When is the owner entitled to stop the work?
If the architect/engineer fails to represent owner properly
If the contractor fails to correct work that is not compliant with the contract documents
If the contractor is presumed to be bankrupt
If there is a safety problem on the site
CSI exam content aligns closely with the standard general conditions used in the industry (such as AIA A201). Under those conditions, the owner’s right to stop the work typically arises when:
The contractor fails to correct work that is not in accordance with the Contract Documents, or
The contractor persistently fails to carry out the work in accordance with the Contract Documents.
In that situation, after appropriate notice, the owner may order the contractor to stop the work until the cause for such order has been eliminated. This is intended to protect the owner from continued defective or nonconforming work and to force corrective action. That is exactly what Option B describes.
Why the other options are incorrect or incomplete:
A. If the architect/engineer fails to represent owner properlyProblems in the A/E’s services are handled through the owner–A/E agreement, not by stopping the contractor’s work under the construction contract. There is no standard right for the owner to stop construction solely because of a dispute with the A/E.
C. If the contractor is presumed to be bankruptBankruptcy or insolvency is typically addressed under termination or suspension provisions, not strictly the owner’s immediate “stop work” right described in general conditions. A presumption of bankruptcy alone does not automatically trigger the standard “stop work” clause.
D. If there is a safety problem on the siteThe contractor is usually designated as the party primarily responsible for site safety and for stopping unsafe operations. The owner may insist that unsafe conditions be corrected, and might in practice insist work stop, but the formal “owner’s right to stop the work” clause in general conditions is tied to nonconforming work or failure to follow the Contract Documents, not generally to safety administration (which is the contractor’s duty).
Therefore, in the context of CSI-aligned general conditions, the correct answer is B: when the contractor fails to correct work that is not compliant with the contract documents.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – Contract Administration and Owner’s Rights during Construction.
CSI Construction Specifications Practice Guide – discussion of General Conditions and owner/contractor responsibilities.
CSI CDT Body of Knowledge – “General Conditions: Rights and Responsibilities of the Parties.”
Which bid form component ensures equal consideration, transparency, and flexibility while awarding a contract, but also manages cost during execution for undefined and unforeseen construction conditions?
Bid security and substitution
Add and deduct alternatives
Allowances and unit prices
Liquidated damages and combined bids
CSI’s treatment of bidding and pricing mechanisms distinguishes between:
Alternates – for defined variations in scope or quality.
Allowances – for items not fully defined at bid time.
Unit prices – for work where quantities are uncertain or may change.
The question mentions:
Equal consideration and transparency during award
Flexibility while awarding
Managing cost during execution for undefined and unforeseen conditions
This language directly aligns with allowances and unit prices:
Allowances are used when the exact nature or selection of certain items (e.g., finishes, special equipment, or yet-to-be-selected products) is not fully defined at bid time. An allowance amount is stated in the documents so all bidders include the same amount, ensuring comparable bids and transparency. Actual cost is reconciled during construction.
Unit prices are used when work items have uncertain quantities (e.g., rock excavation, unsuitable soil replacement). The unit rate is bid up front, and final payment is based on actual measured quantities, which allows the owner to manage cost fairly during execution when unforeseen conditions arise.
Together, allowances and unit prices (Option C) ensure that:
All bidders base their bids on the same assumptions, supporting equal consideration and fairness.
The contract can adapt to undefined or unforeseen conditions without renegotiating basic pricing structures.
Why the others are not correct:
A. Bid security and substitutionBid security protects the owner if the bidder fails to execute the contract; substitution deals with product changes. These do not primarily address managing costs for undefined or unforeseen conditions nor set flexible price structures like allowances or unit prices.
B. Add and deduct alternativesAlternates provide flexibility in award (selecting add or deduct options), but they deal with defined scope options, not ongoing management of undefined or unforeseen conditions during execution.
D. Liquidated damages and combined bidsLiquidated damages relate to time and schedule risk, not unknown scope or quantities; combined bids are procedural. Neither is the primary mechanism CSI associates with managing cost for undefined/unforeseen work.
Relevant CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – sections on bidding, pricing, alternates, allowances, and unit prices.
CSI Construction Specifications Practice Guide – discussion of Division 01 provisions for allowances and unit prices.
CSI CDT Body of Knowledge – topics on bid forms, pricing mechanisms, and managing unknown quantities.
In which project phase would outline specifications be created in order to be used as a checklist for further development of the project documents?
Project Conception phase
Schematic Design phase
Design Development phase
Construction Documents phase
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s project delivery model, the level of development of specifications increases as the project moves through the design phases:
Project Conception – programming, needs assessment, feasibility; little or no formal specifications.
Schematic Design (SD) – conceptual design, basic systems and relationships; CSI now emphasizes Preliminary Project Descriptions (PPDs) as early, performance-oriented spec tools at this stage.
Design Development (DD) – selection and refinement of specific systems and assemblies; this is where outline specifications or expanded PPDs are used as a structured checklist for developing detailed requirements.
Construction Documents (CD) – full, coordinated section-by-section specifications in MasterFormat order, fully detailed to support bidding and construction.
CSI’s Construction Specifications Practice and CDT materials explain that outline specifications (or expanded PPDs) in the Design Development phase play a key role as a checklist and coordination tool. They:
List major assemblies, systems, and products by specification section.
Identify key performance and quality requirements in a concise format.
Help ensure that nothing is overlooked when moving into full specification writing in the Construction Documents phase.
Support coordination between disciplines (architectural, structural, MEP, etc.) by providing a common list of systems and materials.
Therefore, the phase where “outline specifications are created in order to be used as a checklist for further development of the project documents” is the Design Development phase (Option C).
Why the others are not the best fit:
A. Project Conception phaseAt this early stage, work is focused on needs, scope, feasibility, and budgeting. Specifications are generally not yet developed to the “outline” level; instead, information is more conceptual and programmatic.
B. Schematic Design phaseCSI increasingly promotes Preliminary Project Descriptions (PPDs) during Schematic Design, which are even higher-level and more performance-based than traditional outline specs. While some offices may start outline specs during SD, CSI’s standardized view places the checklist-style outline specifications more firmly in Design Development, when system choices are better defined.
D. Construction Documents phaseBy this phase, specifications are typically developed into full, detailed sections (Part 1–General, Part 2–Products, Part 3–Execution) rather than simple outline checklists. The outline specs or expanded PPDs created earlier in DD have already served their purpose in guiding the development of these full specifications and coordinated drawings.
CSI reference concepts:
CSI Project Delivery Practice Guide – chapters describing the design phases and the evolution from PPDs/outline specifications to full specifications.
CSI Construction Specifications Practice Guide – sections on preliminary specifying, PPDFormat, and the role of outline specifications during the Design Development phase.
The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?
Sheet index
Cover sheet
General notes
Building code summary
In CSI-based drawing organization, the cover sheet (sometimes called the title sheet) is the primary identification sheet of the drawing set. It typically includes:
Project name and project number
Owner’s name
Architect/engineer’s name and logo
Names of key consultants (structural, mechanical, electrical, etc.)
General project data (site address, legal description, gross area, etc.)
A location map or vicinity map
Sometimes a sheet index, code summary, and other global project information
CSI’s guidance for construction documents describes the cover sheet as the place where the project is formally identified and the major parties are listed so that anyone picking up the drawing set immediately knows what project it is, who the participants are, and where the project is located. This is exactly what the question is asking about.
Why the others are not correct in CSI’s sense:
A. Sheet index – A sheet index is usually a list of drawing sheets (by discipline and sheet number) and may be placed on the cover sheet or on a separate index sheet, but it does not normally carry the full set of project identification data, consultant names, and location map by itself.
