Labour Day Special Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

PMI CAPM Certified Associate in Project Management (CAPM) Exam Practice Test

Page: 1 / 114
Total 1135 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 1

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Options:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Question 2

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Question 3

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Question 4

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Question 5

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Question 6

Which document describes the necessary information to determine if a project is worth the required investment?

Options:

A.

Cost baseline

B.

Service level agreement

C.

Memorandum of understanding

D.

Business case

Question 7

Which input to the Plan Risk Management process provides information on high-level risks?

Options:

A.

Project charter

B.

Enterprise environmental factors

C.

Stakeholder register

D.

Organizational process assets

Question 8

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Options:

A.

Negative

B.

Zero

C.

Positive

D.

Free

Question 9

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

Options:

A.

Mandatory

B.

Discretionary

C.

Internal

D.

External

Question 10

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Options:

A.

Organizational process updates

B.

Quality metrics

C.

Change requests

D.

Quality control measurements

Question 11

Organizational theory is a tool used in which Project Human Resource Management process?

Options:

A.

Manage Project Team

B.

Acquire Project Team

C.

Develop Project Team

D.

Plan Human Resource Management

Question 12

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

Options:

A.

Historical relationships

B.

Dependency determination

C.

Bottom-up estimating

D.

Rolling wave planning

Question 13

Which item is an input to the Define Activities process?

Options:

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

Question 14

A tool or technique used in the Control Procurements process is:

Options:

A.

Expert judgment.

B.

Performance reporting.

C.

Bidder conferences.

D.

Reserve analysis.

Question 15

The Identify Stakeholders process is found in which Process Group?

Options:

A.

Initiating

B.

Monitoring and Controlling

C.

Planning

D.

Executing

Question 16

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

Options:

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Question 17

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

Options:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Question 18

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Question 19

Change requests are processed for review and disposition according to which process?

Options:

A.

Control Quality

B.

Control Scope

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Question 20

Sensitivity analysis is typically displayed as a/an:

Options:

A.

Decision tree diagram.

B.

Tornado diagram.

C.

Pareto diagram.

D.

Ishikawa diagram.

Question 21

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Question 22

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Question 23

Enterprise environmental factors are an input to which process?

Options:

A.

Control Scope

B.

Define Scope

C.

Plan Scope Management

D.

Collect Requirements

Question 24

An input used in developing the communications management plan is:

Options:

A.

Communication models.

B.

Enterprise environmental factors.

C.

Organizational communications,

D.

Organizational cultures and styles.

Question 25

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

Options:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Question 26

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Enterprise environmental factors

D.

Risk register

Question 27

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Question 28

Which tool or technique is used in validating the scope of a project?

Options:

A.

Facilitated workshops

B.

Interviews

C.

Inspection

D.

Meetings

Question 29

An input to the Plan Cost Management process is:

Options:

A.

Cost estimates.

B.

Resource calendars,

C.

The project charter,

D.

The risk register.

Question 30

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Question 31

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

Options:

A.

Power/influence grid

B.

Power/interest grid

C.

Influence/impact grid

D.

Salience model

Question 32

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques

B.

Expert judgment

C.

Analytical techniques

D.

Variance analysis

Question 33

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Question 34

A temporary endeavor that creates a unique product or service is called a:

Options:

A.

Project

B.

Plan

C.

Program

D.

Portfolio

Question 35

Scope, schedule, and cost parameters are integrated in the:

Options:

A.

Performance measurement baseline.

B.

Analysis of project forecasts,

C.

Summary of changes approved in a period,

D.

Analysis of past performance.

Question 36

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Options:

A.

Project document updates

B.

Activity list

C.

Activity attributes

D.

Project calendars

Question 37

Which item is a formal proposal to modify any document, deliverable, or baseline?

Options:

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Question 38

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.

B.

Project charter.

C.

Work breakdown structure.

D.

Stakeholder register.

Question 39

An output of the Develop Project Team process is:

Options:

A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Question 40

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Question 41

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

Options:

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive

Question 42

Lessons learned are created and project resources are released in which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Question 43

Which Control Quality tool is also known as an arrow diagram?

Options:

A.

Matrix diagram

B.

Affinity diagram

C.

Tree diagram

D.

Activity network diagram

Question 44

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (T&M)

Question 45

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Question 46

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Closing

Question 47

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Options:

A.

Close Project or Phase

B.

Conduct Procurements

C.

Control Procurements

D.

Close Procurements

Question 48

The number of potential communication channels for a project with 5 stakeholders is:

Options:

A.

10.

B.

12.

C.

20.

D.

24.

Question 49

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

Options:

A.

Risk and uncertainty increase; the cost of changes increases.

B.

Risk and uncertainty increase; the cost of changes decreases,

C.

Risk and uncertainty decrease; the cost of changes increases.

D.

Risk and uncertainty decrease; the cost of changes decreases.

Question 50

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Question 51

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Question 52

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Question 53

An input of the Create WBS process is:

Options:

A.

requirements documentation.

B.

scope baseline.

C.

project charter.

D.

validated deliverables.

Question 54

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Question 55

Resource calendars are included in the:

Options:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Question 56

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Question 57

Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Question 58

Risk exists the moment that a project is:

Options:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Question 59

The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

Options:

A.

Cost Plus Incentive Fee Contract (CPIF).

B.

Cost Plus Fixed Fee Contract (CPFF).

C.

Fixed Price Incentive Fee Contract (FPIF).

D.

Time and Material Contract (T&M).

Question 60

The staffing management plan is part of the:

Options:

A.

organizational process assets.

B.

resource calendar.

C.

human resource plan.

D.

Develop Project Team process.

Question 61

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Question 62

Which of the following is an output of Define Scope?

Options:

A.

Project scope statement

B.

Project charter

C.

Project plan

D.

Project schedule

Question 63

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Question 64

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

Options:

A.

Control Scope

B.

Collect Requirements

C.

Create WBS

D.

