Weekend Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI PMI-200 PMI Agile Certified Practitioner (PMI-ACP) Exam Practice Test

Page: 1 / 48
Total 482 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 1

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

Options:

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Question 2

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Options:

A.

Code is unit tested, code is peer reviewed, functional testing is passed, business testing is passed, and all acceptance criteria are met.

B.

Code is unit tested, all acceptance criteria are met, business testing passed, code is merged, code is peer reviewed, and documentation is updated.

C.

All acceptance criteria are met, documentation is updated, functional testing is passed, business testing is passed, and code is peer reviewed.

D.

Code is unit tested, all acceptance criteria are met, business testing is passed, functional testing is passed, code is merged, and documentation is updated.

Question 3

The agile coach of a development team uses a servant leadership approach. The team is starting the third iteration of an upgrade to a software product, and work is going slower than initially planned.

What should the coach do to help the team?

Options:

A.

Help the team to remove impediments that stall project progress.

B.

Work with the development team to adjust the work plan.

C.

Ask the product owner to assign more resources to the project.

D.

Command and control the team to achieve plan goals.

Question 4

A project's product owner asks the scrum master to facilitate the estimation activity. The scrum master then meets with the team and the product owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

Options:

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Question 5

Which option describes how risk should be managed in an agile project?

Options:

A.

Since using an agile methodology minimizes risk in project management, the project team can focus on delivering business value over managing risk.

B.

Project team members would each be responsible for identifying and managing risks for the individual user stones they have been assigned

C.

All stakeholders are responsible for identifying risks during standups, retrospectives, and other team meetings.

D.

The product owner is responsible for identifying risks and entering them into the backlog so that their mitigation can be prioritized.

Question 6

An executive requests information regarding a sprint status. What action should the product owner take?

Options:

A.

Invite the executive to the standup.

B.

Direct the executive to the information radiator.

C.

Personally meet with the executive.

D.

Email the requested information to the executive.

Question 7

During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

Options:

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can. and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Question 8

The customer needs assistance in determining the efficiency of a set of process activities within the solution. What should the agile team do?

Options:

A.

Discuss the efficiency at the next iteration retrospective

B.

Review the process value stream to determine potential improvements

C.

Review the value the customer receives from the user story to determine backlog priority.

D.

Discuss the performance of the solution at the next sprint review

Question 9

What is the first thing an agile development team should do when planning an iteration?

Options:

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

Question 10

A project team held a working session with a finance team to understand the procurement process. After the meeting, while the agile lead was facilitating the value stream mapping exercise, one of the team members asked: "When calculating the cycle time, which factors should be considered?"

How should the agile lead respond?

Options:

A.

Total time and average process time

B.

Critical path and queue lengths

C.

Delays and bottlenecks in the process

D.

End date/time and start date/time

Question 11

During a daily stand up, the tester engages the developer in a discussion about what will be tested during unit testing versus regression testing. What should the scrum master do?

Options:

A.

Ask the tester and developer to discuss it after the meeting, since it is not a part of the daily stand up.

B.

Encourage the discussion to resolve impediments.

C.

After the meeting, escalate this issue to the tester's supervisor to ensure that this does not reoccur.

D.

Ask more questions about the testing techniques to obtain clarification on team efforts for quality improvements.

Question 12

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

Options:

A.

Value stream mapping

B.

Long-term Lean planning

C.

Business process modeling

D.

Planning poker

Question 13

A new stakeholder has recently joined a project. During a meeting with the scrum master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the scrum master inform the new stakeholder?

Options:

A.

Show the stakeholder the latest release breakdown for the project.

B.

Invite the stakeholder to attend the next sprint review meeting.

C.

Show the stakeholder the progress radiators for the project.

D.

Invite the stakeholder to attend the next sprint planning meeting.

Question 14

At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity. How should the project team address this issue?

Options:

A.

Suggest pair programming during the retrospective.

B.

Ask the product owner to re-prioritize the user stories at the next retrospective.

C.

Re-estimate the story points with team members at the next iteration planning meeting.

D.

Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.

Question 15

A client needs to release their product to market earlier than planned. They need to start receiving the expected revenue, according to their financial forecast, which will require completing the work left on all user stories in the backlog.

What should the project lead do to accommodate this request?

Options:

A.

Review the burn up chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

B.

Review the burn down chart to make predictions of how many iterations left are required to complete user stories left and make required adjustments to finish earlier.

C.

Ensure the team focus on completing the current items in the backlog and do not accept any request for changes.

D.

Work with the product owner to launch a minimum viable product (MVP) and focus on completing only this portion of work by the new deadline.

Question 16

A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?

Options:

A.

Create a time-boxed spike story to reduce the technical risk of the feature.

B.

Commence an iteration 0 for the customer and the team to investigate the feature.

C.

Facilitate the decomposition of the feature epic into more manageable user stories.

D.

Facilitate a just-in-time exploration of the functionality by the customer and the team.

Question 17

A project team is working with an enterprise agile center of excellence (CoE) to transition to a Scaled Agile Framework (SAFe). Many of the team members are not familiar with the new methodology and are worried that it will lead to more work and scrutiny.

What should the agile team lead do to help ensure a smooth transition?

Options:

A.

Set up lunch-and-learn sessions with the team to provide overviews about the new way of working.

B.

Encourage knowledge sharing and transparency among the working team.

C.

Request the enterprise coach to help the team through the process

D.

Discuss with the team what will change and when and establish a process to address concerns.

Question 18

More details for a story are required before the upcoming sprint planning meeting What should the scrum master do?