C. General notes – General notes are used to provide global instructions or clarifications applicable to the drawings (e.g., dimensional conventions, typical construction requirements). They are not the primary location for listing the owner, A/E, consultants, or site location map.
D. Building code summary – A building code summary focuses on code-related data: occupancy classification, construction type, fire-resistance ratings, egress calculations, etc. While it may appear on the cover sheet or nearby sheets, it is not where CSI expects all of the names and general project data to be grouped.
So, per CSI’s standard organization of construction drawings and project manuals, the cover sheet is the correct answer.
Which document directly modifies the requirements of the general conditions?
Division 01, General Requirements
Supplementary Conditions
Agreement
Instructions to Bidders
In the standard organization of the contract documents as taught in CSI’s CDT materials and practice guides, the General Conditions establish the baseline contractual rights, responsibilities, and relationships among the owner, contractor, and architect/engineer (A/E).
CSI explains that whenever there is a need to change or add to the standard provisions of the General Conditions (for example, to address project-specific insurance limits, bonding, liquidated damages, or local legal requirements), those changes are made in the Supplementary Conditions. The Supplementary Conditions are expressly written to modify, delete, or add to the printed General Conditions, and they do so by direct reference to specific articles or paragraphs.
The General Conditions set the standard, overall rules of the contract.
The Supplementary Conditions are the only document whose primary purpose is to modify those General Conditions for the specific project.
Other documents (Agreement, Division 01) must be consistent with the Conditions of the Contract but are not the formal instrument intended to “directly modify” the General Conditions.
Why the other options are not correct:
A. Division 01, General Requirements – Division 01 coordinates administrative and procedural requirements for the work and bridges from the Conditions of the Contract to the technical specifications. It may elaborate how procedures are implemented but it is not the document that directly amends the General Conditions.
C. Agreement – The Agreement (e.g., AIA A101) identifies parties, contract sum, contract time, and incorporates the Conditions, drawings, and specifications by reference. It relies on the General and Supplementary Conditions; it does not systematically edit their language.
D. Instructions to Bidders – These govern the procurement phase only (how to submit bids, qualifications, bid security, etc.) and cease to have effect once the Contract is executed. They do not modify the General Conditions of the construction contract.
CSI’s Project Delivery and Construction Specifications Practice Guides describe this hierarchy and emphasize that Supplementary Conditions are the proper instrument for project-specific modifications to the General Conditions, which makes Option B the correct answer.
When do negotiations take the place of bidding?
When exact quantities of work cannot be determined.
When a publicly funded project's lowest bid exceeds the budget.
When the contractor has defaulted on insurance premiums.
When the owner and contractor have established a level of trust.
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI distinguishes between competitive bidding and negotiated procurement:
Competitive bidding: multiple contractors submit sealed bids based on a complete set of contract documents. Award is usually based primarily on lowest responsive, responsible bid, especially in public work.
Negotiated procurement (negotiated contract): the owner selects one contractor (sometimes a small shortlist) and negotiates price, scope, and terms directly rather than relying on competitive bidding.
CSI notes that negotiated contracts are most often used in the private sector, where owners:
Have ongoing relationships with certain contractors,
Value qualifications, performance history, and trust,
May have complex or fast-track projects where early contractor involvement is desired.
Thus, negotiations typically take the place of bidding when there is a pre-existing relationship and trust between the owner and contractor and the owner chooses to negotiate rather than seek competitive bids. That aligns directly with Option D.
Why the other options are incorrect:
A. When exact quantities of work cannot be determined.When quantities are uncertain, a unit-price contract or allowances may be used, but the contractor may still be selected by competitive bidding. Uncertain quantities do not by themselves require a negotiated contract.
B. When a publicly funded project's lowest bid exceeds the budget.For public work, procurement is usually governed by statute. If bids exceed the budget, the typical actions are rebidding, revising scope, or obtaining additional funding—not simply switching to negotiation with one bidder.
C. When the contractor has defaulted on insurance premiums.Insurance problems are a responsibility/qualification issue, not a reason for negotiation to replace bidding. In fact, such a contractor may be deemed not responsible, and thus ineligible for award.
Key CSI References (titles only):
CSI Project Delivery Practice Guide – sections on Procurement, Competitive Bidding vs. Negotiated Contracts.
CSI Construction Specifications Practice Guide – discussions of procurement methods and contract award.
CSI CDT Body of Knowledge – “Bidding and Negotiation” and “Owner’s Selection of Contractor.”
Where are the limits of the work of each alternate defined?
Agreement
Bid Form
Division 01
Sections in Divisions 02–49
Comprehensive and Detailed Explanation (CSI-aligned, paraphrased)
In CSI’s organization of the Project Manual:
Division 01 – General Requirements coordinates administrative and procedural requirements that apply across the technical sections.
One of the standard Division 01 topics is “Alternates”.
In CSI practice:
The Bid Form provides the spaces for bidders to state the prices for each alternate.
The Agreement may list accepted alternates after award.
The technical sections (Divisions 02–49) describe detailed materials and methods, but do not typically define the overall limits or scope of each alternate in one place.
Instead, CSI recommends that the description of each alternate, including its limits and what parts of the Work are added, deleted, or changed, be clearly defined in Division 01 – General Requirements, usually in a section titled “Alternates”. There, the scope of each alternate is described in a way that can be coordinated with and referenced by the technical sections.
Therefore, the correct answer is:
C. Division 01
Why the other options are not best per CSI practice:
A. Agreement – The Agreement (Contract for Construction) may list which alternates are accepted once the contract is formed, but it does not typically define in detail the limits of each alternate; it relies on the specifications for those definitions.
B. Bid Form – The Bid Form is where prices for alternates are entered. It may briefly name or reference each alternate, but the detailed definition and limits are in Division 01.
D. Sections in Divisions 02–49 – Technical sections contain the work results and may note how an alternate affects them (e.g., “this finish is used only if Alternate 2 is accepted”), but the primary, consolidated description of what each alternate includes/excludes is in the Division 01 Alternates section.
Key CSI-Related Reference Titles (no links):
CSI Construction Specifications Practice Guide – Division 01 General Requirements and Alternates.
CSI Project Delivery Practice Guide – procurement and alternates sections.
CSI CDT Study Materials – organization of the Project Manual and the role of Division 01.
Where should the contractor continuously document changes made in the field due to actual conditions encountered, such as foundation pier depth and the location of concealed internal utilities?
Conformed set
Record set
Change order log
Request for information documents
CSI describes that during the construction phase, the contractor is responsible for maintaining a continuously updated set of record documents (often called record drawings or as-built drawings). These are a marked-up set of the contract drawings (and sometimes specifications) showing actual field conditions, including:
Changes in dimensions or locations of foundations and structural elements (e.g., pier depths).
Exact locations of underground and concealed utilities.
Adjustments made during construction that are not fully captured in formal design revisions.
Any other deviations between the original design intent and the actual constructed work that will affect future maintenance, alterations, or operations.
CSI’s guidance is that these markups are maintained continuously on site by the contractor and then turned over at closeout as part of the project record.
This is exactly what Option B – Record set refers to: a set of documents updated to reflect the actual constructed conditions.
Why the other options are incorrect:
A. Conformed setA conformed set is the contract documents updated by the design professional to incorporate all addenda and certain pre-award changes, forming a clean set for construction. It is not the running field record of what was actually built; it’s a “clean” version of what was contracted, not what was constructed.
C. Change order logThe change order log tracks formal contract modifications (change orders) – values, dates, brief descriptions. It does not typically contain detailed field information such as exact pier depths and utility locations. Those details belong on the record drawings/record set.
D. Request for information documentsRFIs (requests for information) are used for clarifications and questions during construction. While they may trigger changes or clarifications, RFIs are not the place where the contractor maintains the running graphic record of actual field conditions. The results of RFIs that change the work must still be reflected on the record set.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – Construction Phase, “Record Documents / As-Built Drawings.”