Define Scope

Question 65

Which statement correctly describes the value of a business case?

Options:

A.

It provides the necessary information to determine if a project is worth the required investment.

B.

It provides for alternative dispute resolution procedures in event of contract default.

C.

It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D.

It is used to help a project manager understand the scope of commercial advantages.

Question 66

Which of the following is a tool and technique used to monitor risk?

Options:

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

Question 67

The diagram below is an example of a:

Question # 67

Options:

A.

Risk breakdown structure (RBS).

B.

Project team.

C.

SWOT Analysis.

D.

Work breakdown structure (WBS).

Question 68

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Question 69

Which of the following is a tool or technique used in the Acquire Project Team process?

Options:

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

Question 70

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Question 71

Which of the following is an input to the Develop Project Charter process?

Options:

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Question 72

Which is one of the determining factors used to calculate CPI?

Options:

A.

EV

B.

SPI

C.

PV

D.

ETC

Question 73

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?

Options:

A.

0.8

B.

0.89

C.

1.13

D.

1.25

Question 74

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode

B.

Encode

C.

Medium

D.

Noise

Question 75

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Question 76

When cost variance is negative and schedule variance is positive, the project is:

Options:

A.

under budget and behind schedule.

B.

over budget and ahead of schedule.

C.

on schedule.

D.

complete; all planned values have been earned.

Question 77

Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?

Options:

A.

Acquisition

B.

Negotiation

C.

Virtual team

D.

Pre-assignment

Question 78

Risk responses reflect an organization's perceived balance between:

Options:

A.

risk taking and risk avoidance.

B.

known risk and unknown risk.

C.

identified risk and analyzed risk.

D.

varying degrees of risk.

Question 79

Which of the following includes how requirements activities will be planned, tracked, and reported?

Options:

A.

Configuration management plan

B.

Scope baseline

C.

Requirements management plan

D.

Schedule baseline

Question 80

Which of the following response strategies are appropriate for negative risks or threats?

Options:

A.

Share, Accept, Transfer, or Mitigate

B.

Exploit, Enhance, Share, or Accept

C.

Mitigate, Share, Avoid, or Accept

D.

Avoid, Mitigate, Transfer, or Accept

Question 81

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Question 82

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Question 83

How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?

Options:

A.

Keep satisfied

B.

Keep informed

C.

Manage closely

D.

Monitor

Question 84

Which of the following can be used as an input for Define Scope?

Options:

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Question 85

Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?

Options:

A.

Affinity

B.

Scatter

C.

Fishbone

D.

Matrix

Question 86

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Question 87

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Question 88

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Question 89

At the end of the project, what will be the value of SV?

Options:

A.

Positive

B.

Zero

C.

Negative

D.

Greater than one

Question 90

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Question 91

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Question 92

What is project management?

Options:

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Question 93

Prototype development may be used as a tool for which of the following risk response strategies?

Options:

A.

Avoid

B.

Accept

C.

Mitigate

D.

Exploit

Question 94

Which process requires implementation of approved changes?

Options:

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

Question 95

Which is an output of the Collect Requirements process?

Options:

A.

Requirements traceability matrix

B.

Project scope statement

C.

WBS dictionary

D.

Work performance measurements

Question 96

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

Options:

A.

Scope baseline

B.

Scope management plan

C.

Change management plan

D.

Cost baseline

Question 97

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Question 98

Which of the following is a tool or technique used in the Determine Budget process?

Options:

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Question 99

Which of the following items is a technique for data gathering?

Options:

A.

Facilitation

B.

Meeting management

C.

Conflict management

D.

Interviews

Question 100

What process group establishes project scope: refines objectives, and defines the actions necessary to attain project objectives'?

Options:

A.

Executing

B.

Planning

C.

Initiating

D.

Monitoring and Controlling

Question 101

A project manager needs to request outside support......manager need to create

A project manager needs to request outside support for a statement ot work (SOW) that is not precise. Which kind of contract does the project manager need to create?

Options:

A.

Time and material (T&M)

B.

Cost plus fixed fee (CPFF)

C.

Fixed price

D.

Cost plus award fee (CPAF)

Question 102

One of the outputs of the project schedule is a detailed plan. What is the main purpose of that detailed plan?

Options:

A.

It represents how and when the project will deliver the products, services, and results defined in the project scope

B.

It creates a formal record of the project and shows the organizational commitment to the project

C.

It describes how the scope will be defined, developed, monitored, controlled and validated

D.

It provides the needs of a stakeholder or stakeholder group

Question 103

The project manager and the project team are in the process of documenting procurement decisions. Which of the following will be the procurement strategy?

Options:

A.

Payment types, delivery methods, and procurement phases

B.

Procurement metrics, make-or-buy decisions, and procurement statement of work

C.

Vendor selection criteria, stakeholder roles and responsibilitys, and prequalified sellers

D.

Timetable procurement activities, product cost, and knowledge transfer schedule

Question 104

What is purpose of using the building information model (BIM) in software tools in the construction field?

Options:

A.

Reduce significant amount of time and money

B.

Help manage risks in large projects

C.

Keep up with emerging trends

D.

Provide sellers with multiple sources for documents

Question 105

If a project manager effectively manages project knowledge, a key benefits is that:

Options:

A.

all stakeholders have access to the same information.

B.

the project team is able to understand the project status.

C.

project stakeholders have a clear picture of the project.

D.

new knowledge is added to organizational process assets.

Question 106

Which can be used to convert a verified deliverable to an accepted deliverable?

Options:

A.

Decomposition

B.

Reporting

C.

Voting

D.

Brainstorming

Question 107

Match the method for categorizing stakeholders with its corresponding description

Question # 107

Options:

Question 108

For which kind of quantitative risk analysis chart can a tornado diagram represent values?

Options:

A.

Sensitivity analysis

B.

Monte Carlo analysis

C.

Expected monetary value analysis

D.

Decision tree analysis

Question 109

What process is included in Project Integration Management?

Options:

A.

