PMI CAPM Certified Associate in Project Management (CAPM) Exam Practice Test
Certified Associate in Project Management (CAPM) Questions and Answers
What is the term assigned to products or services having the same functional use but different technical characteristics?
When is a project finished?
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
What is the difference between the critical path and the critical chain?
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
During which process group is the quality policy determined?
Which activity is an input to the Conduct Procurements process?
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
The process of formalizing acceptance of the completed project deliverables is known as:
Conflict should be best addressed in which manner?
Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?
Which enterprise environmental factors are considered during Estimate Costs?
The project management processes presented in the PMBOK Guide® should:
Which of the following investigates the likelihood that each specific risk will occur?
Outputs of the Control Communications process include:
Which type of analysis would be used for the Plan Quality process?
Which process is included in the Project Integration Management Knowledge Area?
An input of the Plan Procurement Management process is:
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
Which of the following tools or techniques is used for Estimate Activity Durations?
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
To which process is work performance information an input?
Taking out insurance in relation to risk management is called what?
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
What cost control technique is used to compare actual project performance to planned or expected performance?
Most experienced project managers know that:
Who selects the appropriate processes for a project?
Which of the following processes are part of the Project Integration Management Knowledge Area?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
What is the function of a Project Management Office (PMO)?
What type of project structure is a hierarchically organized depiction of the resources by type?
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
Organizations perceive risks as:
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Perform Quality Control is accomplished by:
The stakeholder register is an output of:
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
Information collected on the status of project activities being performed to accomplish the project work is known as what?
Which is an example of Administer Procurements?
Which tools or techniques will a project manager use for Develop Project Team?
Which type of managers do composite organizations involve?
Which action should a project manager take to ensure that the project management plan is effective and current?
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
In an organization with a projectized organizational structure, who controls the project budget?
Which of the following is TRUE about most project life cycles?
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Which tool or technique is used in the Estimate Costs process?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
The process of prioritizing risks for further analysis or action is known as:
Which tool or technique is used in the Develop Project Management Plan process?
An input used in developing the communications management plan is:
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
Which item is an example of personnel assessment?
An output of the Plan Quality Management process is:
Which Process Group and Knowledge Area include the Sequence Activities process?
An input to the Plan Stakeholder Management process is:
Which item is a formal proposal to modify any document, deliverable, or baseline?
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Which tool or technique is used in the Plan Scope Management process?
Sensitivity analysis is typically displayed as a/an:
An input to the Plan Cost Management process is:
An element of the project scope statement is:
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Risk categorization is a tool or technique used in which process?
Identify Risks is part of which Process Group?
A project charter is an output of which Process Group?
An input to Conduct Procurements is:
Inputs to the Plan Schedule Management process include:
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Which Control Quality tool is also known as an arrow diagram?
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?
When does the project team determine which dependencies are discretionary?
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
A tool or technique used in the Control Procurements process is:
An input to Develop Project Charter is a/an:
An input to the Identify Stakeholders process is:
Which process numerically analyzes the effect of identified risks on overall project objectives?
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?
An output of the Create WBS process is:
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
A technique used to determine the cause and degree of difference between baseline and actual performance is:
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
Which tool or technique is used in the Perform Integrated Change Control process?
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which process determines the risks that may affect the project and documents their characteristics?
Which tool or technique is used to manage change requests and the resulting decisions?
The Plan Stakeholder Management process belongs to which Process Group?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
In the Plan Stakeholder Management process, expert judgment is used to:
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?
An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:
The process of defining how the project scope will be validated and controlled is known as:
The purpose of the Project Communications Management Knowledge Area is to:
At the start of a typical project life cycle, costs are:
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
The following is a network diagram for a project.
What is the critical path for the project?
Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:
Which item is a cost of conformance?
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
Power, urgency, and legitimacy are attributes of which stakeholder classification model?
Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?
Requirements documentation will typically contain at least:
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
Which tools or techniques are used during the Close Project or Phase process?
Through whom do project managers accomplish work?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
In project management, a temporary project can be:
Which Process Group includes the Manage Stakeholder Engagement process?