Options:

A.

Email the product owner requesting detailed story specifications and wait for a response

B.

Gather the details from the team members before sprint planning

C.

Schedule a story grooming session with the product owner before sprint planning

D.

Conduct a planning poker session with the team

Question 19

An employee just received an Agile certification and has been promoted to team leader. They are working on a project that is experiencing issues with late deliverables. After monitoring project progress, they notice that one impediment is continuously repeated at start of each phase, affecting team's productivity.

How should the team leader exhibit servant leadership?

Options:

A.

By being a change agent

B.

By being the authority on processes

C.

By being a coach

D.

By removing impediments

Question 20

A team member starts discussing a project roadblock during a daily coordination meeting. The team discusses details of the impediment, which takes up most of the meeting time.

What should the agile facilitator do?

Options:

A.

Dismiss the rest of the team from the meeting to focus on the problem reported by the team member

B.

Ask the team member to wait to discuss until the next daily coordination meeting, the team needs to review the current status.

C.

Inform the team that the meeting will be extended so there is time to hear what the team member is reporting

D.

Stop the team politely and suggest scheduling another meeting to discuss this specific matter.

Question 21

A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features.

What should the product owner do?

Options:

A.

Determine the required tasks for implementing the high-level features

B.

Identify the detailed design for the high-level features

C.

Prioritize the product backlog for the upcoming release.

D.

Estimate the user stories in the iteration backlog

Question 22

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?

Options:

A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.

B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

Question 23

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen. What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Question 24

After completing the release plan, the team realizes that the project is very likely to have a negative ROI What should the team do?

Options:

A.

Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI

B.

Replace some team members to reduce the release costs and minimize a negative ROI

C.

Perform a root-cause analysis to remove waste from the delivery process and increase the ROI.

D.

Communicate the risk of a negative ROI to the stakeholders, and update the release plan

Question 25

Question # 25

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

Options:

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Question 26

A mature agile team welcomes a new member Due to poor experiences with a previous team, the new member is reluctant to communicate.

What should the agile project leader do?

Options:

A.

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

Question 27

Stakeholders have conflicting requirements, and the product owner is struggling to decide which user stories to write. What should the product owner do?

Options:

A.

Ask the agile practitioner to help write the user stories.

B.

Ask the agile team to facilitate a story-writing workshop.

C.

Ask subject matter experts (SMEs) to help write the user stories.

D.

Ask the agile practitioner to facilitate a story-writing workshop.

Question 28

The project team is ahead of schedule and beginning lo gold-plate the feature included in the current sprint. What should the agile project manager do?

Options:

A.

Since the team has extra lime, notify the product owner and secure approval for the extra work on this feature.

B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.

C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.

D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.

Question 29

Question # 29

Case Study

An agile project lead for a company is leading a sales team who has committed to delivering new product functionality to the customer at the end of five sprints. The agile project lead performed initial planning with the team and with the team's support has committed to the scope and deadline.

Check in with the project in three stages to answer the associated questions.

How do two additional features and more story points added by the product owner impact the team's progress and ability to complete work within the iteration, considering the burndown rate of the team has not changed? (Refer to the Case Study and End of Sprint 3 Exhibit)

Options:

A.

The scope of the items in the backlog has been increased to reflect an increase in velocity.

B.

The backlog has been increased and the velocity of the project may no longer be on track.

C.

The team has committed to additional work added to the backlog and will increase velocity.

D.

The team did not complete the backlog items at the same velocity due to external issues

Question 30

During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?

Options:

A.

Rework the iteration scope to accommodate these requirements.

B.

Add these requirements into the product backlog for future consideration.

C.

Raise the discovery of these requirements as an issue, and escalate to management.

D.

Immediately start working on these requirements.

Question 31

A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?

Options:

A.

Engage the team to determine the sprint velocity based on previous agile projects.

B.

Average the sprint velocity based on input from team members

C.

Share the sprint velocity obtained from the sponsor with the team

D.

Run multiple sprints before determining the sprint velocity with the team.

Question 32

An experienced product owner presents the epics and corresponding stones during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master's estimation

B.

Identify a set of user stones based on the team's velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

Question 33

An agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.

What should the agile team do?

Options:

A.

Demand frequent product reviews by the product owner

B.

Continuously work with the product owner to do backlog refinement and product reviews

C.

Have the product owner provide detailed requirement specifications to ensure the proper features are delivered

D.

During the planning session, ensure the team is committed to deliver within the specifications

Question 34

Question # 34

Based on the burndown chart, what is the iteration's status?

Options:

A.

It trended ahead of schedule and completed everything on time

B.

It took more time than expected and had to be lengthened.

C.

It trended behind schedule and did not complete everything on time

D.

It took less time than expected and had to be shortened.

Question 35

A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project

deliverables could not be completed on time.

How should the project team improve during their retrospective for future implementations?

Options:

A.

Use the scrum or team board and daily scrum meetings to track and manage issues and optimize deliverables.

B.

Encourage team members to become general specialists to reduce bottlenecks and create a cross-functional team.

C.

Empower teams and encourage emerging leadership to produce effective solutions to manage complexity.

D.

Define the roles of the individual or group and define the what, how, why, when, and where to do each task.

Question 36

A technical problem arises that will likely impact the stories planned for delivery in the current sprint What should the scrum master do?

Options:

A.

Consider adding a story to the next sprint to seek resolution

B.

Immediately solve the problem on behalf of the team

C.

Ask the team to collaboratively work out a solution.

