumulated technical debt What should the team do?

Options:

A.

Add code cleanup activities to the product backlog and request prioritization by the product owner

B.

Add code cleanup activities to the next iteration and request clarification from the product owner

C.

Add code cleanup activities to the next iteration and ask the product owner to end the current iteration

D.

Add code cleanup activities to the next release backlog and request documentation from the product owner

Question 87

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?

Options:

A.

Capture risks and make them visible, and use a burn down chart to focus on reducing risks early in the project.

B.

Ask the scrum master to extend the sprint's duration to allow more time to work through technical issues.

C.

Place the impacted stories on the story board, and use daily stand ups to make the product owner aware of the technical issues.

D.

Seek guidance from the development manager

Question 88

An agile team has been given a complex project with a basic set of requirements which need further elaboration and review. How should the team iteratively build out the backlog of requirements with the stakeholders?

Options:

A.

Conduct a requirements gathering workshop.

B.

Deliver the basic requirements iteratively.

C.

Have the product owner fill out the requirements backlog.

D.

Have the stakeholders fill out the backlog before starling the project.

Question 89

The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status and a demo of all the stories to the business. What should the product owner have done differently?

Options:

A.

Demonstrated only the completed stories and seek stakeholder feedback

B.

Presented the budget situation and review the cost variance

C.

Reviewed the test results to gam confidence from the stakeholders

D.

Presented a demo of all the stones including the work in progress stories

Question 90

Team A is working on the second sprint of a product release Team B which is an interdependent team located on the same floor, requires extensive and frequent information to complete its sprint goal.

What should the agile team lead do?

Options:

A.

Create a central repository for information, and provide access to team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide team B with the information on an "as needed" basis

Question 91

During a daily stand up, the tester engages the developer in a discussion about what will be tested during unit testing versus regression testing. What should the scrum master do?

Options:

A.

Ask the tester and developer to discuss it after the meeting, since it is not a part of the daily stand up.

B.

Encourage the discussion to resolve impediments.

C.

After the meeting, escalate this issue to the tester's supervisor to ensure that this does not reoccur.

D.

Ask more questions about the testing techniques to obtain clarification on team efforts for quality improvements.

Question 92

During planning, a project team and sponsor created a visual representation of the high-level specifications of the features and user stories to be implemented in a product. Consensus was achieved on this high-level depiction of the product characteristics, but the sponsor is having difficulty understanding what to develop and when.

How should the project manager explain this to the customer and save time in the meeting?

Options:

A.

Team performance and velocity can be determined only after the project has started

B.

Point out the Walking Skeleton and highlight the basic features that provide value.

C.

Create a kanban board for visualizing the work in process (WIP) and future development.

D.

High-level release planning is part of iteration 0 and works as a proof of concept

Question 93

A client states that a product is not being built as requested How should the agile team address this?

Options:

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Question 94

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Question 95

When considering impact on a project, to whom should an agile project manager give top priority on the stakeholder list?

Options:

A.

The stakeholder who can prevent the project from delivering within budget

B.

The stakeholder who can prevent the project from achieving its goals

C.

The stakeholder who can delay the project

D.

The stakeholder who can work as a friend and help prepare the stakeholder list

Question 96

A new project has been approved and is critical for an organization. The project sponsor has a limited budget, and the deadline to have all requirements meet the definition of done (DoD) is short.

Which approach should the agile practitioner take to facilitate the project's success?

Options:

A.

Set up weekly calls with the key stakeholders to participate in iteration reviews and release decisions.

B.

Analyze the impacts of these constraints on the project followed by a report sent to the sponsor to anticipate any risk of delays.

C.

Set up a meeting with the client to review the scope and timelines to manage expectations.

D.

Encourage the team to build increments and ensure the customer provides early feedback for a minimum viable product.

Question 97

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

Options:

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Question 98

A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"

How should the agile lead respond?

Options:

A.

Total time and average process time

B.

Critical path and queue lengths

C.

Delays and bottlenecks in the process

D.

End date/time and start date/time

Question 99

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals needs to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

Options:

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.

B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.

C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.

D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.

Question 100

The customer needs assistance in determining the efficiency of a set of process activities within the solution. What should the agile team do?

Options:

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority.

D.

Discuss the performance of the solution at the next sprint review

Question 101

To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?