When closing a project or phase, part of the process may require the use of which type of analysis?
Every project creates a unique product, service, or result that may be:
Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
Perform Integrated Change Control is the process of:
Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
Which project risk listed in the table below is most likely to occur?
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
Which output is the approved version of the time-phased project budget?
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
Variance and trend analysis is a tool and technique used in which process?
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6?
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?
Tools and techniques used in Direct and Manage Project Work include:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Completion of the product scope is measured against the product:
In the Define Activities process, the schedule management plan is used to:
An input to the Control Quality process is:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A disadvantage associated with virtual teams is that they:
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
The following is a network diagram for a project.
The free float for Activity H is how many days?
The chart below is an example of a:
The zero duration of milestones in project planning occurs because milestones:
Which tool or technique is required in order to determine the project budget?
An intentional activity to modify a nonconforming product or product component is called:
In complex projects/ initiating processes should be completed:
Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:
Project Scope Management is primarily concerned with:
In which organizational structure would the project manager have most authority?
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
What process is included in Project Schedule Management?
A project team conducts regular standup meetings to keep everyone updated on what each one of them is working on. What type of communication is this?
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?
Why is tailoring required in a project?
What is the project manager's responsibility in Project Integration Management?
A project manager is identifying the risks of a project. Which technique should the project manager use?
In which of the Risk Management processes is the project charter used as an input?
The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?
Which are inputs for the Plan Quality Management process?
The Agile principle "welcome changing requirement, even late in development" relates to which agile manifesto?
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
What tool should a project manager use to efficiently manage project resources?
How can a project manager determine if the project activities comply with organizational and project policies, processes, and procedures?
What is the discipline that focuses on the interdependences between projects to determine the optimal approach for managing them?
A project manager has to share a status report with a new stakeholder and is trying to determine the level of detail to include in the report. Which document best details the information the project manager needs lo make this decision?
Which tool should a project manager consider to deal with multiple sources of risk?
In an agile or adaptive environment. when should risk be monitored and prioritized?
To which knowledge area does the Collect Requirements process belong?
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take into account for risk management in this environment?
Which of the following set of elements is part of an effective communications management plan?
Make-or-buy analysis is a tool and technique of which process?
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
Which contract type is least desirable to a vendor?
A project team is discussing an upcoming planned product launch of a highly visible technologically advanced artificial intelligence tool. The team is debating the aspect of iterative and hybrid approaches. Which aspect of tailoring would this best represent?
Which term refers to the work performed to deliver results with specified features and functions?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
What is an output of the plan resource management process
Which components of the project management plan are inputs used when creating the stakeholder engagement plan?
Which of the following are processes associated with Project Cost Management?
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
What is the best tool to calculate the critical path on a project?
Which of the following can a project manager use to represent dellned team member roles in a group of tasks?
A project reports an earned value (EV) of USS45 for work completed with an actual cost (AC) of US$40. What is the cost performance index (CPI)?
Which is the correct hierarchy in a project environment, from most to least Inclusive?
Which of the following lists represents the outputs of the Monitor Communications process?
Which of the following is an example of facit knowledge?
Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?
What should a project manager use to determine how much money is needed to complete a project?
A sponsor asks a project manager to provide a project's expected total costs based on its progress. What formula should the project manager use to determine this?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
Which of the following are components of the technical project management skill?
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
Which are examples of processes that may be used once or at predefined points in the project life cycle?
A firm contracted an event management company to conduct the annual sales day event. The agreement states that the event management company will charge the firm for the actuals and receive 8% of the total cost. What type of contract Is this?
Directing another person to get from one point to another using a known set of expected behaviors and the ability to lead a team and inspire them to do their jobs well is related to?
Analyzing activity sequences, durations, resource requirements, and schedule constraints for project execution and monitoring and controlling relates to which process?
Which of the following technology platforms is most effective for sharing information when managing virtual project teams?
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
When managing costs in an agile environment, what should a project manager consider?
Project reporting is a tool that is most closely associated with which process?
Which of these is true of project integration management?