D.

Engage a technical manager to assist with finding a solution

Question 37

While struggling to take ownership of delivery an agile team fails to keep up with its sprint commitments What should the agile coach do?

Options:

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

Question 38

During iteration planning, it was determined that an epic should be decomposed What was the determining factor?

Options:

A.

Size and priority

B.

Minimum marketable features

C.

Release plan

D.

Sprint mapping

Question 39

The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?

Options:

A.

By coaching the team to outperform previous velocity

B.

By coaching the team to adhere to expectations set by the scrum master

C.

By encouraging overestimation to increase velocity

D.

By advising the team to remain committed and focused on project goals

Question 40

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, the junior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, thejunior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

Options:

A.

Escalate the issue to the functional manager and request another team member with more experience.

B.

Ask the team to refer to the team charter on how to resolve this kind of impediment and help the team member.

C.

Coach the team by reminding them that a self-managed team requires everyone to be able to remove their impediments.

D.

Remind them that self-managed teams require everyone to be honest and supportive of one another to resolve impediments.

Question 41

An agile team notices that the same problems continue to occur during multiple iterations Several team members have suggestions to fix the problem.

What is the proper agile approach to handle this?

Options:

A.

Hold frequent retrospectives and share the responsibility for making changes

B.

Understand that this is the nature of innovative business and strive to work harder

C.

Collect team member feedback and discuss them privately with the product owner

D.

Conduct a team-building exercise to increase trust among the team members

Question 42

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

Options:

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value C. Recommend cancelling the current iteration and plan the change request into the next iteration.

C.

Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Question 43

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes detailed design plan

D.

Product vision, business objectives, timeframes

Question 44

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered. What should the agile practitioner do?

Options:

A.

Calculate velocity based on completed sprints and triangulate the remaining work on the backlog to commit to an accurate schedule.

B.

Decompose the product backlog into user stories with tasks/acceptance criteria and estimate to commit to an accurate schedule.

C.

Use analogous estimating techniques based on projects with a similar velocity.

D.

Provide a delivery range based on the team's estimated velocity.

Question 45

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

Options:

A.

Explain to the client that the sprint deadline is approaching and the feature can be included in the next iteration.

B.

Remind the team and the client of the importance of assessing the risks of these features before deciding to include them

C.

Negotiate with the team to add the additional features in this sprint because they are important requirements.

D.

Ask the client for an extension of the deadline to enable delivery of this sprint with the additional features.

Question 46

In a scrum team, who should be responsible for the budget and release plans?

Options:

A.

The scrum master assigns someone on the team to handle the budget, and the product owner is responsible for release plans

B.

The finance department is responsible for budget, and the product owner is responsible for release plans

C.

The scrum team as a whole, as they are self-organizing and share accountability

D.

The product owner is responsible for both the budget and the release plans

Question 47

A scrum team is experiencing lengthy discussions leading to no concrete actions during their scrum events. The scrum master determines that these inefficient meetings are producing waste.

What should the scrum master do to make the meetings more efficient?

Options:

A.

Issue fixed agendas and a decision log for all scrum events to ensure that only relevant agenda points are discussed and decisions are appropriately captured.

B.

Remind the team of the purpose of each scrum event, and implement a policy that long conversations deviating from the scope of each event will be stopped.

C.

Ask the product owner to conduct these discussions in individual meetings with the team members.

D.

Remind the team that staying on topic during meetings is part of being a self-managing team.

Question 48

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?

Options:

A.

Conduct a workshop for all key stakeholders to analyze the case and decide on the proper approach.

B.

Suggest an approach that was successful in a previous project.

C.

Accept the manager's suggestion and avoid unnecessary conflicts and delays.

D.

Work with the team to analyze the market opportunity and create a tailored agile approach if needed

Question 49

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

Options:

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

Question 50

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

Options:

A.

Ask for a team extension so that an engineer with the needed experience can be added to the team.

B.

Suggest that the product owner perform the initial investigation and present the outcome to the team.C Request thai the product owner include a spike in the next iteration's backlog so they can perform an initial investigation

C.

Propose alternative components with which the team has experience.

Question 51

An agile practitioner wants to communicate the effect of technical debt on the project What should the practitioner do?

Options:

A.

Post and discuss rises in the burn down chart

B.

Adjust story points to account for technical debt

C.

Log technical debt as an impediment

D.

Add refactoring tasks to all stories

Question 52

Business stakeholders of an agile project frequently skip the review meetings. What should the agile practitioner do?

Options:

A.

Ask the product owner to inform all stakeholders about the project's progress.

B.

Send meeting notes to all stakeholders after each review meeting.

C.

Include the results of the review meetings in the information radiators.

D.

Convince the stakeholders of the benefits of attending the review meetings.

Question 53

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team's agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Question 54

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?

Options:

A.

Schedule a meeting with the product owner to review the sprint priorities.

B.

Put the high-priority item back into the product backlog.

C.

Extend the sprint end date to accommodate the high-priority item.

D.

Ask the project sponsor to add more resources to ensure timely completion.

Question 55

During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated.

What should the agile project leader have done to avoid this situation?

Options:

A.

Provided just-in-time training of the required skill to specific team members

B.

Lowered the feature's priority until a team member acquired the skill to build it

C.

Assigned the feature to another agile team that had members with the required skills

D.

Ensured that the team was comprised of cross-functional, generalized specialists

Question 56

A large project team is assigned to a complex technical project with many interdependent epics. The team starts to experience problems in the second sprint as the technical leads are independently unable to determine the needed solutions.