Monitor and Control Project Work

B.

Control Scope

C.

Control Schedule

D.

Develop Team

Question 110

What specific quality considerations should be examined while completing Quality Management plan?

Options:

A.

Risk register

B Stakeholder engagement

B.

Continuous improvement

C.

Standards and regulatory compliance

Question 111

Which key benefit can a project manager obtain by identifying stakeholders?

Options:

A.

Identify the appropriate focus for engagement of each stakeholder.

B.

Assess the risk exposure for each stakeholder.

C.

Map stakeholder power and influence grid.

D.

Identify the appropriate channels of communication with all stakeholders.

Question 112

What is the recommended approach for handling risk in a high-variability environment?

Options:

A.

Adaptive

B.

Predictive

C.

Iterative

D.

Incremental

Question 113

In the Control Quality process, which tools and techniques techniques can be applied to verify deliverable?

Options:

A.

Statistical sampling, inspection, and meetings

B.

Lessons learned register, control charts, and product evaluation

C.

Checklists, retrospective documents, and approved change requests

D.

Black box tests, questionnaires and surveys, and lessons learned register

Question 114

What process is used to identify quality requirements and/or standards for a project and its deliverables'?

Options:

A.

Manage Quality

B.

Plan Quality Management

C.

Control Quality

D.

Perform Qualitative Risk Analysis

Question 115

How is program success measured?

Options:

A.

By delivering the benefit of managing the program's projects in a coordinated manner

B.

By the quality, timeliness, cost-effectiveness, and customer satisfaction of the product or service

C.

By completing the right projects to achieve objectives rather than completing projects the right way

D.

By aggregating the successes of the individual projects in the program

Question 116

During what project management process does the project team begin identifying risks?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Question 117

What tool or technique is primarily used to plan risk responses'?

Options:

A.

Risk categorization

B.

Project risk document updates

C.

Strategies for overall project risk

D.

Risk management plan

Question 118

Company Aā€™s accountant sends notification about a change in the companyā€™s tax classification.

What would a project have to be initiated?

Options:

A.

To change business and technological strategies

B.

To improve processes and services

C.

To meet regulatory and legal requirements

D.

To satisfy stakeholder requests

Question 119

Development of the benefits management plan occurs in which stage of the project life cycle?

Options:

A.

Starting the project

B.

Organizing the project

C.

Completing pre-project work

D.

Executing the product

Question 120

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options:

A.

Engage customer earlier

B.

Conduct quality audits

C.

Validate Scope

D.

Validate quality requirements

Question 121

What is an example of an emerging trend in procurement management?

Options:

A.

Online technology enable projects to postpone ordering long lead items until the items are needed

B.

Online technologies allow a project's progress to be viewed by all stakeholders to build better relations

C.

Online procurement tools provide buyers with multiple sources to advertise to sellers.

D.

Online procurement tools provide sellers with designated sources for procurement documents and the resources to complete them.

Question 122

What Knowledge Area must be led by the project manager and cannot be delegated to other specialists?

Options:

A.

Project Cost Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Schedule Management

Question 123

Which of these is true project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects

B.

Project Integration Management and Expert Judgement are mutually exclusive

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero

Question 124

Which of the following is example of communication tools and techniques?

Options:

A.

Conflict management

B.

Stakeholder mapping

C.

Advertising plan

D.

Developing team

Question 125

What does ā€™verifiedā€™ in verified deliverable represent?

Options:

A.

The correctness of a deliverable

B.

The completeness of a deliverable

C.

The deliverable requirements

D.

The customer acceptance of a deliverable

Question 126

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Closes Project or Phase

D.

Perform itegrated Change Control

Question 127

A project manager is creating a project charter to provide a direct link between the project and the organization's strategic objectives. What must be considered when creating this document?

Options:

A.

High-level requirements and the project team

B.

Key stakeholder list and contingency reserve

C.

Detailed milestone schedule and project objectives

D.

Project purpose and high-level project description

Question 128

In which project risk management process is the data analysis technique not used?

Options:

A.

Plan Risk Management

B.

Implement Risk Response

C.

Monitor Risks

D.

Perform Quantitative Risk Analysis

Question 129

Project managers plan a key role performing integration on the project what are the three different levels of integration?

Options:

A.

Process, cognitive

B.

Complexity, understand and change

C.

Interact, insight and leadership

D.

Communication, knowledge and value

Question 130

Which of these is a hybrid contract?

Options:

A.

Cost plus award fee (CPAF)

B.

Firm fixed price (FFP)

C.

Fixed price incentive fee (FPIF)

D.

Time and material (T&M)

Question 131

A project manager is reviewing a past project with similar.... team choosing for tailoring?

A project manager is reviewing a past project with similar requirements to the project that is currently chartered. The project team decided to adopt quality tools, techniques and templates recommended at the organizational level after reviewing the lessons learned of the previous project What specific area of quality, is the project team choosing for tailoring?

Options:

A.

Policy compliance and auditing

B.

Standards and compliance

C.

Review of lessons learned

D.

Test and inspection planning

Question 132

Match the praxes manager's sphere of influence with the associated primary role:

Question # 132

Options:

Question 133

What is the primary benefit of the Manage Quality process?

Options:

A.

Increases the probability of meeting quality objectives

B.

Enhances the performance of the product berg created

C.

Defines quality roles and responsibilities

D.

Ensures that the project is completed as originally planned

Question 134

What is the most important skill that project managers should possess to lead stakeholders throughout a project?

Options:

A.

Communication

B.

Problem-solving

C.

Negotiating

D.

Trust-building

Question 135

A project manager proactively meets with other project managers who manage other projects in the same program. To minimize the impact that other projects within the program may have on their project of what should the project manager be aware?

Options:

A.

Demands on the same resources

B.

Requirements that impact the scope

C.

Uncertainty of emerging issues

D.

Project charter

Question 136

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?

Options:

A.

Risk management plan

B.

Communications management plan

C.

Change management plan

D.