Options:

A.

A list of templates to be used to create the project vision

B.

A list of project stakeholders and user stories

C.

A checklist for future acceptance tests for project deliverables

D.

A list of questions for the team and customer representative

Question 102

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product

Question 103

An agile project leader is delivering a team kick-off session. The first exercise is a "Life Timeline" - a story-telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.

What is the project leader trying to create?

Options:

A.

A safe space for team members to learn to trust one another, leading to collaborative relationships.

B.

A safe space for team members to learn to be vulnerable, leading to high performance relationships.

C.

A safe space for team members to learn to share, leading to collaborative relationships.

D.

A safe space for team members to learn about each other's weaknesses and strengths.

Question 104

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

Options:

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Question 105

A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?

Options:

A.

Create a time-boxed spike story to reduce the technical risk of the feature.

B.

Commence an iteration 0 for the customer and the team to investigate the feature.

C.

Facilitate the decomposition of the feature epic into more manageable user stories.

D.

Facilitate a just-in-time exploration of the functionality by the customer and the team.

Question 106

During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do?

Options:

A.

Explore options for increasing knowledge in the next iteration's backlog.

B.

Experiment with the tool's usage by adding extra tasks in the current iteration.

C.

Propose alternative tools that the team is more competent using.

D.

Ask a tool expert to join the team and perform the relevant work.

Question 107

Question # 107

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Question 108

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

Options:

A.

Invited end customers to attend the stand ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Question 109

A project team's standups often run over the allotted time as members attempt to resolve issues. With a large team, this is leading to productivity impacts and bringing complaints from some members that the meetings are wasting their time when they are not directly involved in an issue’s resolution.

How can the project leader help to manage the team's time?

Options:

A.

Set up individual status meetings and find ways to make sure issues are resolved in advance so that time is not wasted for all team members during the standups

B.

Add time to the standups to accommodate issue-resolution discussions so that everyone is up to date on the decisions made

C.

Change the standups to weekly status meetings with a longer duration to allow team members to resolve issues collaboratively

D.

Ask team members to raise issues during standups and then discuss resolution options with specific members in separate conversations

Question 110

A new product owner needs to manage the backlog of a high-visibility fast-moving project that is consuming a considerable amount of time What should the product owner do?

Options:

A.

Schedule regular meetings with the scrum team to write, groom and size user stories

B.

Focus on stories based on the highest number of story points to first address those items with the highest value

C.

Seek regular input from project stakeholders, and reflect this input in the backlog's priorities

D.

Schedule in-person monthly meetings with key stakeholders to review the project's progress

Question 111

A project manager was assigned to lead the development of a new application for a company. The application will be widely used by all company employees around the world. During the firstmeeting with key project stakeholders, the project manager was asked to find a way to determinate all possible types of users who may interact with the application that is going to be developed.

What should the project manager do next?

Options:

A.

Push it back due to the number of users and socialize the idea of developing a standard application and training session for all users.

B.

Identity and create personas that can help the team better understand the needs of the target user base.

C.

Build a minimum viable product (MVP), a standard application for all users, and release the new version (per users/areas).

D.

'Engage the human resources (HR) team to identify the key users and interview all of them accordingly.

Question 112

During a review session, an agile team presented done requirements to a group of stakeholders Stakeholder feedback indicated that the done requirements failed to meet the most pressing needs and provide value.

What should the team have done to prevent this?

Options:

A.

Reprioritized requirements prior to committing to iteration work

B.

Ensured that requirements remained stable during the iteration cycle

C.

Had stakeholders focus on items created after the product backlog was initially built

D.

Worked on features rather than a set of components

Question 113

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents How should the agile practitioner address this concern?

Options:

A.

Educate the QA manager that in agile quality is integrated from the beginning to end of the project

B.

Write backlog items that include QA as part of the description

C.

Ask for the current QA documents and incorporate them into the technical debt backlog

D.

Ask the product owner to write tests and QA controls into the acceptance criteria

Question 114

In companies where decision making is driven by data analytics and unknown variables are addressed, what advantages does agile project execution offer over a predictive approach?

Options:

A.

A formalized agile approach offers controlled flexibility in dealing with unknown variables in a manner that adds business value.

B.

Agile is focused only on digital transformation project management, whereas a predictive approach focuses on traditional "brick and mortar" projects.

