The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back-to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
"Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted."
What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?
The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:
A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4. However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.
Towards the end of implementing a varied work (initiated originally by the Contractor as a "Value Engineering Proposal", relevant designs provided by the Contractor) it turned out, that there is some part of it not complying with the otherwise prevailing standards. Which statements are correct in this situation? [FIDIC Red Book, 2017 Edition]
Choose all of the correct answers (multiple possibilities).
If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which of the following form a Contractor's entitlement, in case the Contractor does not receive an interim payment within the allocated contractual deadline for payment? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
You are the Contract Manager of the Employer for a Data Centre Project using the FIDIC Yellow Book (edition 2017). As a Contract Manager during the procurement stage, you are to explain the difference between Dispute Avoidance and Adjudication Board (DAAB) and other alternative dispute resolutions for this type of project. Which one of the following statements of its explanation is NOT correct?
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.
Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?
Which of the following documents form part of a FIDIC Construction Contract ["Red Book" (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
What are two differences between a notice and other communications under the FIDIC Red Book (edition 2017)? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer– a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?
You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?
In a construction project using the FIDIC Silver Book (edition 1999), if the Parties prefer the dispute board to be appointed on an "ad-hoc" basis instead of as a standing Dispute Avoidance and Adjudication Board (DAAB), what is it called? (1 correct answer applies)
What does discharge confirm under the FIDIC Red Book (edition 1999)?
The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]
(2 correct answers apply)
Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?
You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".
For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?
In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?