CSI Construction Specifications Practice Guide – Division 01 sections on “Project Record Documents” and “Closeout Submittals.”
CDT Body of Knowledge – Construction Phase responsibilities of the contractor and record documentation.
Which of the following statements is correct?
Contract documents are complementary
Requirement of one of the contract documents may be superseded by others
Specifications take precedence over drawings
The architect/engineer may require the contractor to perform at a higher level than the contract documents require
In CSI-based project delivery and typical general conditions (such as those coordinated with CSI practices), contract documents are described as “complementary”. This means the drawings, specifications, and other contract documents are intended to be read together as a unified whole, and requirements shown or stated in one document are binding as if they appeared in all.
CSI’s CDT body of knowledge and practice guides explain that:
The project manual (including the specifications and conditions of the contract) and the drawings together form the contract documents used to describe the work.
These documents are interrelated and mutually supportive; no single document is intended to stand alone.
The concept of “complementary” means that if a requirement is found in any contract document, it applies, unless it has been consciously modified by a change in the contract (e.g., via addenda, change order, or supplementary conditions).
Therefore, statement A. Contract documents are complementary reflects the core CSI teaching on how contract documents function together.
Why the other options are incorrect (from a CSI/CDT perspective):
B. Requirement of one of the contract documents may be superseded by othersCSI teaches that the contract documents should be coordinated, not competing. While modifications can be made through proper instruments (addenda, change orders, supplementary conditions), the baseline rule is not that any document “supersedes” another by default. Instead, the emphasis is on coordination and consistency across the entire set of documents. Precedence is only established where explicitly written into the conditions or supplementary conditions, and even then it is a last resort, not a standard operating principle.
C. Specifications take precedence over drawingsCSI specifically cautions against blanket “order of precedence” clauses (such as “specifications govern over drawings”), because they encourage sloppy coordination and can lead to disputes rather than preventing them. CSI promotes the idea that both drawings and specifications must be coordinated so they do not conflict. While some owners or agencies may include precedence clauses in their own conditions, this is not a CSI best practice and is not the general rule taught in CDT-preparation materials.
D. The architect/engineer may require the contractor to perform at a higher level than the contract documents requireUnder standard contract principles presented in CSI’s practice guides, the architect/engineer (A/E) cannot unilaterally change the contractor’s obligations beyond what the contract documents require, except through properly authorized changes (e.g., change orders) that include appropriate adjustments to cost and/or time if applicable. The A/E administers the contract and interprets the documents but cannot simply demand higher performance than what the contract documents specify without formal change mechanisms.
In summary, the CSI-aligned view is that contract documents are complementary and intended to be interpreted together, which is best represented by Option A.
According to standard general conditions, which of the following is true about shop drawings?
They are contract documents.
They illustrate some portion of the work.
They are reviewed only by the architect/engineer.
They include performance charts, instructions, and brochures.
CSI, in alignment with standard general conditions (such as AIA A201 and EJCDC documents, which CDT relies on), defines submittals as including three primary types:
Shop drawings – Drawings, diagrams, schedules, and other data specifically prepared by the contractor, subcontractors, or suppliers to illustrate how a portion of the work will be fabricated, assembled, or installed.
Product data – Manufacturer’s printed information such as catalog cuts, performance charts, instructions, and brochures.
Samples – Physical examples that illustrate materials or workmanship.
Key points from these definitions:
Shop drawings are not contract documents. They do not change the requirements of the drawings and specifications; instead, they show how the contractor proposes to meet those requirements.
Standard conditions explicitly state that the contract documents are not modified by submittals, even when reviewed by the architect/engineer.
The contractor must review shop drawings first; they are then submitted to the architect/engineer for review for conformance with design intent, but this does not make them contract documents.
Now, compare to the options:
A. They are contract documents.This is explicitly incorrect. Shop drawings are submittals and do not have the status of contract documents.
B. They illustrate some portion of the work.This is the standard CSI-aligned definition: shop drawings are created to illustrate portions of the work (fabrication, installation, layout, connections, etc.). This is correct.
C. They are reviewed only by the architect/engineer.Incorrect. The contractor is required to review and approve shop drawings before submitting them; the architect/engineer then reviews them. Sometimes others (e.g., consultants, certifying authorities) may also review them.
D. They include performance charts, instructions, and brochures.This describes product data, not shop drawings. Product data submittals often are manufacturer literature with performance charts, brochures, and instructions.
Therefore, the correct choice, consistent with CSI definitions and standard general conditions, is Option B – They illustrate some portion of the work.
CSI references (by name only, no links):
CSI Construction Specifications Practice Guide – “Submittals: shop drawings, product data, and samples”
CSI Project Delivery Practice Guide – “Construction Phase – Submittal Procedures and Responsibilities”
What is a fundamental principle required to provide fairness in a competitive bidding process?
Bid securities provide protection to all bidders for unfair practices of others.
The bid shopping process provides the most beneficial pricing to the owner.
All bids are prepared based on identical conditions, information, and time constraints.
A minimum of three bids are required to assure sufficient competition.
CSI’s treatment of procurement and competitive bidding emphasizes that fairness and integrity in competitive bidding depends on one core principle:
All bidders must be provided the same information, at the same time, under the same conditions.
In CDT terminology, this is often expressed as ensuring that all bidders have identical bidding requirements, drawings, specifications, addenda, and time to prepare bids. When this principle is followed:
No bidder has an unfair informational advantage.
Prices are based on the same scope and conditions, allowing an “apples-to-apples” comparison.
The bidding process is considered fair, competitive, and defensible.
That is exactly what Option C states: “All bids are prepared based on identical conditions, information, and time constraints.” This is the fundamental fairness requirement in competitive bidding as taught in CSI’s CDT materials.
Why the other options are not correct in CSI’s framework:
A. Bid securities provide protection to all bidders for unfair practices of others.Bid security (bid bonds, certified checks, etc.) protects primarily the owner, not “all bidders,” against the risk that the selected bidder will refuse to enter into the contract or furnish required bonds. It is about contract assurance, not fairness among bidders.
B. The bid shopping process provides the most beneficial pricing to the owner.“Bid shopping” (where an owner or prime contractor uses one bidder’s price to pressure others into lowering their price after bids are opened) is explicitly recognized by CSI as an unethical and unfair practice. It undermines trust and is contrary to the fairness principle.
D. A minimum of three bids are required to assure sufficient competition.While owners often seek multiple bids, CSI does not define “three bids” as a fundamental fairness requirement. A fair bidding process could, in principle, have fewer bidders; the key is that each bidder is treated equally and given identical information and conditions.
Thus, in CSI’s description of competitive bidding, Option C captures the central fairness principle.
Under a single prime contract, shop drawings should be routed to the architect/engineer from whom?
Contractor
Material supplier
Owner
Subcontractor
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI-aligned contract administration procedures and the AIA A201 General Conditions, under a single prime contract:
All subcontractors, suppliers, and lower-tier entities submit their shop drawings, product data, and samples to the Contractor.
The Contractor reviews them for coordination, compliance with the contract documents, and completeness.
After the Contractor’s review and approval, the shop drawings are forwarded to the Architect/Engineer (A/E) for review and action.
This maintains the single point of responsibility between the Owner and the Contractor and ensures the Contractor coordinates all submittals before they reach the A/E. Therefore, under a single prime contract, shop drawings should reach the A/E from the Contractor, making Option A correct.
Why the other options are incorrect:
B. Material supplier and D. Subcontractor – They prepare many of the shop drawings but are required to submit them through the prime Contractor, not directly to the A/E. Direct submission would bypass the Contractor’s coordination and contractual responsibility.
C. Owner – The Owner is not part of the technical submittal review chain; they rely on the A/E and Contractor to manage shop drawings.