Which of the in an adaptive project environment, which action helps the project manager?
Which project documents can determine the budget?
What are the two most common contract types used in a project?
In the last two iterations, a project team failed to deliver all of the stories on time. What should the project manager do first in order to prevent this from recurring?
Which set of tools and techniques is useful for estimating activity durations for the project schedule?
Which tools and techniques should a project manager use when estimating costs?
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?
The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?
Product requirements specify a functionality that depends upon expertise that is unavailable internally. What process should be implemented to generate a make-or-buy decision?
Project managers plan a key role performing integration on the project what are the three different levels of integration?
A program consists of four agile teams. Each team has a separate daily standup. Later each day, there is another standup meeting attended by one member from each team.
Which Scrum technique is this?
Which behavior is a management trait?
What do top project managers do to maximize their sphere of influence within a project team?
A product owner reviews the list of stakeholders to confirm their continued involvement with the product team. A new stakeholder is identified as actively involved in the next product release.
What should the project manager do next to engage the new stakeholder?
Match each tool or technique with its corresponding Project Cost Management process.
A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?
What tern describes an intentional activity to modify a nonconforming product or product component?
Which tools and techniques should a project manager use to monitor risks?
A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI’s Talent Triangle best relates to this need to improve?
A business analyst needs to ensure the project team understands the most critical roles and responsibilities within the requirements change process. Which responsibility is the most important?
What is the recommended approach for handling risk in a high-variability environment?
A stakeholder is reading project documents given by the project manager. The stakeholder is
curious about the difference between a verified deliverable and an accepted deliverable.
Which of the following definitions can the project manager use to explain the difference?
A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team.
What should the project manager do next?
A software development team is pulling work from its backlog to be performed immediately as they become available. What emerging practice for project scheduling is the team using?
What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders'?
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
Which of the following set of items belongs to the communications management plan?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take to account for risk management n this environment’
What internal enterprise environmental factor (EEF) can impact a project?
Select three elements that apply to agile/ adaptive environments
When establishing a contingency reserve, including time, money and resources, how is the risk being handled?
A project's business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?
During project planning, team members seemed clear on deliverables. However, as the project progressed deeper into the execution phase, team members expressed the need for smaller components to better understand what must be delivered.
What should the project manager do?
Calculate the Schedule Performance Index (SPI) based on the following information: earned value (EV) is 30 and planned value (PV) is 15.
What communications management process enables an effective information flow among project stakeholders'?
The activity tailoring is necessary because:
The project manager is leading a construction project that has been ongoing for eight years. The project manager needs to calculate the correct static payback period and consults the cash flow statement of the construction project investment.
What equation should the project manager use?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
During what project management process does the project team begin identifying risks?
What is main purpose of Project Quantity Management?
Agile release planning provides a high-level summary timeline of the release schedule based on.
Which three of the following are the most widely used techniques that a business analyst should implement to gather requirements? (Choose three)
What is an example of an emerging trend in procurement management?
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
A project manager is managing a small project that has a time constraint. What should the project manager do to ensure the delivery is on time?
Which is a major component of an agreement?
Which is a method of prototyping that creates a functioning representation of the final finished product to the user?
Which process is engaged when a project team member makes a change to project budget with project manager's approval
A new game development process must have three versions. Each version is to be developed in approximately five iteration cycles with a duration of one month each. This will help this small enterprise to have a return on investment (ROI) as the project runs from the first cycle. Which methodology should the project manager adopt and implement in the project?
A project manager is working with the project sponsor to identify the resources required for the project. They use a RACI chart to ensure that the team members knows their roles and responsibilities.
What are the four elements of a RACI chart?
Who defines the scope of the product
Among all of the key stakeholders in an agile project, who is responsible for creating project requirements for the team?
Who identifies project requirements in the early phase of the project?
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
When paying a consultation fee to a technical expert, what type of contract is often used'?
A project team has missed a milestone.
Which response strategy should be implemented?
Which of the following tasks is related to the perform qualitative risk analysis process?
Which of the following events would result in a baseline update?