C.

The agile formal change management system is better able to deal with unknown variables.

D.

Agile is relativity new; therefore, it is inherently more aligned with data-analytic-based efforts.

Question 115

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Options:

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Question 116

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope the team plans to work only on spike user stories for the next three sprints

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints.

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after allspikes are executed

Question 117

During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?

Options:

A.

Cross-train some members in the automation framework to broaden their capacity with that skill

B.

Ask the product owner to add team members to boost this particular skill set

C.

Send a member to automation framework training when funds are available

D.

Avoid using test automation by swarming on the testing tasks and using manual testing

Question 118

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

Options:

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements' schedule within set time scales.

Question 119

A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.

What should the scrum master do?

Options:

A.

Review the release plan with the product owner and invite the stakeholders to a series of release reviews.

B.

Review the metrics and the process to determine where the overhead could be further reduced to speed up delivery.

C.

Explain to the product owner why the sprint reviews are now replaced by release reviews as inspect and adapt is a key principle in Scrum.

D.

Explain to the product owner that getting feedback early and often from stakeholders is important so necessary changes can be made quickly.

Question 120

Prior to a retrospective, discussions among team members indicate conflict. An agile practitioner wants to ensure an open and safe environment during the retrospective.

What should the agile practitioner do?

Options:

A.

Review established ground rules with the team

B.

Ask team members specific questions to identify the cause

C.

Encourage the team to continue working to maintain the iteration's schedule

D.

Meet with the product owner and stakeholders to discuss the issue

Question 121

A stakeholder complains about the amount of changes that are being introduced to a project. What should the product owner do?

Options:

A.

Escalate the complaint to the scrum master

B.

Suggest implementing a more rigorous change governance

C.

Coach the stakeholder on agile principles

D.

Agree to limit scope changes going forward to control costs

Question 122

Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.

What should the agile coach do?

Options:

A.

Incorporate quality assurance in the planning stage of product development.

B.

Schedule a dedicated meeting with the product owner to tackle this roadblock.

C.

Conduct a brainstorming exercise to get to the root of the issue and devise action plans.

D.

Conduct a retrospective meeting at the end of the current iteration to identity necessary improvements.

Question 123

A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project

deliverables could not be completed on time.

How should the project team improve during their retrospective for future implementations?

Options:

A.

Use the scrum or team board and daily scrum meetings to track and manage issues and optimize deliverables.

B.

Encourage team members to become general specialists to reduce bottlenecks and create a cross-functional team.

C.

Empower teams and encourage emerging leadership to produce effective solutions to manage complexity.

D.

Define the roles of the individual or group and define the what, how, why, when, and where to do each task.

Question 124

Several team members have complained to senior management about their scrum master's processes. What should the scrum master do to address the team's process concerns?

Options:

A.

Include senior management in the process decisions.

B.

Communicate the processes and expectations to the team.

C.

Conduct retrospectives at the end of every sprint.

D.

Include process feedback in the next sprint planning session.

Question 125

How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?

A project charter has been completed and is ready for approval. The project's goal and approach have been clearly determined and a list of generalized specialists has been set.

How should the project manager introduce the team, communicate the importance of the team charter, and help develop a high-performing team?

Options:

A.

Analyze the list of all project participants and stakeholders, clarifying stakeholder roles and responsibilities.

B.

Promote consensus-driven decision-making and a shared vision for team commitments and decisions.

C.

Determine roles and responsibilities among team members and promote hierarchy, responsibility, and ownership among team members.

D.

Have team members introduce one another and create a hierarchy that reflects responsibilities, roles, and decision-making.

Question 126

A project team identifies a number of technical challenges with features in the next sprint What should they do?

Options:

A.

Request direction from the technical manager

B.

Encourage the product owner to reallocate the features to another sprint

C.

determine who is best qualified to address the challenges

D.

Ask the product owner to assign the tasks to the most appropriately skilled resources

Question 127

In a project, the customer asks for a requirement that clearly deviates from the contract terms. How should the contractor react?

Options:

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.

Question 128

During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

Options:

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can. and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Question 129

Business stakeholders of an agile project frequently skip the review meetings. What should the agile practitioner do?

Options:

A.

Ask the product owner to inform all stakeholders about the project's progress.

B.