Relevant CSI references:
CSI Project Delivery Practice Guide – sections on submittal procedures and lines of communication.
CSI Construction Specifications Practice Guide – Division 01 provisions for submittals and routing.
AIA A201 General Conditions (referenced in CSI CDT materials) – Articles on submittals and contractor responsibilities.
Which term or word is appropriate to use in specification text?
Any
As per
As required
Work
CSI’s Construction Specifications Practice Guide and CDT materials provide clear guidance on appropriate wording in specifications. They stress:
Use clear, specific, and enforceable language.
Avoid vague, subjective, or nontechnical terms that create ambiguity and open interpretation.
Among the answer choices, “Work” is the only word that is appropriate and standard in CSI-compliant specification text:
“Work” is a defined term in the General Conditions (and often Division 01), usually meaning the total construction and services required by the Contract Documents, including all labor, materials, equipment, and services necessary to complete the project.
Because it is defined and used consistently, “Work” is an acceptable and precise term for specification language. Example usage (conceptually): “Perform all Work in accordance with…”.
Why the other terms are inappropriate per CSI guidance:
A. AnyCSI recommends avoiding “any,” “either,” “etc.” and similar words because they are non-specific and create ambiguity. For example, “provide any fasteners as needed” does not clearly define what is required and can lead to disputes and inconsistent interpretation.
B. As perThe phrase “as per” is discouraged in CSI-style writing. It is considered informal and can be replaced by clearer, more direct phrasing such as “in accordance with,” “according to,” or “as indicated in.” CSI advocates for concise, plain, and unambiguous English in specs.
C. As requiredCSI strongly cautions against phrases like “as required” or “as necessary” when they are not tied to a clear condition or reference. They shift the decision to someone’s judgment later, instead of stating the requirement explicitly. If something is required, the specification should state what, when, and under what conditions, rather than simply saying “as required.”
Therefore, in a CSI-compliant specification, the term that is clearly appropriate from the options given is “Work” (Option D).
Relevant CSI references (no URLs):
CSI Construction Specifications Practice Guide – Chapters on language and writing style for specifications (clear, concise, complete, correct).
CSI Practice Guide for Principles & Formats of Specifications – Guidance on defined terms such as “Work.”
CSI CDT Body of Knowledge – Sections on specification-writing best practices and prohibited vague phrases.
Which of the following is a component of the contract documents?
Procurement requirements
Resource drawings
Shop drawings
Addenda
CSI defines the contract documents as the documents that form the legally binding contract between the owner and the contractor. These typically include:
Agreement (contract form)
Conditions of the Contract (General and Supplementary)
Drawings
Specifications
Addenda (issued before contract execution, modifying bidding documents)
Modifications (issued after execution — change orders, CCDs, etc.)
Thus, addenda, once issued prior to contract signing, become a binding part of the contract documents.
Why others are incorrect:
A. Procurement requirements – These include instructions to bidders, bid forms, and similar pre-contract information; once the contract is executed, they are not part of the contract documents.
B. Resource drawings – Background reference materials only; not contractually binding.
C. Shop drawings – Prepared by the contractor/subcontractors for review and coordination; not part of the contract documents, even after A/E review.
CSI Reference:
CSI Project Delivery Practice Guide, “Procurement and Contracting”; Construction Specifications Practice Guide, “Definition of Contract Documents.”
What is the procedure for guarding against defects and deficiencies before and during the execution of the work?
Quality assurance
Quality control
Quality management
Quality monitoring
CSI distinguishes clearly between quality assurance (QA) and quality control (QC):
Quality assurance focuses on procedures, planning, and processes established before and during the work to prevent defects and deficiencies. It’s proactive and process-oriented—things like qualifications, mock-ups, preinstallation conferences, submittal review, and establishing methods.
Quality control focuses on inspection, tests, and verification of completed or in-progress work to identify defects and verify that requirements are met. It is more reactive and product-oriented.
The question asks for the procedure for guarding against defects and deficiencies before and during execution of the work, which clearly points to quality assurance—the preventive system of checks and requirements set up in advance and applied as the work proceeds.
Therefore, Option A – Quality assurance is correct.
Why the other options are not correct:
B. Quality control – QC is about testing and inspection of the finished or in-progress work to detect defects, not primarily about guarding against them through advance procedures.
C. Quality management – This is an overarching concept that can include both QA and QC but is not the specific procedural term CSI uses in the documents and Division 01 sections.
D. Quality monitoring – Not a standard CSI technical term in the same formal sense as quality assurance and quality control.
Key CSI-Oriented References (titles only, no links):
CSI Construction Specifications Practice Guide – sections on “Quality Requirements” and the distinction between QA and QC.
CSI Project Delivery Practice Guide – Design and Construction Phase quality processes.
CSI CDT Body of Knowledge – “Quality Requirements in Division 01 and Technical Sections.”
A drawing set arranged in the following order is an example of what type of drawing organization?
Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection
Traditional drawing set organization
Uniform Drawing System
AIA CAD Layer Guidelines
BIM Implementation
CSI, together with other organizations, developed the Uniform Drawing System (UDS) as part of the National CAD Standard. The UDS provides:
Standard sheet identification and discipline designations
A recommended order for drawing disciplines within a set of contract documents
Consistent organization to help all project participants find information efficiently
The UDS discipline order groups drawings by discipline in a typical sequence, for example:
General (G) – often includes Cover Sheet, Sheet Index, Life Safety
Civil (C)
Landscape (L)
Architectural (A)
Interiors (I)
Structural (S)
Mechanical (M)
Electrical (E)
Plumbing (P)
Fire Protection (FP)(and additional disciplines as needed)
The order given in the question:
Cover Sheet, Sheet Index, Life Safety, Demolition, Civil, Landscaping, Architectural, Interiors, Structural, Mechanical, Electrical, Plumbing, Fire Protection
matches the intent of the Uniform Drawing System discipline grouping and ordering:
The initial items (Cover Sheet, Sheet Index, Life Safety, Demolition) fit within the General / Architectural front sections.
Then the disciplines follow in a sequence consistent with UDS recommendations: Civil → Landscape → Architectural → Interiors → Structural → Mechanical → Electrical → Plumbing → Fire Protection.
Therefore, this is an example of UDS-based drawing set organization, which corresponds to Option B – Uniform Drawing System.
Why the other options are incorrect:
A. Traditional drawing set organization“Traditional” is vague and not a CSI-standardized system. The sequence in the question clearly follows a recognized CSI / NCS discipline order, not just an informal tradition.
C. AIA CAD Layer GuidelinesThe AIA CAD Layer Guidelines address layer naming conventions in CAD files, not the order of sheets in a printed / published drawing set.
D. BIM ImplementationBIM is about digital building information models and processes. It does not by itself define a sheet order; the sheet organization is still typically based on CSI / UDS discipline sequence, even on BIM projects.
Relevant CSI / CDT References (titles only, no links):
CSI / National CAD Standard – Uniform Drawing System (UDS) documentation on discipline designators and sheet ordering.
CSI Project Delivery Practice Guide – discussions of drawing organization and coordination with specifications.
mentation
Answer: A
For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?
Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.
Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.
Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.
Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).
CSI’s project delivery and ethical guidance (as reflected in CDT materials and standard practice) emphasize:
Known information that may affect cost, risk, or safety must be disclosed consistently and fairly to all bidders.
The design professional must act in a manner that is honest, transparent, and protective of public safety, even when data is incomplete.
The bid documents should not conceal information that could materially affect the work, even if its full extent is uncertain.
Applying those principles:
The design team has evidence (one contaminated boring) that contamination may exist onsite. Even if the extent is unknown, that fact is potentially material to bidders (cost of remediation, handling of contaminated soils, schedule impacts).
