Big Black Friday Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

Construction Specifications Institute CDT Construction Documents Technologist Exam Practice Test

Page: 1 / 12
Total 120 questions

Construction Documents Technologist Questions and Answers

Question 1

When is the owner entitled to stop the work?

Options:

A.

If the architect/engineer fails to represent owner properly

B.

If the contractor fails to correct work that is not compliant with the contract documents

C.

If the contractor is presumed to be bankrupt

D.

If there is a safety problem on the site

Question 2

Which bid form component ensures equal consideration, transparency, and flexibility while awarding a contract, but also manages cost during execution for undefined and unforeseen construction conditions?

Options:

A.

Bid security and substitution

B.

Add and deduct alternatives

C.

Allowances and unit prices

D.

Liquidated damages and combined bids

Question 3

In which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?

Options:

A.

Project Conception phase

B.

Schematic Design phase

C.

Design Development phase

D.

Construction Documents phase

Question 4

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

Options:

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Question 5

Which document directly modifies the requirements of the general conditions?

Options:

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Question 6

When do negotiations take the place of bidding?

Options:

A.

When exact quantities of work cannot be determined.

B.

When a publicly funded project's lowest bid exceeds the budget.

C.

When the contractor has defaulted on insurance premiums.

D.

When the owner and contractor have established a level of trust.

Question 7

Where are the limits of the work of each alternate defined?

Options:

A.

Agreement

B.

Bid Form

C.

Division 01

D.

Sections in Divisions 02–49

Question 8

Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?

Options:

A.

Conformed set

B.

Record set

C.

Change order log

D.

Request for information documents

Question 9

Which of the following statements is correct?

Options:

A.

Contract documents are complementary

B.

Requirement of one of the contract documents may be superseded by others

C.

Specifications take precedence over drawings

D.

The architect/engineer may require the contractor to perform at a higher level than the contract documents require

Question 10

According to standard general conditions, which of the following is true about shop drawings?

Options:

A.

They are contract documents.

B.

They illustrate some portion of the work.

C.

They are reviewed only by the architect/engineer.

D.

They include performance charts, instructions, and brochures.

Question 11

What is a fundamental principle required to provide fairness in a competitive bidding process?

Options:

A.

Bid securities provide protection to all bidders for unfair practices of others.

B.

The bid shopping process provides the most beneficial pricing to the owner.

C.

All bids are prepared based on identical conditions, information, and time constraints.

D.

A minimum of three bids are required to assure sufficient competition.

Question 12

Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?

Options:

A.

Contractor

B.

Material supplier

C.

Owner

D.

Subcontractor

Question 13

Which term or word is appropriate to use in specification text?

Options:

A.

Any

B.

As per

C.

As required

D.

Work

Question 14

Which of the following is a component of the contract documents?

Options:

A.

Procurement requirements

B.

Resource drawings

C.

Shop drawings

D.

Addenda

Question 15

What is the procedure for guarding against defects and deficiencies before and during the execution of the work?

Options:

A.

Quality assurance

B.

Quality control

C.

Quality management

D.

Quality monitoring

Question 16

A drawing set arranged in the following order is an example of what type of drawing organization?

Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection

Options:

A.

Traditional drawing set organization

B.

Uniform Drawing System

C.

AIA CAD Layer Guidelines

D.

BIM Implementation

Question 17

For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?

Options:

A.

Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.

B.

Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.

C.

Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.

D.

Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).

Question 18

Under SectionFormat®, where would the Article "Manufacturers" be found?

Options:

A.

Either Part 1 or Part 2

B.

Part 1 only

C.

Part 2 only

D.

Part 3 only

Question 19

In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?

Options:

A.

Construction documentation

B.

Design

C.

Project conception

D.

Programming

Question 20

Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?

Options:

A.

The contractor begins negotiating agreements with subcontractors.

B.

The owner forwards construction contract agreements to subcontractors.

C.

The contractor and owner issue an amendment indicating the project is in the construction phase.

D.

The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.

Question 21

The emphasis shifts from overall relationships and functions to more technical issues during which design phase?

Options:

A.

Preliminary design

B.

Schematic design

C.

Design development

D.

Construction documents

Question 22

Who has the right to stop the work if hazardous materials are encountered during the construction?

Options:

A.

Architect/engineer

B.

Contractor

C.

Stakeholders

D.

Facility manager

Question 23

Which document obligates the architect/engineer to review submittals during construction administration?

Options:

A.

AIA Document A201, General Conditions of the Contract for Construction

B.

AIA Document B101, Standard Form of Agreement Between Owner and Architect

C.

AIA Document D200, Project Checklist

D.

AIA Document G612, Owners Instructions to the Architect

Question 24

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Question 25

Which construction agreement provision establishes the duration of the work or a specific date when the owner can occupy the project completely or partially for its intended use?

Options:

A.

Cutoff date

B.

Date of commencement of the work

C.

Date of substantial completion

D.

Scope of work

Question 26

Which of the following is LEAST important to log when documenting the decision-making process?

Options:

A.

Date, time, and location of the meeting

B.

List of attendees and who they represent

C.

Length of time each attendee spent speaking

D.

Action items with responsibilities assigned and date to accomplish

Question 27

Who is responsible for planning, maintaining, and supervising construction safety measures and programs?

Options:

A.

Architect/engineer

B.

OSHA

C.

Owner's inspector

D.

Contractor

Question 28

When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?

Options:

A.

The architect/engineer’s projected operating costs

B.

The construction manager’s life cycle analysis

C.

The estimator’s preliminary project description

D.

The facility manager’s historical record of actual costs

Question 29

The three types of commissioning include systems and equipment commissioning, building envelope commissioning, and what other process?

Options:

A.

Mechanical commissioning

B.

Facility commissioning

C.

Process commissioning

D.

Total project commissioning

Question 30

Which of the following statements best describes stakeholder and participant interest in a project?

Options:

A.

Participants have direct interest in the project while stakeholders have indirect interest

B.

Stakeholders have direct interest in the project while participants have indirect interest

C.

Both stakeholders and participants have direct interest in the project

D.

Both stakeholders and participants have indirect interest in the project

Question 31

Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?

Options:

A.

Mobilization meeting

B.

Preconstruction meeting

C.

Prebid meeting

D.

Coordination meeting

Question 32

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Question 33

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Question 34

Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?

Options:

A.

Warranty of title

B.

Implied warranty of merchantability

C.

Purchase warranty

D.

Extended warranty

Question 35

Which of the following is a scaled view?

Options:

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Question 36

Which of the following ensure that all systems work together effectively to meet the overall project performance goals?

Options:

A.

Total project commissioning

B.

Inspection by architect

C.

Safety testing

D.

Field testing

Page: 1 / 12
Total 120 questions