Stakeholder engagement plan

Question 137

What tern describes an intentional activity to modify a nonconforming product or product component?

Options:

A.

Preventive action

B.

Corrective action

C.

Defect repair

D.

Updates

Question 138

Which of the following is an example of tacit knowledge

Options:

A.

Risk register

B.

Project requirements

C.

Expert judgment

D.

Make-or-buy analysis

Question 139

What process in Project Risk Management prioritizes project risks?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Responses

D.

Implement Risk Responses

Question 140

A project manager is performing a specific process and has..........is being referred to?

A project manager is performing a specific process and has a list of accepted deliverables One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables Which process is being referred to?

Options:

A.

Control Quality

B.

Validate Scope

C.

Validate Quality

D.

Control Scope

Question 141

Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?

Options:

A.

Learn methods

B.

collaborative teams

C.

Generalizing specialists

D.

Knowledge sharing

Question 142

What is the Project Schedule Management practice used to deliver incremental value to the customer'?

Options:

A.

Resource optimization

B.

Iterative scheduling with a backlog

C.

On-demand scheduling

D.

Critical path method

Question 143

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMIā€™s Talent Triangle best relates to this need to improve?

Options:

A.

Strategic and business management skills

B.

Leadership skills

C.

Technical project management

D.

Organizational management

Question 144

What should a project manager consider to address the full delivery life cycle for large projects?

Options:

A.

A range of techniques utilizing a plan driven approach, adaptive approach or a hybrid ot both

B.

Only techniques of an agile/adaptive approach in large organizations

C.

Change the role of the project manager to managing pro|ci I in adaptive nuviionin-

D.

Splitting larger projects into two or more smaller project is which can be addressed in an adaptive method

Question 145

Why is required in a project?

Options:

A.

Because a one-size-fits-all approach avoids complications and saves time.

B.

Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required.

C.

Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project.

D.

Project managers should apply every process in the PMBOK Guide to the project, so failoring is not requires.

Question 146

What estimating technique is used when there is limited information?

Options:

A.

Analogous estimating

B.

Parametric estimating

C.

Bottom-up estimating

D.

Three-point estimating

Question 147

What is the goal of the control quality process in project management?

Options:

A.

To monitor the activities of the project and ensure Iho work is being executed as it was planned

B.

To obtain a quality cerlific ation for the product of the project service or result

C.

To assess performance and ensure the project product, service, or result meets the customer's expectations

D.

To test the product service, or result to determine if the errors observed are within the defined quality margins

Question 148

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Question 149

The following chart contains information about the tasks in a project.

Question # 149

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Question 150

At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

Options:

A.

Result

B.

Product

C.

Service

D.

Improvement

Question 151

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Question 152

Analytical techniques are a tool and technique of which process in Project Procurement Management?

Options:

A.

Plan Procurement Management

B.

Control Procurements

C.

Conduct Procurements

D.

Close Procurements

Question 153

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

Options:

A.

Control Quality

B.

Monitor and Control Project Work

C.

Control Scope

D.

Perform Integrated Change Control

Question 154

Tools and techniques used in Direct and Manage Project Work include:

Options:

A.

Process analysis and expert judgment

B.

Analytical techniques and a project management information system

C.

Performance reviews and meetings

D.

Expert judgment and meetings

Question 155

The following chart contains information about the tasks in a project.

Question # 155

Based on the chart, what is the schedulevariance (SV) for Task 8?

Options:

A.

-2,000

B.

-1,000

C.

1,000

D.

2,000

Question 156

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Question 157

The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Question 158

Whose approval may be required for change requests after change control board (CCB) approval?

Options:

A.

Functional managers

B.

Business partners

C.

Customers or sponsors

D.

Subject matter experts

Question 159

The following is a network diagram for a project.

Question # 159

The free float for Activity E is how many days?

Options:

A.

2

B.

3

C.

5

D.

8

Question 160

Which type of organizational structure is displayed in the diagram provided?

Question # 160

Options:

A.

Balanced matrix

B.

Projectized

C.

Strong matrix

D.

Functional

Question 161

The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

Options:

A.

adaptive

B.

reflexive

C.

predictive

D.

iterative

Question 162

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Control Costs

C.

Plan Cost Management

D.

Determine Budget

Question 163

The primary benefit of the Plan Schedule Management process is that it:

Options:

A.

provides guidance to identify time or schedule challenges within the project.

B.

tightly links processes to create a seamless project schedule.

C.

guides how the project schedule will be managed throughout the project.

D.

creates an overview of all activities broken down into manageable subsections.

Question 164

Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

Options:

A.

influencing

B.

leadership

C.

motivation

D.

coaching

Question 165

Which quality tool may prove useful in understanding and estimating the cost of quality in a process?

Options:

A.

Checksheets

B.

Histograms

C.

Flowcharts

D.

Control charts

Question 166

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition

B.

Inspection

C.

Project analysis

D.

Document analysis

Question 167

The following chart contains information about the tasks in a project.

Question # 167

Based on the chart, what is the schedule performance index (5PI) for Task 4?

Options:

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Question 168

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Options:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Question 169

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Question 170

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

Options:

A.

Update

B.

Preventive action

C.

Defect repair

D.

Corrective action

Question 171

The following chart contains information about the tasks in a project.

Question # 171

Based on the chart, what is the cost performance index (CPI) for Task 2?

Options:

A.

0.8

B.

1

C.

1.25

D.

1.8

Question 172

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Question 173

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.

B.

Contain the standard activity list.

C.

Document and support the project change requests.

D.

Prescribe the level of detail needed to manage the work.

Question 174

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

Options:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Question 175

Project Scope Management is primarily concerned with:

Options:

A.

Developing a detailed description of the project and product.

B.

Determining how requirements will be analyzed, documented, and managed.

C.

Defining and controlling what is and is not included in the project.

D.

Formalizing acceptance of the completed project deliverables.

Question 176

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Options:

A.

Strong

B.

Weak

C.

Managed

D.