What should the project lead do to help the team?

Options:

A.

Coordinate a collaboration session so all the team members are involved in the solution process.

B.

Plan a minimum viable product (MVP) in collaboration with the product owner to reduce technical complexity and move issues to the next release.

C.

Provide training for all team members to enable higher technical skills and the ability to resolve complex issues.

D.

Hire external consultants to advise on solution options and train team members in any technical gaps.

Question 57

What should a learn consider when calculating the effort needed to complete a product backlog?

Options:

A.

The increase in velocity and cost

B.

A buffer in the sprint to mitigate unexpected risks

C.

Assigning extra points to each task to allow time for changes

D.

Stories describing infrastructure tasks and analysis tasks

Question 58

A team member on a new scrum project previously provided support to another application Due to issues with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes this issue in the risk register.

What should the scrum master do next?

Options:

A.

Monitor the threats and risks while allowing the team member to multitask on both projects

B.

Assign more resources to the sprints to compensate for the absences of the team member

C.

Ensure that the threats and risks are communicated and addressed

D.

Assign fewer stories to the sprints so that the team member can still meet sprint goals

Question 59

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

Options:

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Question 60

A development team determined the first release of a product should focus on delivering a minimally viable version of the solution. What is the most important reason the team decided to do this?

Options:

A.

To produce a fast return on investment

B.

To reduce risk as quickly as possible

C.

To gain competitive advantage as soon as possible

D.

To maintain visibility with project stakeholders

Question 61

A scrum team is working together virtually. One of the team members sends a daily email to the other team members listing impediments that they find. During retrospective meetings, the team member complains that their colleagues fail to take actions on the impediments.

How should the team address this issue?

Options:

A.

The team member that is complaining should talk individually with the scrum master to remove impediments.

B.

They should ask for more details about the impediments and then resolve them when the team has more time to investigate.

C.

The team member that is complaining should address the impediments in daily scrum, communicating them directly.

D.

Team members should state that they need to prioritize their work instead of responding to daily emails about impediments.

Question 62

Members of an agile team are complaining that user stories are too large, taking multiple sprints to complete them. They say this way of working is becoming difficult to handle and it has been challenging to map relationships between stories. This situation is affecting the value delivery for the product owner.

What should the scrum master do to handle this situation?

Options:

A.

Separate large user stories.

B.

Apply work-in-progress limits.

C.

Organize user stories into epics.

D.

Replace user stories into features.

Question 63

During a current sprint, a team member asks permission from the scrum master to investigate an alternative design approach What should the scrum master do?

Options:

A.

Discourage the team member from deviating from the plan and document the request during the retrospective

B.

Encourage the team member to research the issue and present the findings during the retrospective

C.

Discourage the team member from using experimentation/spikes unless it is fully developed and accounts for a variety of use cases

D.

Encourage the team member to use experimentation/spikes for continuous improvement and help the team understand why it is important.

Question 64

A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint. What should the team do?

Options:

A.

Advise the product owner that the story will have to wait until the next sprint.

B.

Work extra hours to complete the story and satisfy the customer's requirements.

C.

Break down the story into smaller increments and negotiate other stories on the sprint backlog.

D.

Increase the length of the sprint to accommodate the story.

Question 65

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Question 66

The project manager has requested that the customer participate in the requirements gathering session for the next release. A conflict comes up regarding the requirements between the customer and team.

What should the project manager do?

Options:

A.

Based on value to the organization, the project manager should decide what can be included or not in the final requirements.

B.

The customer is the end user of the product and should have the authority to decide about the product requirements.

C.

The project manager should discuss the requirements with the customer alone so that the team can deliver the prioritized requirements.

D.

Encourage self-organization by communicating the importance of a collaborative approach in decision making about the requirements.

Question 67

A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan.

Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?

Options:

A.

Empower each cross-functional team lead to manage their team's issues and impediments.

B.

Post the daily coordination meetings and discuss impediments raised by the teams.

C.

Ask the project management office (PMO) to work on the communications management plan for the cross-functional teams.

D.

Set up additional meetings to handle additional communications if necessary.

Question 68

A new team member asks what changes could accelerate a change to the project plan What should be the proper response?

Options:

A.

Competitors joined forces with the team

B.

The customer changed requirements

C.

Project team members obtained additional certifications

D.

Technology which did not interfere with the final product

Question 69

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

Options:

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Question 70

For what is the MoSCoW method used?

Options:

A.

Estimating story size

B.

Prioritizing stories

C.

Validating a product

D.

Tracking progress

Question 71

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the scrum master do?

An agile team is struggling to achieve their goal during the first release due to an unstable environment beyond the authority of the product owner. Close to the end of the current sprint, the release manager resigns and a new person takes over.

What should the scrum master do?

Options:

A.

Report the issue to the product owner and request help.

B.

Let the new release manager participate in the daily standup.

C.

Invite the new release manager to the sprint demo and ask for help.

D.

Send a status report to the release manager highlighting the issue.

Question 72

During mid-sprint changes, an agile facilitator meets with the executive and development teams. During the meeting, executive team members resolve conflicts, and on their own initiative, review the iteration charts to discuss changes to the iteration's functional goal.

What practice is the agile facilitator implementing?

Options:

A.

Building openness and transparency on the project's health and status

B.

Facilitating conflict resolution among executive team members

C.

Using active stakeholder involvement to build features in an incremental and iterative approach

D.