The best course is to disclose what is known and ensure all bidders have access to the same geotechnical information. This is exactly what Option B proposes:
Place a clear note or disclaimer in the contract documents stating that contaminants were encountered in at least one boring and may be present elsewhere.
Recommend that the owner make the geotechnical report available to all bidders, so every bidder can evaluate the risk and price accordingly.
Why the other options are inconsistent with CSI-aligned practice:
A. Withhold the information… – Concealing known contamination is unethical and undermines fair bidding. Even with unit prices for remediation, bidders would be pricing blindly without knowing that contamination has already been detected.
C. Insist the owner undertake additional investigation… – While the design team should recommend further investigation, it cannot “insist” beyond professional advice, especially where the owner has clearly stated financial constraints. Regardless, disclosure of existing data is still required.
D. Proceed with design as is… – Ignoring known contamination and calling it “statistically insignificant” is not defensible; even one contaminated boring is important information that must be shared.
So, the most appropriate and CSI-consistent choice is Option B: disclose the potential and share the geotechnical report so all bidders are equally informed.
CSI references (by name only, no links):
CSI Project Delivery Practice Guide – sections on procurement, fair competition, and disclosure of information
CDT ethics and professional conduct principles regarding risk disclosure to bidders
Under SectionFormat®, where would the Article "Manufacturers" be found?
Either Part 1 or Part 2
Part 1 only
Part 2 only
Part 3 only
CSI’s SectionFormat® establishes a standard three-part structure for specification sections:
Part 1 – GeneralAdministrative and procedural requirements specific to that section (scope, related work, references, submittals, quality assurance, delivery/storage, warranties, etc.).
Part 2 – ProductsDescriptions of products, materials, and equipment required: manufacturers, materials, components, fabrication, finishes, performance requirements, and similar.
Part 3 – ExecutionField/application/installation requirements: examination, preparation, installation/application procedures, tolerances, field quality control, adjustment, cleaning, protection, etc.
Within this structure, CSI specifically places “Manufacturers” as an article in Part 2 – Products. This is because Part 2 is where the specifier identifies:
Acceptable manufacturers or manufacturer list
Standard products and models
Performance or quality requirements associated with those manufacturers
Product substitutions (if addressed by article structure)
Placing “Manufacturers” in Part 2 maintains consistency across specs and makes it clear that manufacturer-related information is part of the product requirements, not administrative conditions or execution procedures.
Why the other options do not align with SectionFormat®:
A. Either Part 1 or Part 2Although some poorly structured sections in practice may misplace content, CSI’s recommended SectionFormat® is explicit: manufacturers belong in Part 2 – Products. Allowing Part 1 or Part 2 would blur the distinction between administrative requirements and product requirements.
B. Part 1 onlyPart 1 is not intended for listing manufacturers. It covers general/administrative topics, not the specific products or manufacturers.
D. Part 3 onlyPart 3 deals with execution/installation in the field, not who manufactures the products. Manufacturer listing in Part 3 would conflict with CSI’s structure and make the section harder to interpret and coordinate.
Therefore, under SectionFormat®, the correct location for the “Manufacturers” article is Part 2 only (Option C).
Key CSI References (titles only, no links):
CSI SectionFormat® and PageFormat™ (official CSI format document).
CSI Construction Specifications Practice Guide – chapters explaining the three-part section structure and where to place specific articles such as “Manufacturers.”
CSI MasterFormat®/SectionFormat® training materials used for CDT preparation.
In what project stage does the architect/engineer obtain and document the owner's decisions about specific products and systems?
Construction documentation
Design
Project conception
Programming
Within CSI’s project delivery framework, the Design stage (which includes schematic design and design development) is where the architect/engineer (A/E) works with the owner to evaluate options, select specific systems, and record decisions that will later be fully detailed in the construction documents.
CSI’s project-phase descriptions (as presented in the CSI Project Delivery Practice Guide and CDT study materials) explain the stages roughly as follows (paraphrased, not verbatim):
Project Conception: The owner defines a need or opportunity, explores whether a project is warranted, and considers general feasibility. The focus is on defining the reason for the project, not picking specific products or systems.
Programming: The owner’s requirements and objectives are documented—space needs, performance criteria, budget, schedule, and qualitative expectations. At this point, needs and performance requirements for systems (e.g., “energy-efficient HVAC,” “durable flooring”) are identified, but not necessarily specific named products or system configurations.
Design:
Schematic Design: General design concepts, overall configuration, and preliminary system approaches are developed; the owner begins making more concrete decisions.
Design Development: The A/E and consultants refine and confirm decisions about specific systems, materials, and assemblies, and these decisions are documented so they can be incorporated into specifications and drawings.
Construction Documents: The A/E takes those already-made decisions and fully documents them in coordinated drawings and specifications, but this phase is not usually where the majority of decisions about which specific products and systems to use are first obtained; instead, it formalizes and details what was already decided in Design.
CSI’s CDT content emphasizes that during Design Development, the A/E “confirms and documents owner decisions about materials, products, and systems” so that these can be translated into clear contract documents during the Construction Documents phase. That activity—obtaining and documenting the owner’s decisions about specific products and systems—is core to the Design stage, making Option B correct.
Why the other options are not correct under CSI’s framework:
A. Construction documentationIn the Construction Documents phase, the A/E develops the detailed drawings and specifications based on decisions made earlier. Changes and additional decisions can occur here, but CSI treats the primary “obtaining and documenting owner choices” as a Design-stage responsibility; the CD phase is about formalizing and coordinating them into contract documents.
C. Project conceptionAt conception, there often isn’t an A/E contracted yet, and the owner is still deciding whether to proceed at all. Product and system decisions would be far too early and poorly defined at this point.
D. ProgrammingProgramming focuses on what the facility must do, not on exactly how via specific products or named systems. It defines performance and functional requirements (e.g., acoustical needs, energy performance) but typically stops short of selecting specific manufacturers or detailed system configurations.
Key CSI-aligned references (no links):
CSI Project Delivery Practice Guide – chapters on project phases (Programming, Design, Construction Documents) and owner/A/E responsibilities.
CSI CDT Body of Knowledge – sections on the Design phase and decision-making responsibilities for products and systems.
Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?
The contractor begins negotiating agreements with subcontractors.
The owner forwards construction contract agreements to subcontractors.
The contractor and owner issue an amendment indicating the project is in the construction phase.
The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In Design-Bid-Build (DBB), CSI describes a clear, linear sequence of phases:
Programming and design
Procurement (bidding/negotiation and selection of contractor)
Award of the construction contract
Construction
At the end of the procurement phase, the owner has received and evaluated bids, determined the successful bidder, and is ready to award the contract. CSI’s project delivery guidance explains that the award step typically involves:
Issuing a Notice of Award or letter of intent to the successful bidder; and/or
Forwarding the owner–contractor agreement (and other contract forms) for execution.
Only after this step do the parties fully execute the contract and the owner issues a Notice to Proceed, marking the official start of the construction phase. This matches Option D:
The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.
Why the other options are incorrect:
A. The contractor begins negotiating agreements with subcontractors.Subcontractor negotiations and subcontracts typically occur after the contractor has been formally awarded and has a binding contract with the owner. This is not the immediate step that awards the contract for construction.
B. The owner forwards construction contract agreements to subcontractors.The owner’s contract is with the prime contractor, not with subcontractors. Subcontracts are between the prime contractor and subcontractors. The owner does not award contracts directly to subs in standard DBB.
C. The contractor and owner issue an amendment indicating the project is in the construction phase.There is normally no “amendment” to enter the construction phase. The project enters the construction phase upon execution of the owner–contractor agreement and issuance of the Notice to Proceed, not by amendment.
Key CSI References (titles only):
CSI Project Delivery Practice Guide – chapters on Design-Bid-Build and the Procurement and Contract Award processes.