Balanced

Question 177

The following is a network diagram for a project.

Question # 177

The shortest non-critical path for the project is how many days in duration?

Options:

A.

10

B.

12

C.

14

D.

16

Question 178

A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

Options:

A.

Work breakdown structure

B.

Requirements document

C.

Project charter

D.

Project management plan

Question 179

While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:

Options:

A.

ends.

B.

begins.

C.

delays.

D.

deviates.

Question 180

An intentional activity to modify a nonconforming product or product component is called:

Options:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Question 181

A risk that arises as a direct result of implementing a risk response is called a:

Options:

A.

contingent risk

B.

residual risk

C.

potential risk

D.

secondary risk

Question 182

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Question 183

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Question 184

Power, urgency, and legitimacy are attributes of which stakeholder classification model?

Options:

A.

Salience

B.

Influence/impact

C.

Power/interest

D.

Power/influence

Question 185

Which item is a cost of conformance?

Options:

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Question 186

Outputs of the Control Communications process include:

Options:

A.

expert judgment and change requests.

B.

work performance information and change requests.

C.

organizational process asset updates and an issue log.

D.

project management plan updates and an issue log.

Question 187

The purpose of the Project Communications Management Knowledge Area is to:

Options:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Question 188

The chart below is an example of a:

Question # 188

Options:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

Question 189

The zero duration of milestones in project planning occurs because milestones:

Options:

A.

Are unpredictable and challenge the Plan Schedule Management process.

B.

Occur at random times in the project plans.

C.

Represent a moment in time such as a significant project point or event.

D.

Represent both significant and insignificant points in the project and are difficult to anticipate.

Question 190

Specification of both the deliverables and the processes is the focus of:

Options:

A.

Change control

B.

Configuration control

C.

Project monitoring and control

D.

Issue control

Question 191

An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

Options:

A.

Forecasting,

B.

Brainstorming.

C.

Historical databases.

D.

Cost of quality.

Question 192

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

Options:

A.

Information management systems

B.

Work performance reports

C.

Stakeholder analysis

D.

Data gathering and representation

Question 193

Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

Options:

A.

Cause-and-effect diagram

B.

Histogram

C.

Control chart

D.

Scatter diagram

Question 194

In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

Options:

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Question 195

Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

Options:

A.

100

B.

120

C.

1,000

D.

1,200

Question 196

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders

B.

Stakeholders and functional managers

C.

Project team members and consultants

D.

Project team members and stakeholders

Question 197

Which of these is true of project integration management?

Options:

A.

Project Integration Management is mandatory and more effective in larger projects.

B.

Project Integration Management and expert judgment are mutually exclusive.

C.

Project Integration Management is the responsibility of the project manager

D.

Project Integration Management excludes the triple constraints if cost performance index (CPI) equals zero.

Question 198

In which Project Cost Management process is work performance data included?

Options:

A.

Plan Cost Management

B.

Estimate Costs

C.

Determine Budget

D.

Control Costs

Question 199

What important leadership quality/qualities should project managers possess?

Options:

A.

Skills and behaviors related to specific domains of project management

B.

Skills and behaviors needed to guide a team and help an organization reach its goals

C.

Industry expertise that helps to better deliver business outcomes

D.

Industry and organizational expertise that enhances performance

Question 200

A team receives four different requests from separate stakeholders related to one application Match each requirement with its corresponding type of change request.

Question # 200

Options:

Question 201

Make-or-buy analysis is a tool and technique of which process?

Options:

A.

Conduct Procurements

B.

Plan Procurement Management

C.

Analyze Procurements

D.

Control Procurements

Question 202

Once the make-or-buy analysis is completed, which document defines the project delivery method?

Options:

A.

Procurement statement of work (SOW)

B.

Procurement strategy

C.

Terms of reference

D.

Change request

Question 203

When should Project Risk Management be conducted?

Options:

A.

Project Planning

B.

Monitoring and Controlling

C.

Quality Planning

D.

Throughout the project lifecycle

Question 204

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

Options:

A.

Plan Quality Management

B.

Control Quality

C.

Risk Management

D.

Plan Scope Management

Question 205

In which of the Risk Management processes is the project charter used as an input?

Options:

A.

Plan Risk Responses

B.

Implement Risk Responses

C.

Plan Risk Management

D.

Perform Quantitative Risk Responses

Question 206

Which statement about identification and engagement of stakeholders during a project is correct?

Options:

A.

Project stakeholders should be Identified and engaged in every phase of the project to influence the success of the project directly.

B.

Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.

C.

Project stakeholders should be identified when the project chatter is being completed and engaged during requirements gathering.

D.

Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process.

Question 207

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

Options:

A.

Internal enterprise environmental factor

B.

Risk register database

C.

External enterprise environmental factor

D.

Organizational process asset

Question 208

An organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:

Options:

A.

Project Management Information System

B.

Project Management System

C.

Project Management Office

D.

Project Management Knowledge Area

Question 209

A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?

Options:

A.

Informal

B.

Unofficial

C.

Formal

D.

Hierarchical

Question 210

Which statement is related to the project manager's sphere of influence at the organizational level?

Options:

A.

A project manager interacts with other project managers to detect common interests and impacts between their projects.

B.

A project manager facilitates communication between the suppliers and contractors on the project.

C.

A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.

D.

A project manager may inform other professionals about the value of project management.

Question 211

Which of the following is used as an input to prepare a cost management plan?

Options:

A.

Expert judgment

B.

Lessons learned

C.

Cost estimates

D.

Project management plan

Question 212

The project manager is creating the communications management plan Which group of inputs Is required to begin?

Options:

A.

Work performance reports, change requests, and risk register

B.

Work performance data, project documents, and stakeholder engagement plan

C.

Project charter, project management plan, and project documents

D.

Work performance data, stakeholder register, and team management plan

Question 213

Which of the following best correspond to the organizational process assets (OPAs) that affect the project?

Options:

A.

Policies and lessons learned from other projects

B.