Seeking continuous feedback from executive team members

Question 73

A user interface (UI) developer has features for channels ready for review. During the team review, the architect is disappointed that Splunk software has not been implemented for better server and client logs. The architect insists on the implementation of Splunk software, which will impact the release date.

Which one of the following is the ideal option for the team to resolve this conflict?

Options:

A.

Have the team brainstorm and propose error logging at the client level, which will have a higher impact with less effort within the release timeline.

B.

The product owner should explain to the architect that monitoring, alerting, and logging are not essential for the customer and can be prioritized post-release.

C.

Inform the sponsor that features are being added and will extend the release date after getting approval and communicating this to the architect.

D.

Ask the developer to build and let the testing be postponed until after the release, and inform the architect that the feature will be implemented.

Question 74

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables: however, issues arise when the deliverables are integrated. What should the agile practitioner do?

Options:

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

Question 75

A client states that a product is not being built as requested How should the agile team address this?

Options:

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Question 76

A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?

Options:

A.

Assign agile roles within the team and conduct training for each role to provide understanding of the agile methodology.

B.

Organize training and development workshops to help all stakeholders to form a shared understanding of agile practices.

C.

Plan a transformation to agile delivery methods for senior leadership before starting project implementation.

D.

Apply only agile methods and practices for specific deliverables of the work and assign this work to experienced agile team members.

Question 77

The initial roadmap and release dates for an agile project were set based on data from similar projects and some expert opinions. Halfway through the project, however, the team’s estimates are different. Based on the team’s velocity, two more iterations were necessary to accomplish the initial scope.

How should the agile lead explain the difference to the project sponsor?

Options:

A.

Explain how many scope changes were requested by the product owner and how many hours the team dedicated to unplanned tasks.

B.

Explain that initial estimates help measure project feasibility but the real estimates depend on how much the team learns in each sprint.

C.

Explain some features and requirements made aspects of the project unique and are not comparable to previous experiences.

D.

Explain the list of materialized risks not considered at the beginning of the project ted to extra work hours and costs.

Question 78

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Question 79

A scrum master has a team of six members. The team complains they are losing time because they are attending meetings for which they see no value.

What should the scrum master do?

Options:

A.

Ask the team to attend because functional area managers want them to.

B.

Inform the team they do not need to attend and will no longer participate.

C.

Attend these meetings in place of the team members and assess their value.

D.

Attend the meetings with the team members to show solidarity.

Question 80

Several team members have complained to senior management about their scrum master's processes. What should the scrum master do to address the team's process concerns?

Options:

A.

Include senior management in the process decisions.

B.

Communicate the processes and expectations to the team.

C.

Conduct retrospectives at the end of every sprint.

D.

Include process feedback in the next sprint planning session.

Question 81

During a backlog refinement meeting, a senior team member raises a concern about an epic sizing that requires the use of a new interface for a vendor product. The product owner acknowledges this as a risk. What should the product owner do now?

Options:

A.

Log the risk in the risk register, and share the information with impacted stakeholders at the next monthly review meeting.

B.

Create a spike story to determine what needs to be done to use the new interface.

C.

Lower the epic's priority so that it can be deferred, and analyze it during backlog refinement meetings.

D.

Move the work to the vendor, since they have better knowledge of interface implementation.

Question 82

A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution.

What should the project leader do?

Options:

A.

Assign the spike to another resource to continue research for the long-term solution

B.

Re-establish the spike; encourage experimentation and collaborate with the team

C.

Stop experimentation and negotiate the short-term solution with the customer

D.

Schedule a root-cause analysis with the development team on the main issues with the spike

Question 83

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Question 84

As user stories are developed, what should be done to record and update acceptance criteria?

Options:

A.

Add more user stories.

B.

Use sprint retrospectives.

C.

Update current user stories.

D.

Update new tasks in the project plan.

Question 85

A project is to be started with a team of nine existing and nine new members. The scrum master feels that the team is too large and wants to break it into three teams. The scrum master sets aconstraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the scrum master do to accomplish this?

Options:

A.

Ask the team members' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the scrum master.

Question 86

What should an agile practitioner do to ensure that the end product meets business requirements?

Options:

A.

Invite the team to iteration review meetings

B.

Obtain agreement from the product owner on business requirements

C.

Request that regular reports are sent to stakeholders.

D.

Confirm managers and stakeholders are invited to product review meetings

Question 87

A project team member expresses frustration about the length of time it takes to make decisions for a complex project. Approvals needs to happen at many levels in the company.

What should the team lead do to improve decision quality and reduce the time required to make decisions?

Options:

A.

Make sure the project owner is fully embedded into the project team so that they are readily available to make quick decisions.

B.

Establish collaborative behaviors among all members of the organization through a group decision-making process.

C.

Ensure all decisions are routed as quickly as possible to the project sponsor and have the rules of engagement visibly posted.

D.

Reduce the number of required approvals and expand the decision-control limits to the scrum master.

Question 88

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

Options:

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

Question 89

Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.

What can an agile practitioner conclude about team A and team B's estimates?

Options:

A.

Team B has underestimated scope compared to team A.

B.

Team A is more confident in delivering velocity than team B.

C.

Both teams need to indicate their proposed technology before the estimates can be analyzed.

D.

Both teams have estimated the project to be of same size.

Question 90

A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.

What should the Scrum Master do?

Options:

A.

Point out that the team chose to work on other requirements to speed up the project

B.

Ensure that the product owner reviews the contents of the information radiator

C.

Ensure that the next sprint planning meeting reviews the satisfaction histogram

D.