CSI Construction Specifications Practice Guide – discussions on contract formation and Notice of Award/Notice to Proceed.
CSI CDT Body of Knowledge – “Project Delivery Methods” and “Procurement and Award of Contract.”
The emphasis shifts from overall relationships and functions to more technical issues during which design phase?
Preliminary design
Schematic design
Design development
Construction documents
In CSI’s project delivery / design-phase framework, the design development (DD) phase is where the emphasis shifts from big-picture concepts to more detailed, technical decisions:
Earlier phases like schematic design focus on overall relationships, general size, massing, and functions of spaces and systems.
Once the project enters design development, the team refines those schematic decisions into more precise technical solutions, coordinating architectural, structural, mechanical, electrical, and other systems, and beginning to define materials, systems, and outline specifications.
By the construction documents phase, the design is largely established and the emphasis is on fully detailing and documenting the agreed technical decisions for pricing, permitting, and construction.
CSI’s practice guides describe DD as the phase in which design decisions are “developed and refined” and more technical information is incorporated, bridging from conceptual/schematic level to the level needed to create final construction documents. That wording corresponds directly to “the emphasis shifts from overall relationships and functions to more technical issues,” which is why Design development (C) is correct.
A. Preliminary design – Not a standard CSI primary phase label; in many frameworks this term is used informally or overlaps with early conceptual planning, where the focus is still on overall functional relationships, not detailed technical issues.
B. Schematic design – Focuses on general arrangement, shape, and relationships of spaces and systems, not yet at the more detailed technical decision level.
D. Construction documents – This phase emphasizes complete, coordinated, enforceable documentation (finalizing drawings and specs), not the initial shift from conceptual to technical; that shift has already occurred in design development.
CSI-aligned references (no external links):
CSI Project Delivery Practice Guide – chapters on Schematic Design, Design Development, and Construction Documents phases.
CSI Construction Specifications Practice Guide – overview of how design phases relate to the development of specifications.
CSI CDT Exam Study/Practice materials – sections describing the purpose and focus of each design phase.
Who has the right to stop the work if hazardous materials are encountered during the construction?
Architect/engineer
Contractor
Stakeholders
Facility manager
Under standard conditions of the contract used in CDT (e.g., AIA A201 as referenced by CSI), when hazardous materials or unsafe conditions are encountered:
The Contractor is required to stop work in the affected area and notify the Owner and Architect/Engineer.
The Contractor must not proceed until the hazardous condition has been evaluated and remedied by the Owner with qualified professionals.
CSI’s project delivery materials emphasize that the contractor is responsible for means, methods, and safety of construction operations. That includes the authority—indeed the obligation—to stop work where hazardous substances or conditions present an imminent danger to workers.
Why the others are incorrect:
A. Architect/engineer – The A/E can recommend suspension of work for nonconforming work or other reasons, but the specific duty and right to stop work because of hazardous conditions in the field lies with the Contractor under typical general conditions.
C. Stakeholders – This is a generic term, not a contract party with defined authority in CSI’s framework.
D. Facility manager – The facility manager may be involved if the existing facility is affected, but is not the contract party empowered in the construction contract to stop the contractor’s work.
Relevant CSI references (no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase responsibilities and safety.
CSI CDT Body of Knowledge – discussion of contractor responsibilities and hazardous materials clauses in standard general conditions.
Which document obligates the architect/engineer to review submittals during construction administration?
AIA Document A201, General Conditions of the Contract for Construction
AIA Document B101, Standard Form of Agreement Between Owner and Architect
AIA Document D200, Project Checklist
AIA Document G612, Owners Instructions to the Architect
In CSI/CDT study materials, a key concept is that each party’s legal obligations come from their own agreement:
The owner–contractor relationship is defined in the Owner–Contractor Agreement and its General Conditions (commonly AIA A201).
The owner–architect relationship is defined in the Owner–Architect Agreement (commonly AIA B101).
The architect’s duty to provide construction administration services, including reviewing submittals, is a service owed to the owner and is therefore set out in the Owner–Architect Agreement, not the General Conditions.
In AIA’s standard structure (which CSI uses extensively in CDT):
AIA B101 (Owner–Architect Agreement) lists the architect’s basic services, including:
Construction Phase Services
Review of submittals (shop drawings, product data, samples, etc.)This is what legally obligates the architect to review submittals as part of their contracted services to the owner.
AIA A201 (General Conditions) describes the architect’s role in the context of the construction contract between owner and contractor (e.g., the architect will review submittals in accordance with the Contract Documents), but the architect’s obligation itself arises from B101, which is the contract between owner and architect.
Therefore, the document that actually obligates the architect/engineer (A/E) to perform submittal review as part of construction administration is AIA Document B101 → Option B.
Why the other options are incorrect:
A. AIA Document A201, General Conditions of the Contract for ConstructionA201 is part of the Owner–Contractor contract. It establishes procedures and the architect’s function with respect to the contractor, but it does not itself create the architect’s contractual obligation to the owner; that comes from B101. A201 can describe what the architect will do “as provided in the Owner–Architect Agreement,” but the promise from the architect is in B101.
C. AIA Document D200, Project ChecklistD200 is a non-contractual guide/checklist used for planning and scoping services. It is an aid, not a contract, and does not bind the architect to perform submittal review.
D. AIA Document G612, Owners Instructions to the ArchitectG612 is also a form tool, used for gathering owner’s instructions and information; it is not itself the agreement that defines the architect’s scope of services and obligations.
CSI / CDT-aligned references (no links):
CSI Project Delivery Practice Guide – discussions of standard AIA documents and how responsibilities are allocated between owner, architect, and contractor.
CSI Construction Specifications Practice Guide – sections on relationships between A201 and B101.
CDT Exam references to AIA A201 – General Conditions and AIA B101 – Owner–Architect Agreement in the “Agreements & Conditions of the Contract” domain.
Which of the following is a component of project design team coordination during the construction documents phase?
Duplication of important information by each discipline
Ensuring drawing note terminology is differentiated from specification terminology
Requiring the owner to hire a third-party to write the Division 01 specifications independently
Quality assurance tasks shared between design and consulting teams
During the construction documents phase, CSI’s guidance emphasizes that coordination between the architect/engineer (A/E) and the various consulting disciplines (structural, mechanical, electrical, etc.) is essential to produce consistent, coordinated, and complete contract documents (drawings, specifications, and project manual). Part of that coordination is a shared quality assurance (QA) effort among the design team members.
In CSI’s practice guides and CDT body of knowledge, the following principles are stressed (paraphrased to respect copyright):
The prime design professional is responsible for overall coordination of the construction documents, but each consultant is responsible for the technical accuracy and coordination of their own portions.
Coordination includes review of cross-references, matching terminology, alignment of requirements between drawings and specifications, and resolving conflicts before bid/issue.
Quality assurance during this phase is not done in isolation; it is a team activity. Consultants and the lead design firm review each other’s work where it interfaces (e.g., architectural and mechanical coordination of ceilings and diffusers; structural and architectural coordination of openings, etc.).
Therefore, “Quality assurance tasks shared between design and consulting teams” (Option D) correctly describes a standard component of project design team coordination during the construction documents phase.
Why the other options are incorrect:
A. Duplication of important information by each disciplineCSI stresses “say it once, in the right place” as a fundamental principle. Information should not be unnecessarily duplicated because duplication increases the risk of conflict and inconsistency (for example, a requirement shown in both drawings and multiple spec sections but updated in only one location). Coordination aims to avoid duplication, not to promote it.
B. Ensuring drawing note terminology is differentiated from specification terminologyCSI emphasizes consistent terminology across drawings, specifications, and other documents. The same items (e.g., “gypsum board,” “reinforcing steel,” “membrane roofing”) should be described using the same terms in both drawings and specifications to reduce ambiguity. Coordination meetings often include checking that terminology is aligned, not intentionally differentiated.