Information technology software and employee capability

C.

Resource availability and employee capability

D.

Marketplace conditions and legal restrictions

Question 214

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

Options:

A.

Diversity background

B.

Stakeholder's relationships

C.

Technical expertise

D.

Knowledge management

Question 215

Which of the following are components of the technical project management skill?

Options:

A.

Ability to explain business aspects of the project, business strategy, goals and objectives, and business value.

B.

Ability to deal with people, to be collaborative, and to apply persuasion and negotiation.

C.

Ability to focus on relationships with people, inspire trust, and implement decisions and actions that support the business strategy.

D.

Ability to plan and prioritize, gather the right artifacts available for each project, and focus on critical success factors.

Question 216

Which knowledge area includes the processes to identify, define, and unify the various project management processes?

Options:

A.

Project Integration Management

B.

Project Communications Management

C.

Project Qualify Management

D.

Project Risk Management

Question 217

A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.

Which strategies should the project manager take into account for risk management in this environment?

Options:

A.

Occasionally identify, evaluate, and classify risks.

B.

Review requirements and cross-functional project teams.

C.

Include contingency reserves and update the project management plan frequently.

D.

Frequently review incremental work products and update the requirements for proper prioritization.

Question 218

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

Options:

A.

Project Schedule Management

B.

Project Scope Management

C.

Project Resource Management

D.

Project Integration Management

Question 219

When project requirements are documented in user stones then prioritized and refined just prior to construction, which approach is being used for scheduling?

Options:

A.

Iterative scheduling with backlog

B.

On-demand scheduling

C.

Life cycle scheduling with backlog

D.

Defining Iterative activities

Question 220

What charts and (igures should project managers use during the Perform Quantitative Risk Analysis process?

Options:

A.

Tornado diagrams and influence diagrams

B.

Detectability bubble charts and probability and impact matrix

C.

Hierarchical charts and burndown charts

D.

Flow charts and responsible, accountable, consult, and inform (RACI) charts

Question 221

Match the influence with its corresponding category of influence.

Question # 221

Options:

Question 222

What process is included in Project Schedule Management?

Options:

A.

Estimate Activity Durations

B.

Create Work Breakdown Structure (WBS)

C.

Direct and Manage Project Work

D.

Estimate Activity Resources

Question 223

In an agile and adaptive project, which scope management entity invokes stakeholder engagement?

Options:

A.

Collect Requirements

B.

Create work breakdown structure (WBS)

C.

Plan Scope Management

D.

Scope Baseline

Question 224

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Options:

A.

Change request

B.

Risk response

C.

Risk management plan

D.

Lessons learned

Question 225

Which of the following is used to classify stakeholders based on their assessments of power, urgency, and legitimacy?

Options:

A.

Power interest grid

B.

Stakeholder cube

C.

Salience model

D.

Directions of influence

Question 226

What organizational asset can influence the Plan Risk Management process?

Options:

A.

Corporate policies and procedures for social media, ethics, and security

B.

Organizational risk policy

C.

Stakeholder register templates and instructions

D.

Organizational communication requirements

Question 227

Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

Options:

A.

List of identified risks, potential risk owners, list of potential risk response

B.

List of identified risks, list of causes, list of risk categories

C.

Short risk titles, list of potential risk owners, list of impacts on objectives

D.

List of activities affected, list of potential risk responses, list of causes

Question 228

What is the project manager's responsibility in Project Integration Management?

Options:

A.

Ensuring that requirements-related work is clarified in the project management plan

B.

Investing sufficient effort in acquiring, managing, motivating, and empowering the project team

C.

Combining the results in all other knowledge areas, and overseeing the project as a whole

D.

Developing a strategy to ensure effective stakeholder communication

Question 229

The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?

Options:

A.

Acquire Resources

B.

Control Resources

C.

Manage Team

D.

Develop Team

Question 230

Which set of activities should a project manager use as part of the Develop Team process?

Options:

A.

Training and establishing ground rules

B.

Networking activities and estimating team resources

C.

Conflict management activities and tracking team performance

D.

Recruit new team members and training

Question 231

In order to detect quality Issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches tor Project Quality Management?

Options:

A.

The frequency of the quality and review steps

B.

The number of deliverables

C.

The duration of each of the quality and review steps

D.

The tools used in the quality and review steps

Question 232

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

Options:

A.

Monitor and Control Project Work

B.

Direct and Manage Project Work

C.

Close Project or Phase

D.

Perform Integrated Change Control

Question 233

A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

Options:

A.

Early requirements gathering

B.

Feedback analysis

C.

Progressive elaboration

D.

Requirements documentation

Question 234

What tool should a project manager use to efficiently manage project resources?

Options:

A.

List of project resources

B.

Resource breakdown structure

C.

Resources detailed in the project scope

D.

Resource requirements

Question 235

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

Options:

A.

Predictive

B.

Adaptive

C.

A mix

D.

Agile

Question 236

A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?

Options:

A.

Earned value (EV) / actual cost (AC)

B.

Estimate at completion (EAC) - AC

C.

Budget at completion (BAC) / cost performance index (CPI)

D.

EV - planned value (PV)

Question 237

A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

Options:

A.

Verified deliverables

B.

Validated deliverables

C.

Accepted deliverables

D.

Completed change requests

Question 238

Which is an example of analogous estimating?

Options:

A.

Estimates are created by individuals or groups with specialized knowledge.

B.

Estimates are created by using information about resources of previous similar projects.

C.

Estimates are created by analyzing data.

D.

Estimates are created at the task level and aggregated upwards.

Question 239

A project manager is identifying the risks of a project. Which technique should the project manager use?

Options:

A.

Representations of uncertainty

B.

Prompt lists

C.

Audits

D.

Risk categorization

Question 240

Which of the following documents ate created as part of Project Integration Management?

Options:

A.

Project charter and project management plan

B.

Communications management plan and scope management plan

C.

Quality management plan and risk management plan

D.