Send meeting notes to all stakeholders after each review meeting.

C.

Include the results of the review meetings in the information radiators.

D.

Convince the stakeholders of the benefits of attending the review meetings.

Question 130

What should an agile practitioner do to ensure that the end product meets business requirements?

Options:

A.

Invite the team to iteration review meetings

B.

Obtain agreement from the product owner on business requirements

C.

Request that regular reports are sent to stakeholders.

D.

Confirm managers and stakeholders are invited to product review meetings

Question 131

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Question 132

Question # 132

A scrum master is overseeing the launch of a chatbot for the service desk. Complaints come up post-release about edge case responses to queries. After analyzing the issues, the business decision was made to take the chatbot offline, resulting in workflow disruptions and risking the reputation.

How could this situation have been avoided? (Refer to Testing Protocol Table)

Options:

A.

Conduct user acceptance testing to ensure the chatbot meets stakeholder needs and expectations.

B.

Perform integration testing to minimize any bugs between the chatbot components.

C.

Perform functional testing to verify the chatbot performs the reguired functions.

D.

Conduct regression testing to ensure all previously functioning chatbot features continue to work after updates.

Question 133

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points. How should this be handled?

Options:

A.

The story should be assigned eight story points as per the majority vote

B.

The story should be added to the backlog and reassessed later

C.

The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached

D.

The decision for the number of story points should be made by the customer

Question 134

A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.

What agile practice can help the team to alleviate this?

Options:

A.

Test-driven development (TDD)

B.

Clear definition of done and regular demos

C.

Collaborative team planning games

D.

Consistent team velocity

Question 135

What should a Scrum Master do when one team member falls behind in their tasks?

Options:

A.

Move the task to another team member who has spare capacity in the sprint

B.

Ask the team for suggestions

C.

Privately offer the team member encouragement to meet task commitments

D.

Notify the product owner.

Question 136

A software development team is working in an environment in which increased competition, demanding customer expectations, and new technological developments pose significant challenges. How should the team plan improvements to their product?

Options:

A.

Follow the project schedule created at the start of the project.

B.

Hold regular retrospectives and have team members commit to specific actions.

C.

Allow team members to choose improvement items and trust their judgment.

D.

Encourage team members to write code that is tightly coupled together.

Question 137

The agile practitioner has determined that two different team members are working on addressing the same major issue on the project. How should the agile practitioner address this?

Options:

A.

Implement a burnup chart and add the issue resolution as a task to the product backlog for the customer to prioritize.

B.

Add the issue to the kanban board and assign the it to the team member who has made the most progress on resolving it.

C.

Conduct a root-cause analysis on the issue and identify related risks and risk response owners at the next retrospective.

D.

Document all project issues in a common space and ask the team members to decide on task allocation principles.

Question 138

A software team is developing a product in an environment with increased uncertainty. Although there is a clear vision of the goals to be achieved, the product owner is not fully certain about how some of the product features should work.

How should the product owner address this situation?

Options:

A.

Improve the product testing and quality assurance skills among the team

B.

Facilitate more product planning sessions with the software team.

C.

Consider moving to a more predictive product development approach.

D.

Develop a prototype of the product to obtain feedback from users.

Question 139

A product's scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter. What should the project team do next?

Options:

A.

Estimate the project team's capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Question 140

Question # 140

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

Options:

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

Question 141

A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?

Options:

A.

Advise the product owner that the story will have to wait until the next sprint.

B.

Work extra hours to complete the story and satisfy the customer's requirements.

C.

Break down the story into smaller increments and negotiate other stories on the sprint backlog.

D.

Increase the length of the sprint to accommodate the story.

Question 142

Business partners are attending a daily standup meeting for a project. The business partners are asking questions about the sprint backlog and delivery timing.

How should the project manager explain why this is not the forum to ask these questions?

Options:

A.

The daily standup meeting provides a status update for the scrum.

B.

The daily standup meeting helps to resolve issues that arise within the backlog.

C.

The daily standup meeting helps the team prioritize the work.

D.

The daily standup meeting helps the team keep and synchronize commitments.

Question 143

If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?

Options:

A.

Project sponsor and project team

B.

Scrum master

C.

Product owner

D.

Stakeholders and project team

Question 144

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

Options:

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Page: 1 / 48
Total 482 questions