Point out that it is the responsibility of the product owner to clarify requirements

Question 91

A project team developer has been involved in a large corporate initiative that has negatively impacted team productivity on another project to which they have been assigned. How should the developer have handled this situation?

Options:

A.

Worked as planned to meet the team's commitments and participated in other events as time permitted.

B.

Worked extensively on the corporate initiative in order to inform the team of that effort.

C.

Asked to be relieved of project tasks to maintain team velocity.

D.

Have not participated in any initiative that could take focus away from the team's project and goals.

Question 92

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

Options:

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements' schedule within set time scales.

Question 93

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?

Options:

A.

Included the stakeholders in the project planning meeting

B.

Organized an earlier demo to solicit business feedback

C.

Ensured all business leaders signed off on requirements

D.

Engaged key stakeholders periodically to collect requirements

Question 94

A new project is under way and the team is using the Kanban method. One of the team members raised a specific issue related to a programming language that the team member faced in previous projects.

What should the project leader do to handle the issue?

Options:

A.

Include the issue in the risk log.

B.

Monitor the issue in a notation system.

C.

Ask the team member to take full ownership of the issue.

D.

Advise the team member to add the issue to the board.

Question 95

A Kanban team is struggling to prioritize and determine which tasks to handle first according to value. What should the team do to improve this situation?

Options:

A.

Involve their product owner.

B.

Review their work in progress (WIP) limits.

C.

Use class of service.

D.

Measure their lead time.

Question 96

Question # 96

An agile development team is working on a digital transformation project and is facing challenges in obtaining consistent feedback from stakeholders who are dispersed around the world. The product owner is under pressure as this lack of engagement has led to prolonged decision-making cycles and has adversely affected the outcomes of sprints.

How should the team improve stakeholder engagement to help ensure timely feedback and better decision-making? (Refer to Stakeholder Power/Interest Grid)

Options:

A.

Implement a dynamic feedback platform leveraging collaboration tools, accommodating diverse schedules and enabling stakeholders to provide feedback asynchronously.

B.

Establish a rotating stakeholder committee composed of representatives from different regions and departments, ensuring diverse perspectives are considered in decision-making processes.

C.

Enforce a strict policy requiring stakeholders to attend weekly synchronous feedback sessions, leveraging technology to accommodate various time zones and scheduling conflicts.

D.

Appoint regional liaison officers responsible for coordinating stakeholder interactions within their respective time zones, facilitating regular communication and feedback exchange.

Question 97

DRAG DROP

All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)

Question # 97

Options:

Question 98

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

A Scrum team decided to switch to Kanban for the maintenance phase of the product. The kanban board consists of the following columns "To do," "In progress," "Ready to be tested," "Test in progress," and "Done." Since the team changed their way of working, they have noticed the work is flowing slower in the system. A large queue of "Ready to be tested" work items has been building up.

What should the team do to improve its speed of delivery?

Options:

A.

Analyze the process efficiency, cycle time, and lead time of the entire process.

B.

Estimate in story points and pull in new work per the team's capacity

C.

Add limits to all columns and only pull work in when the queue is not full.

D.

Create a cumulative flow diagram and start looking for bottlenecks.

Question 99

Part way through a project, several team members are in conflict over whether or not a deliverable has been properly completed. How should the agile leader reduce this conflict?

Options:

A.

Facilitate team agreement on the definition of done (DoD) during the chartering process.

B.

Motivate the team durinq Tuckman's "storminq" phase.

C.

Ensure the product owner is grooming the backlog so user stories are clearly written.

D.

Ensure epics are broken down into smaller user stories for clarity.

Question 100

After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.

What should the product owner do to resolve this?

Options:

A.

Ask the development team to address the issue since it is in their domain.

B.

Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.

C.

Meet with the team and stakeholders to address rework and rewrite stories as needed.

D.

Cancel the current sprint, and meet with stakeholders to reassess the project's validity.

Question 101

A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?

Options:

A.

Sort the stories in the backlog by descending story points and release the stories at the top of the list equal to the team's velocity.

B.

Prioritize the most valuable product features in the backlog first.

C.

Determine the features with the highest risk and release those first.

D.

Determine which features comprise the smallest feature set that could be successful in the market and establish viability of the product.

Question 102

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

Options:

A.

Refinement meeting

B.

Daily standup meetings

C.

Retrospective

D.

Spike

Question 103

A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.

What agile practice can help the team to alleviate this?

Options:

A.

Test-driven development (TDD)

B.

Clear definition of done and regular demos

C.

Collaborative team planning games

D.

Consistent team velocity

Question 104

An agile team lead is assigned to a project that must ensure data security. What should the team lead do to guarantee that security, as a non-functional requirement, is managed throughout the project?

Options:

A.

Include security concerns on the agenda for every meeting.

B.

Request that a security expert be added to the team.

C.

Add security as a non-functional requirement to the risk register, and review regularly.

D.

Ensure that planning and prioritizing includes consideration of security requirements.

Question 105

A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.

What should the team do to improve the accuracy of their estimates?

Options:

A.

Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint

B.

Discuss estimating techniques in the daily scrum meeting

C.

Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint.

D.

Begin tracking estimated effort metrics as an input to performance evaluation

Question 106

An event management team is following an agile approach to prepare for an upcoming conference. The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.

What should the team do?

Options:

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

Question 107

During backlog refinement, a team routinely creates tests to demonstrate to the customer that each acceptance criterion has been met. Most acceptance tests results are observable or demonstrable, but testing for one requirement is providing a challenge to the team. The requirement states that the home button should be recognizable and the team is unsure how to test this.