Project scope statement and communications management plan

Question 241

The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?

Options:

A.

Monitor Communications

B.

Plan Communications Management

C.

Manage Communications

D.

Manage Stakeholder Engagement

Question 242

Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?

Options:

A.

Develop Schedule

B.

Control Schedule

C.

Estimate Activity Durations

D.

Define Activities

Question 243

What can increase the complexity of the Manage Stakeholder Engagement process?

Options:

A.

The project must be of high quality.

B.

The stakeholders are from different countries.

C.

The project must comply with strict local government regulations.

D.

The project has a tight budget and timeline.

Question 244

Which of the following lists represents the outputs of the Monitor Communications process?

Options:

A.

Project communications, project management plan updates, project documents updates, and organizational process assets updates

B.

Work performance information, change requests, project management plan updates, and project documents updates

C.

Communications management plan, project management plan updates, work performance report, and project documents update

D.

Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Question 245

Stakeholder identification and engagement should begin during what phase of the project?

Options:

A.

After the project management plan is completed

B.

After the stakeholder engagement plan is completed

C.

As soon as the project charter has been approved

D.

After the communications management plan is completed

Question 246

Which of the following Process Groups covers all nine Project Management Knowledge Areas?

Options:

A.

Executing

B.

Monitoring and Controlling

C.

Planning

D.

Initiating

Question 247

When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?

Options:

A.

Authority

B.

Role

C.

Competency

D.

Responsibility

Question 248

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Question 249

Which process determines the risks that might affect the project?

Options:

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Question 250

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.

B.

Baseline Budget.

C.

Control Costs.

D.

Estimate Costs.

Question 251

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.

B.

A customer has approved a change request broadening the project scope and increasing the budget.

C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.

D.

One of the key project team resources has left the team and no replacement is available.

Question 252

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Options:

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Question 253

Which of the following is an output from Control Scope?

Options:

A.

Change requests

B.

Variance analysis

C.

Accepted deliverables

D.

Requirements documentation

Question 254

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Question 255

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

Options:

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Question 256

Which type of estimating is used to improve the accuracy of an activity's duration?

Options:

A.

Analogous

B.

Parametric

C.

Three-point

D.

What-if scenario analysis

Question 257

Which is an input to the Verify Scope process?

Options:

A.

Performance report

B.

Work breakdown structure (WBS)

C.

Requested changes

D.

Project management plan

Question 258

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Question 259

In a weak matrix, the project managers role is:

Options:

A.

part-time

B.

full-time

C.

occasional

D.

unlimited

Question 260

Which cost estimate technique includes contingencies to account for cost uncertainty?

Options:

A.

Vendor bid analysis

B.

Three-point estimates

C.

Parametric estimating

D.

Reserve analysis

Question 261

The progressive detailing of the project management plan is called:

Options:

A.

expert judgment.

B.

rolling wave planning.

C.

work performance information.

D.

specification.

Question 262

In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:

Options:

A.

enterprise environmental factors.

B.

organizational process assets.

C.

project management plan,

D.

project funding requirements.

Question 263

Which of the following is an input to the Direct and Manage Project Execution process?

Options:

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Question 264

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Question 265

Which Process Group contains those processes performed to define a new project?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Question 266

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Question 267

What is a tool to improve team performance?

Options:

A.

Staffing plan

B.

External feedback

C.

Performance reports

D.

Co-location

Question 268

A tool and technique used during the Perform Qualitative Risk Analysis process is:

Options:

A.

risk data quality assessment.

B.

variance and trend analysis.

C.

data gathering and representation techniques.

D.

risk audits.

Question 269

Which is used to solicit proposals from prospective sellers?

Options:

A.

Procurement statement of work

B.

Resource calendars

C.

Procurement document

D.

Independent estimates

Question 270

In Project Cost Management, which input is exclusive to the Determine Budget process?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

Project schedule

D.

Resource calendars

Question 271

Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?

Options:

A.

Requirements traceability matrix

B.

Work breakdown structure (WBS) dictionary

C.

Requirements management plan

D.

Requirements documentation

Question 272

Which of the following is an output of Direct and Manage Project Execution?

Options:

A.

Project management plan

B.

Change request status updates

C.

Organizational process assets updates

D.

Work performance information

Question 273

What is the most accurate rough order of magnitude (ROM)?

Options:

A.

In the Initiation phase, the estimate is in the range of +/- 50%.

B.

In the Planning phase, the estimate is in the range of +/- 50%.

C.

In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.

D.

In the Closing phase, the estimate is in the range of +/- 15%.

Question 274

The process of identifying the stakeholders' information needs is completed during:

Options:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Question 275

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Question 276

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio

B.

Process

C.

Project

D.

Program

Question 277

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Question 278

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Question 279

The project manager needs to review the templates in use. The templates are part of the:

Options:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Question 280

Which of the following is an example of schedule compression?

Options:

A.

Activity sequencing

B.

Resource leveling

C.

Lead and lag adjusting

D.

Crashing

Question 281

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

Options:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

Question 282

A method to manage stakeholder expectations in the scope statement is to clearly:

Options:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Question 283

What does a CPI value greater than 1.0 indicate?

Options:

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

Question 284

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Question 285

In which process might a project manager use risk reassessment as a tool and technique?

Options:

A.

Perform Qualitative Risk Analysis

B.

Monitor and Control Risk

C.

Monitor and Control Project Work

D.

Plan Risk Responses

Question 286

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Question 287

Which of the following statements is true regarding project and product lifecycles?

Options:

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.

Question 288

What causes replanning of the project scope?

Options:

A.

Project document updates

B.

Project scope statement changes

C.

Variance analysis

D.

Change requests

Question 289

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited

B.

Low to moderate

C.

Moderate to high

D.

High to almost total

Question 290

Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

Options:

A.

Teaming

B.

Collective bargaining

C.

Sharing

D.

Working

Question 291

Which standard has interrelationships to other project management disciplines such as program management and portfolio management?