C. Requiring the owner to hire a third-party to write the Division 01 specifications independentlyDivision 01 – General Requirements – is typically prepared or controlled by the lead design professional or specifier, in coordination with the owner. CSI materials do not identify it as a standard or required coordination practice for the owner to hire an independent third party to write Division 01 separately from the design team. That may occur on some projects, but it is not a defined component of team coordination in CSI’s CDT framework.
In summary, CSI-based construction documentation practice defines coordination during the construction documents phase as a shared responsibility among the architect/engineer and all consultants, including joint quality assurance reviews, consistency checks, and cross-discipline coordination. This aligns directly with Option D.
Key CSI References (no links):
CSI Project Delivery Practice Guide – chapters on Design Phase and Construction Documents coordination.
CSI Construction Specifications Practice Guide – sections on coordination between drawings and specifications and the role of Division 01.
CSI CDT Body of Knowledge – topics on roles and responsibilities of the design team and coordination of construction documents.
Which construction agreement provision establishes the duration of the work or a specific date when the owner can occupy the project completely or partially for its intended use?
Cutoff date
Date of commencement of the work
Date of substantial completion
Scope of work
CSI and the AIA A201–style general conditions define Substantial Completion as the stage in the progress of the work when the project (or a designated portion) is sufficiently complete in accordance with the contract documents so that the Owner can occupy or use it for its intended purpose.
In the typical Owner–Contractor Agreement, a clause or article states either:
A calendar date for substantial completion, or
A number of days from the date of commencement by which substantial completion must be achieved.
This is what establishes the duration of the work and the key date when the Owner can begin using the facility. Therefore, Option C – Date of substantial completion – correctly identifies the provision that defines the duration and occupancy milestone.
Why the others are incorrect:
A. Cutoff date – Not a standard CSI/AIA contract term.
B. Date of commencement of the work – This identifies the start, not the required completion/occupancy point.
D. Scope of work – Describes what is to be built, not when it must be complete or ready for use.
Relevant CSI references (no links):
CSI Project Delivery Practice Guide – sections on contract time, substantial completion, and final completion.
CSI CDT Study Materials – definitions of substantial completion, correction period, and related milestones.
Which of the following is LEAST important to log when documenting the decision-making process?
Date, time, and location of the meeting
List of attendees and who they represent
Length of time each attendee spent speaking
Action items with responsibilities assigned and date to accomplish
Good documentation of project decisions (typically in meeting minutes) is essential for traceability, accountability, and later dispute avoidance. CSI-oriented project management procedures and your uploaded construction management documents emphasize that minutes should record, at a minimum:
When the meeting occurred – date, time, location.
Who attended and whom they represent (owner, A/E, contractor, etc.).
What was decided and what remains unresolved.
Action items, assigned responsibilities, and due dates.
These elements are repeatedly included in the sample agendas and minutes procedures in your Construction Management Plan and Project Management Manual, which require minutes and action/open-items lists to be prepared and circulated after key meetings.
None of these procedures mention, or require, tracking how long each attendee spoke. That level of granularity does not contribute meaningfully to documenting decisions, responsibilities, or follow-up work. It adds administrative burden without improving clarity or accountability.
Thus:
A (date/time/location) – important context for the record.
B (attendees and representation) – critical to know who agreed to what.
D (action items, responsibilities, dates) – central to the decision-making trail.
C (length of time each attendee spoke) – least important and not standard practice in CSI-based documentation.
So the correct answer is Option C.
CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – sections on project meetings and documentation.
CSI CDT body of knowledge – “Documenting decisions and maintaining project records.”
Who is responsible for planning, maintaining, and supervising construction safety measures and programs?
Architect/engineer
OSHA
Owner's inspector
Contractor
Under CSI-based contract administration principles (which align with typical General Conditions such as AIA A201), site safety is primarily the responsibility of the Contractor. The Contractor:
Is solely responsible for construction means, methods, techniques, sequences, and procedures.
Must plan, maintain, and supervise all construction safety programs and precautions in connection with the work.
Must ensure that workers and the public are protected from hazards arising from construction operations.
The architect/engineer (A/E) is not responsible for construction safety; their role is limited to observing the work for general conformance with the contract documents, not directing means, methods, or safety programs. Likewise, OSHA sets safety regulations but does not manage project-specific safety programs; compliance and implementation rest with the Contractor.
Therefore, Option D – Contractor is correct.
Why the other options are incorrect:
A. Architect/engineer – The A/E does not control means and methods or safety programs; CSI and standard General Conditions explicitly state that the A/E’s services do not include responsibility for jobsite safety.
B. OSHA – OSHA establishes regulations and enforcement, but it does not plan or supervise each project’s safety measures; that duty is contractually on the Contractor.
C. Owner’s inspector – An owner’s representative/inspector may observe and report, but does not take over the Contractor’s legal responsibility for implementing and supervising safety.
Key CSI-Oriented References (titles only, no links):
CSI Project Delivery Practice Guide – sections on Roles and Responsibilities during Construction.
CSI Construction Specifications Practice Guide – discussion of General Conditions and contractor responsibilities.
CSI CDT Body of Knowledge – “Construction Phase: Responsibilities of Owner, Contractor, and A/E.”
When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?
The architect/engineer’s projected operating costs
The construction manager’s life cycle analysis
The estimator’s preliminary project description
The facility manager’s historical record of actual costs
CSI’s project-delivery and facility-management perspective emphasizes that O&M budgeting should be grounded in real, documented performance and cost history wherever possible. The facility manager is the team member who typically maintains:
Utility bills
Maintenance contracts and work orders
Repair and replacement histories
Staff, labor, and consumables costs
These form a historical record of actual O&M costs, which provides the most reliable basis for forecasting future O&M budgets.
Technical guidance on O&M cost analysis similarly stresses that:
Agencies “should maintain O&M cost records” that document baseline costs.
When defining an O&M cost baseline, it is recommended to use as much historical data as possible, and that historic O&M costs and actual site data should be used wherever possible.
Research on O&M budgeting practice has found that historical-based budgeting predominates among budgeting bases used in real facilities.
That is exactly what Option D describes: the facility manager’s historical record of actual costs is the correct and most defensible basis for making O&M budget decisions.
Why the others are less appropriate from a CSI/CDT standpoint:
A. Architect/engineer’s projected operating costs – A/E projections can be useful at early planning stages, but they are estimates, not verified costs. Once a facility has operating history, the A/E’s projections are secondary to actual cost data.
B. Construction manager’s life cycle analysis – Life-cycle cost analyses are valuable for choosing systems and strategies, but they are models and assumptions, not the primary budget baseline once real cost data exist.
C. Estimator’s preliminary project description – A Preliminary Project Description (PPD) is a design-stage estimating and scoping tool, not an operating-cost record. It has no direct tie to actual O&M performance.
Therefore, under CSI-aligned practice, the facility manager’s historical record of actual costs (Option D) is the correct basis.
Core CSI-aligned references for this question (no URLs):
CSI Project Delivery Practice Guide – chapters on facility management and life-cycle considerations.
DOE/FEMP guidance on O&M baselines and cost savings, stressing use of historic O&M cost data and actual site data.
Research on O&M budgeting showing predominance of historical-based budgeting.
The three types of commissioning include systems and equipment commissioning, building envelope commissioning, and what other process?
Mechanical commissioning
Facility commissioning
Process commissioning
Total project commissioning
CSI defines commissioning as a quality-focused process that verifies the facility and its systems meet the Owner’s Project Requirements (OPR). In the Project Delivery Practice Guide, commissioning is categorized into three broad types (paraphrased):
Systems and equipment commissioning – verifying that HVAC, electrical, plumbing, life safety, and other building systems perform as intended.