What should the team lead do?

Options:

A.

Determine if the home button is present and if it is shaped like a house, it is recognizable.

B.

Record the product owner's opinion on how they will know if the button is recognizable.

C.

Skip creating a specific test for Ibis particular requirement because it is too abstract

D.

Consult the design team as subject matter experts (SMEs) for criteria on what makes a button recognizable.

Question 108

Two agile teams from different company sites need to work and collaborate on the same project. What is the first action the agile project manager should take in order to ensure a smooth collaboration between the two teams?

Options:

A.

Organize onsite backlog-refinement workshops to ensure common understanding.

B.

Set up weekly meetings where all team members will participate.

C.

Call an onsite meeting where ground rules will be discussed and agreed upon.

D.

Ask the product owner to prepare an onsite team-building activity.

Question 109

The transition of a monthly news publication from paper to digital is planned to start in the next few weeks. There is a debate between the product owner and the development team about the initial features to be made available and the first five stages of implementation.

What should the scrum master do to address this situation?

Options:

A.

Request more clarification from the client relations team.

B.

Ask the team to define the minimum marketable feature

C.

Tell the team to proceed with coding the items as currently defined.

D.

Encourage open discussions to help the team reach agreement

Question 110

As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?

Options:

A.

Holistically at the project level

B.

At the end of each sprint

C.

At a sprint level after each demo

D.

Periodically, at both the release and project level

Question 111

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Question 112

During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer How should the team resolve this?

Options:

A.

Refer to the values of the agile framework and the team

B.

Review the signed customer contract

C.

Check the sprint priority list

D.

Submit the problem to the product owner

Question 113

A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?

Options:

A.

The purpose of the daily coordination meeting is for the scrum master to be able to follow up on the sprint plan. The team should explain what may be impeding them from reaching the sprint goal.

B.

According to the Scrum guide, the daily coordination meeting is part of the Scrum framework. The purposes of this meeting are to enable the scrum master to verify the team is on track and to escalate impediments.

C.

The daily coordination meeting is an effective way for the development team to follow up on progress toward the sprint goal and discuss anything that may hinder their work. It is a way to actively manage risks and dependencies.

D.

The daily coordination meeting is held to verify that people are working on the right things. The whole Scrum team should be able to answer these questions: What did I do yesterday, what will I do today, and what can stop me from making progress?

Question 114

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

Options:

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

Question 115

While attending a conference, an agile practitioner learns of a new user interface (Ul) framework that could benefit the team. What should the agile practitioner do next?

Options:

A.

Identify a team member to do a proof of concept using this framework.

B.

Email the team directing them to immediately begin using this new framework.

C.

Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it.

D.

Discuss this option at the next retrospective.

Question 116

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

During a team meeting, conflicting opinions arise regarding the best approach to complete a project task. The project manager wants to ensure that the team can effectively handle these conflicts and come to a resolution that benefits the project.

What is an effective way to handle conflicting opinions in team meetings in an agile environment?

Options:

A.

End the discussion until there is consensus.

B.

Wait for the problem to resolve itself.

C.

Choose the option that is best for the team.

D.

Restate the positions to find what is in common.

Question 117

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?

Options:

A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.

B.

Request the team work overtime to get the work done on time and within the allocated budget.

C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.

D.

Review the contract documentation with the customer to clarity the specific agreed upon budget amount.

Question 118

Question # 118

Based on the backlog metrics in the chart what can explain the jump in points at the end of iteration 4?

Options:

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with thatwork.

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Question 119

Why is stakeholder engagement important for project success?

Options:

A.

To participate in establishing a shared vision as a member of the team

B.

To provide the acceptance criteria for the delivered items

C.

To propose implementation methods to the development team

D.

To evaluate the performance of the development team

Question 120

An agile team is planning the next iteration for a product release that has accumulated technical debt What should the team do?

Options:

A.

Add code cleanup activities to the product backlog and request prioritization by the product owner

B.

Add code cleanup activities to the next iteration and request clarification from the product owner

C.

Add code cleanup activities to the next iteration and ask the product owner to end the current iteration

D.

Add code cleanup activities to the next release backlog and request documentation from the product owner

Question 121

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

Options:

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Question 122

An agile team has received several new features to be added to the product backlog. The team is struggling to provide a reasonable estimate for feature development due to a lack of experience.

How should an experienced agile practitioner assist the team?

Options:

A.

Add a task to the product backlog to allow the team time to investigate and experiment prior to estimating.

B.

Add a task to the product backlog to allow the team to apply a wideband Delphi estimation technique.

C.

Add a task to the product backlog to allow the team to apply planning poker to estimate the effort.

D.

Add a task to the product backlog to allow the team to apply a three-point estimation technique.

Question 123

A customer and a product delivery team meet to discuss a product's attributes, goals expectations. hypothesis1 and high-level needs. What is a benefit of this meeting?

Options:

A.

The team will learn how its contribution will create product value

B.

It will enable team acceptance of client priorities.

C.

It will enable the team to see the entire project in one glance

D.

It will enable the team to ask any questions to the customer upfront

Question 124

A product's scope and acceptance criteria have been defined, and the product is planned for release at the end of the next quarter. What should the project team do next?

Options:

A.

Estimate the project team's capacity.

B.

Determine how much work can be delivered.

C.

Calculate how much work will fit into the next iteration.

D.

Estimate items in the product backlog.

Question 125

A project is starting and the type of work is complex and suitable for agile in assessing the team members, it appears that co-location would be a challenge.

