Maintenance needs to be outsourced; management demands a contract option with the lowest risk possible.
Which is the best option to choose?
Failure probability of mechanical equipment components is high, and management wants to keep downtime to an absolute minimum.
Which is the best spare part option to choose?
The data center organization has all its services prepared and wishes to announce the outcome to its customers so that they can place their order.
What document – or information – will it share?
The organization is preparing for business continuity.
Due to the current economic situation, management wants to spend as little money as possible on an alternative facility.
Which option should you propose?
The needs analysis has been completed and the data center organization is tasked with the capability assessment.
Which of the below is a mandatory activity as part of the capability assessment?
Training programs need to be selected.
Of the below, which is the first activity to start with?
A resource matrix is to be created.
What are the main considerations?
During what project phase do you need to start involving the stakeholders?
Which, of the items below, is not part of operational cost (OPEX)?
In document management, what is the objective of the publication process?
Customers of the data center want to know how much of the data center's power comes from renewable sources.
What should the data center service provider do to respond to these requests?
When creating a compliance document register, which categories should at least be included?
When is the right moment to label assets?
To set up a framework for an effective environmental management system, which standard should be followed?
What describes the term predictive maintenance?
Customers complain about support response times being too slow. After a check with the vendor about the agreed SLAs, it is concluded that no violation occurred.
What is the likely cause of the customers complaining?
A recent cooling equipment failure resulted in a sudden shutdown of IT systems. Although the service provider was quickly on-site, it eventually took more than 12 hours for the cooling equipment to be repaired. Management wants to prevent this from happening again.
What is the best response?
Who is accountable for the outcome of a project?