Which of the following types of a dependency determination is used to define the sequence of activities?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following is a tool or technique of the Define Activities process?
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
A method to manage stakeholder expectations in the scope statement is to clearly:
Which is an input to the Verify Scope process?
One of the tools and techniques of the Manage Project Team process is:
Analogous cost estimating relies on which of the following techniques?
What causes replanning of the project scope?
Which is a communication method used in the Report Performance process?
A tool or technique in Perform Quality Control that a project manager would use is:
In a weak matrix, the project managers role is:
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Which process determines the risks that might affect the project?
"Tailoring" is defined as the:
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
Managing procurement relationships and monitoring contract performance are part of which process?
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
The project manager needs to review the templates in use. The templates are part of the:
Which type of estimating is used to improve the accuracy of an activity's duration?
Which of the following statements is true regarding project and product lifecycles?
In which type of organizational structure are staff members grouped by specialty?
Which of the following project documents is an input to the Control Scope process?
Which of the following characteristics are found in a functional organizational structure?
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
Which cost estimate technique includes contingencies to account for cost uncertainty?
What is the most accurate rough order of magnitude (ROM)?
Co-location is a tool and technique of:
Which of the following is an information gathering technique in Identify Risks?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
In Project Cost Management, which input is exclusive to the Determine Budget process?
Which of the following is an input to Control Scope?
Which provides the basic framework for managing a project?
The precedence diagramming method (PDM) is also known as:
Change request status updates are an output of which process?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Labor, materials, equipment, and supplies are examples of:
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Which tool or technique is used in Close Procurements?
Which Process Group contains those processes performed to define a new project?
Which process occurs within the Monitoring and Controlling Process Group?
Tools and techniques used for Plan Communications include the communication:
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
Documented identification of a flaw in a project component together with a recommendation is termed a:
Which of the following correctly explains the term "progressive elaboration'?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
What risk technique is used to quantify the probability and impact of risks on project objectives?
What provides information regarding the ways people, teams, and organizational units behave?
Which of the following reduces the probability of potential consequences of project risk events?
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
Which characteristic do projects and operational work share in common?
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Which of the following documents allows the project manager to assess risks that may require near term action?
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Prototype development may be used as a tool for which of the following risk response strategies?
In the basic communication model, which term refers to the method that is used to convey the message?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Which of the following is an input to Direct and Manage Project Execution?
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
When cost variance is negative and schedule variance is positive, the project is:
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
A project lifecycle is defined as:
What happens to a stakeholder's project influence over time?
Which of the following is a group decision-making technique?
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
Which of the following is an output of the Conduct Procurements process?
Risk responses reflect an organization's perceived balance between:
Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
Funding limit reconciliation is a tool and technique used in which process?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
At the end of the project, what will be the value of SV?
Which of the following are three inputs to the risk register?
The total of the planned value (PV) is also known as:
Administer Procurements is part of which Process Group?
Which baselines make up the performance measurement baseline?
Which of the following is a tool or technique used in the Acquire Project Team process?
Which of the following is a tool and technique used to monitor risk?
What are the identified risks for doing excessive decomposition in a WBS?
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:
The diagram below is an example of a:
Which activity may occur at project or phase closure?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Which process requires implementation of approved changes?
The process of identifying specific actions to be performed to produce project deliverables is:
Which of the following can be used as an input for Define Scope?
Which of the following is an input to the Develop Project Charter process?
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
The probability and impact matrix is primarily used to:
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
The process to ensure that appropriate quality standards and operational definitions are used is:
Which type of dependency is contractually required or inherent in the nature of the work?
Projects are separated into phases or subprojects; these phases include:
A tool and technique used during the Collect Requirements process is:
Which statement correctly describes the value of a business case?
The correct equation for schedule variance (SV) is earned value:
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Which of the following is a tool or technique used in the Determine Budget process?
Which input will be used when tasked with developing the human resource plan?
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
An input to the Collect Requirements process is the:
The staffing management plan is part of the:
Which is an output of the Collect Requirements process?
A close-up of a list Description automatically generated