What should the agile practitioner do?

Options:

A.

Select and implement collaboration tools to augment team interactions

B.

Provide each geographical area with their own product owner and divide the work between the teams

C.

Increase the number of requirements documents and ensure they are clearly communicated

D.

After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Question 126

An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.

How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?

Options:

A.

Work with the team to create explicit rules such as coding and quality standards and testing policies.

B.

Discipline the team members and institute status meetings with penalties for any future escaped defects.

C.

Hire more generalized specialists because the current team members cannot keep up with the pace.

D.

Apply work in process (WIP) limits so the developers are not pressured to release code that is problematic.

Question 127

A Scrum team has worked hard to reach their sprint goal, but impediments have prevented them from succeeding. The team needed help from a specialist on another team, but the specialist was on a 2-week vacation.

What should the scrum master do?

Options:

A.

At the sprint retrospective, the scrum master and development team should discuss why the team did not know the specialist was unavailable during the sprint. The scrum master should then set clear rules so situations like these can be avoided in the future.

B.

It can be very distressing for a Scrum team not to reach its sprint goals. The scrum master should hold an evaluation meeting to discuss who in the team was responsible for discovering the specialist was not available, then make an improvement task for the next sprint.

C.

The scrum master, as a servant leader, should always try to remain positive about the team's work. Even when team members’ make mistakes, there should be trust that everyone is doing their best. Engaged team members work more efficiently, and a sustainable pace is important for project success.

D.

At the sprint retrospective, the Scrum team should reflect on how the past sprint has worked out. The scrum master should facilitate an open discussion to discover the root causes for the missed sprint goals and find a way to avoid similar situations in future sprints.

Question 128

A team using Kanban identifies that their cycle time has significant variation After brainstorming the team determines that the root cause is the stones' varying sizes and risks.

What should the team do?

Options:

A.

Reduce work in progress (WIP) limits to accommodate slack for riskier stories

B.

Create a triage step on the Kanban board to pre-identify risky stones

C.

Set a policy to break down stories larger than a specified complexity then adjust the WIP

D.

Create a dedicated overflow swimlane on the Kanban board for stories that are too large

Question 129

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure

B.

Description of all features' functions and an estimate of their cost

C.

Priority list of desired features and functions

D.

Comprehensive schedule of immediate deliverables

Question 130

What is the risk of using agile in a distributed team?

A Frequent integration of work produced

B. Lack of shared knowledge of user stories

C. Need for more locations to learn agile

D. Unclear team structure

Options:

Question 131

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate USS40.000 more than expected for the quarter. What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Question 132

A scrum team is working on an important project with a short deadline. To save time and reduce overhead, the product owner proposes that the regular sprint reviews should be cancelled and replaced with a review of each release according to the release plan.

What should the scrum master do?

Options:

A.

Review the release plan with the product owner and invite the stakeholders to a series of release reviews.

B.

Review the metrics and the process to determine where the overhead could be further reduced to speed up delivery.

C.

Explain to the product owner why the sprint reviews are now replaced by release reviews as inspect and adapt is a key principle in Scrum.

D.

Explain to the product owner that getting feedback early and often from stakeholders is important so necessary changes can be made quickly.

Question 133

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

Options:

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Question 134

What should the agile practitioner know about tracking velocity?

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Question 135

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

Options:

A.

Invited end customers to attend the stand ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

Question 136

Question # 136

Based on the chart, what is the current status of the iteration when comparing story points planned versus completed?

Options:

A.

The iteration is in jeopardy.

B.

The team has removed scope.

C.

The iteration is ahead of schedule.

D.

The team's velocity is constant.

Question 137

An agile team is continuously interrupted by stakeholders wanting to ask product backlog questions. Distractions can have a negative impact on value delivery and quality.

Who is responsible for protecting against distractions?

Options:

A.

Product owner

B.

Project manager

C.

Agile leader

D.

Developers

Question 138

As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)

Options:

A.

Proactively engage the resource managers to lead the team and provide the required support.

B.

Request the enterprise coach and human resources support the team with the transition.

C.

Document the pros and cons and review with stakeholders to determine the dependencies.

D.

Protect the team from disruptions and seek an exemption for status quo.

E.

Assess the impacts of the change and brainstorm potential solutions.

Question 139

During a Kanban team's daily stand up, an agile coach observes that the team seems disinterested in the work status. While it appears that there are no issues with flow, there is a marked lack of attention to team effort. When the agile coach queries the team for reasons, members explain that work continues to be scheduled with no end in sight.

What should the agile coach do?

Options:

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

Question 140

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Question 141

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Question 142

The agile team has failed to meet their iteration goal, and contention has developed between members. The agile leader would like to determine how to improve the team's productivity and morale.

How should the agile leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Question 143

A new agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The scrum master and the team are currently defining their working agreement.

What should be part of the working agreement for a dispersed team?

Options:

A.

Identity support needed from external vendors to assist dispersed team members.

B.

Meet face to face at regular intervals to enhance shared understanding.

C.

Designate one person to communicate with all team members working at different locations.

D.

Define what project work can be done by dispersed team members.

Question 144

The coach on a new agile team notices that one team member is influencing most of the team's decisions. What should the coach do?

Options:

A.

Replace the team member with a more collaborative individual.

B.

Permit the team member to continue influencing because agile teams are self-organizing.

C.

Ask probing questions to other team members to encourage dissenting viewpoints.

D.

Intervene if the team's velocity drops.

Page: 1 / 48
Total 482 questions