Options:

A.

Program Management Body of Knowledge Guide

B.

The Standard for Program Management

C.

Organizational Project Management Maturity Model (OPM3$)

D.

Guide to the Project Management Body of Knowledge (PMBOKĀ®)

Question 292

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

Options:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Question 293

What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000

Options:

A.

1

B.

0.4

C.

0.5

D.

0.8

Question 294

Testing falls into which of the following categories of cost of quality?

Options:

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Question 295

A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

Options:

A.

To the project management plan.

B.

To the risk register.

C.

In the scope verification processes.

D.

And their impact to the project in terms of time, cost, and risk.

Question 296

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Question 297

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Question 298

When would resource leveling be applied to a schedule model?

Options:

A.

Before constraints have been identified

B.

Before it has been analyzed by the critical path method

C.

After it has been analyzed by the critical path method

D.

After critical activities have been removed from the critical path

Question 299

Work performance information and cost forecasts are outputs of which Project Cost Management process?

Options:

A.

Estimate Costs

B.

Plan Cost Management

C.

Determine Budget

D.

Control Costs

Question 300

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

Options:

A.

Historical information and the lessons-learned database.

B.

Historical information and the stakeholder register.

C.

Organizational process assets and the lessons-learned database.

D.

Project documents and historical information.

Question 301

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Question 302

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

Options:

A.

Crashing

B.

Fast tracking

C.

Leads and lags adjustment

D.

Parallel task development

Question 303

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

Options:

A.

Product

B.

Cost-benefit

C.

Stakeholder

D.

Research

Question 304

Perform Quality Control is accomplished by:

Options:

A.

Identifying quality standards that are relevant to the project and determining how to satisfy them.

B.

Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

C.

Ensuring that the entire project team has been adequately trained in quality assurance processes.

D.

Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

Question 305

Which activity is an input to the Conduct Procurements process?

Options:

A.

Organizational process assets

B.

Resource availability

C.

Perform Integrated Change Control

D.

Team performance assessment

Question 306

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

Options:

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Plan Risk Management

D.

Plan Risk Responses

Question 307

Projects are undertaken by an organization to support the:

Options:

A.

Product performance.

B.

Budget process.

C.

Collective capabilities.

D.

Organizational strategy.

Question 308

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

Options:

A.

Pareto

B.

Ishikawa

C.

Shewhart-Deming

D.

Delphi

Question 309

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Question 310

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Question 311

What is the term assigned to products or services having the same functional use but different technical characteristics?

Options:

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Question 312

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Question 313

What is the number of stakeholders, if the project has 28 potential communication channels?

Options:

A.

7

B.

8

C.

14

D.

16

Question 314

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

Options:

A.

budget at completion (BAC)

B.

earned value management (EVM)

C.

to-complete performance index

D.

cost performance index

Question 315

Portfolio Management is management of:

Options:

A.

a project by dividing the project into more manageable sub-projects.

B.

a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling.

C.

all projects undertaken by a company.

D.

a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives.

Question 316

Conflict should be best addressed in which manner?

Options:

A.

Early, in private, using a direct, collaborative approach

B.

Early, in public, using an indirect, collaborative approach

C.

Early, in private, using an indirect, cooperative approach

D.

As late as possible, in public, using a direct, confrontational approach

Question 317

Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

Options:

A.

Organizational process assets

B.

A work breakdown structure

C.

The project management plan

D.

Enterprise environmental factors

Question 318

When can pre-assignment of project team members occur?

Options:

A.

When the project uses capital expenditures

B.

When the required staff can be acquired from outside sources

C.

When the project would be ignored due to travel expenses

D.

When the project is the result of specific people being promised as part of a competitive proposal

Question 319

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Question 320

Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

Options:

A.

The customer and functional managers

B.

The risk owners and stakeholders

C.

The sponsors and stakeholders

D.

The project management team

Question 321

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

Options:

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

Question 322

What is one of the objectives of Project Risk Management?

Options:

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Question 323

Taking out insurance in relation to risk management is called what?

Options:

A.

Transference

B.

Avoidance

C.

Exploring

D.

Mitigation

Question 324

The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

Options:

A.

start-to-start (SS)

B.

start-to-finish (SF)

C.

finish-to-start (FS)

D.

finish-to-finish (FF)

Question 325

Which of the following processes are part of the Project Integration Management Knowledge Area?

Options:

A.

Develop Project Management Plan, Collect Requirements, Create WBS

B.

Develop Project Management Plan, Control Scope, Develop Schedule

C.

Develop Project Charter, Define Scope, Estimate Costs

D.

Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

Question 326

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Question 327

The individual or group that provides resources and support for a project and is accountable for success is the:

Options:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Question 328

Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

Options:

A.

The influence of the stakeholders increases, the cost of changes increases.

B.

The influence of the stakeholders decreases, the cost of changes increases.

C.

The influence of the stakeholders increases, the cost of changes decreases.

D.

The influence of the stakeholders decreases, the cost of changes decreases.

Question 329

The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

Options:

A.

Push

B.

Pull

C.

Interactive

D.

Iterative

Question 330

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Question 331

Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

Options:

A.

Coaching

B.

Avoidance

C.

Consensus

D.

Influencing

Question 332

When is a project finished?

Options:

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

Question 333

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Question 334

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Question 335

Change requests are an output from which Project Integration Management process?

Options:

A.

Direct and Manage Project Execution

B.

Develop Project Management Plan

C.

Close Project

D.

Develop Project Charter

Question 336

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

Options:

A.

Portfolio

B.

Project

C.

Program

D.

Operations

Question 337

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Question 338

The links between the processes in the Process Groups are often:

Options:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Question 339

Plan Risk Management is the process of defining how to:

Options:

A.

Communicate identified risks to the project stakeholders.

B.

Conduct risk management activities for a project.

C.

Analyze the impact a specific risk may have on the project.

D.

Address unexpected risks that may occur during a project.

Question 340

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Page: 1 / 114
Total 1135 questions