Building envelope commissioning – verifying performance of the exterior enclosure, including air/water infiltration, thermal performance, and durability.
Total project commissioning (also called whole-building or total building commissioning) – extending commissioning to the entire project, including design, construction, and operational aspects, integrating envelope, systems, and other building components.
Given that the question already lists “systems and equipment commissioning” and “building envelope commissioning,” the missing third category described by CSI is “total project commissioning”, which corresponds to Option D.
Why the other options are not correct:
A. Mechanical commissioning – This is a subset of systems and equipment commissioning (focused on HVAC/mechanical systems), not one of CSI’s three overarching categories.
B. Facility commissioning – While the term might be used informally, CSI’s categorized terminology in the CDT body of knowledge is “total project commissioning” rather than “facility commissioning.”
C. Process commissioning – This term is more common in industrial process industries and is not identified by CSI as one of the three principal commissioning categories for building projects.
CSI References (no links):
CSI Project Delivery Practice Guide – sections on commissioning types and scope (total project, systems and equipment, building envelope).
Which of the following statements best describes stakeholder and participant interest in a project?
Participants have direct interest in the project while stakeholders have indirect interest
Stakeholders have direct interest in the project while participants have indirect interest
Both stakeholders and participants have direct interest in the project
Both stakeholders and participants have indirect interest in the project
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
In CSI/CDT terminology, there is an important distinction between participants and stakeholders in a project:
Project participants are those who are formally part of the project delivery process, typically through a contractual or professional role. Examples: the owner, architect/engineer, contractor, and sometimes construction manager, commissioning authority, or key consultants. They:
Have direct responsibilities for planning, designing, constructing, administering, or managing the facility.
Are directly affected by project decisions and outcomes under the contracts and agreements.
Stakeholders are a broader group of parties who have an interest in the project, but many of them are not directly involved in performing the work or administering the contract. Examples include:
Users/occupants
Neighbors and surrounding community
Authorities having jurisdiction (from a public-interest standpoint)
Facility management staff, investors, or the general public
Their interest is often indirect—they are affected by the project’s performance, appearance, safety, cost, or impact, but they are not all active participants in day-to-day project execution or contract administration.
Because of this CSI distinction:
Participants → direct interests (active roles)
Stakeholders → often indirect interests (affected by, but not always performing, the work)
That matches Option A: Participants have direct interest in the project while stakeholders have indirect interest.
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – discussions of project participants vs. stakeholders and their roles throughout the facility life cycle.
CSI CDT Exam Study Materials – sections defining owner, design professional, contractor as participants, and users/community as stakeholders.
Which meeting is held for the purposes of introducing the design and construction teams, establishing the ground rules for communication, and explaining the administrative process?
Mobilization meeting
Preconstruction meeting
Prebid meeting
Coordination meeting
In CSI’s project delivery framework, the preconstruction meeting (often called the preconstruction conference) is a formal meeting held after award of the construction contract and before substantial field work begins. Its typical purposes match the stem of this question almost word-for-word:
Introduce the key members of the owner’s team, the design team, and the contractor’s team.
Review and establish communication protocols – who communicates with whom, in what format (letters, emails, RFIs, submittals), and through which channels (e.g., via the A/E as the owner’s representative).
Explain administrative procedures for submittals, RFIs, change orders, applications for payment, project meetings, record documents, and closeout requirements.
Clarify roles and responsibilities, lines of authority, and decision-making processes during construction.
Review the project schedule, major milestones, site logistics, and constraints so everyone begins the project with a common understanding.
These points are fully consistent with how CSI’s Project Delivery Practice Guide and typical Division 01 “Project Management and Coordination” sections describe the preconstruction conference: as the kickoff meeting for the construction phase, focused on communication, procedures, and administration—not bidding or detailed technical coordination.
Why the other options are not correct:
A. Mobilization meeting“Mobilization” refers to the contractor’s process of moving onto the site (bringing in equipment, setting up field offices, etc.). While a project might have discussions about mobilization, “mobilization meeting” is not the standard CSI project-delivery term for this formal kickoff. The structured, procedure-focused meeting described in the question is the preconstruction meeting.
C. Prebid meetingA prebid meeting (pre-bid conference) occurs during procurement, before bids are submitted. Its primary purposes are to familiarize prospective bidders with the project, review procurement requirements, visit the site, and answer questions that might affect bids. It does not introduce the already-selected construction team, nor does it establish the project’s communication and administrative procedures for contract execution. That occurs after award in the preconstruction meeting.
D. Coordination meetingCoordination meetings are typically recurring, working meetings during construction to resolve ongoing technical, scheduling, or coordination issues between trades (e.g., MEP coordination). They do not serve as the initial, formal kickoff to introduce teams and set overall administrative and communication “ground rules.”
Therefore, the meeting that introduces the design and construction teams, sets communication ground rules, and explains administrative processes is the Preconstruction meeting (Option B), as aligned with CSI project delivery and Division 01 practices.
Key CSI References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on Construction Phase and Project Meetings (Preconstruction Conference).
CSI Construction Specifications Practice Guide – discussions of Division 01 “Project Management and Coordination” and required project meetings.
CSI CDT Body of Knowledge – topic area: “Construction Phase Services and Communication.”
What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?
Building code
Quality control standard
Reference standard
Specification master
CSI’s terminology for specifications includes the concept of a “reference standard”, which is:
A requirement established by a recognized authority, by custom, or by general consensus.
An accepted criterion used to define properties, performance, or methods for materials, products, or workmanship (e.g., ASTM, ANSI, ACI, AISC, UL).
Cited in specifications so that, instead of repeating technical details, the spec simply references the named standard.
This is exactly the definition implied by the phrase “requirement set by authority, custom, or general consensus that is also an established accepted criterion.” That is the CSI definition of a standard, and in specification-writing context, specifically a reference standard. Hence the correct choice is C.
Why not the others:
A. Building code – A building code is a legal document adopted by public authority and enforced by the authority having jurisdiction; it is one type of regulatory document but not the generic term used in CSI for “established accepted criterion” used as a reference in specs.
B. Quality control standard – Quality control is a process; standards may be used within QC, but “quality control standard” is not the CSI term that matches this specific definition.
D. Specification master – CSI refers to master guide specifications or master specifications, but this is a spec-writing resource, not the formal term for a requirement established by authority or consensus.
CSI-aligned references (no URLs):
CSI Construction Specifications Practice Guide – explanations of standards and reference standard method of specifying.
CSI CDT Body of Knowledge – definitions of “standard” and “reference standard” in the context of specifications.
Cost classification, data organization, and specifications use which written formats?
OmniClass and UniFormat
UniFormat and MasterFormat
OmniClass and MasterFormat
SectionFormat® and MasterFormat
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI distinguishes among several written formats, each with a specific purpose:
UniFormat – organizes information by systems and assemblies (elements) and is commonly used for:
Cost classification and early cost estimating,
Data organization in the programming, schematic design, and design development stages.
MasterFormat – organizes information by work results (trades/products) and is used for:
Project specifications,
Detailed cost information tied to specification sections,
Organizing procurement and construction information.
CSI’s practice guides clearly connect cost classification and data organization in early design with UniFormat, and detailed specifications and later-stage cost information with MasterFormat. Therefore, the correct pair is:
UniFormat and MasterFormat (Option B)
Why the other options are incorrect:
A. OmniClass and UniFormat – OmniClass is a broader classification system for the built environment, not the primary written format CSI assigns to “specifications.” UniFormat is used for cost and systems, but OmniClass is not the standard format for specs.
C. OmniClass and MasterFormat – Again, OmniClass is overarching; it does not replace UniFormat as the main element-based cost classification tool.
D. SectionFormat and MasterFormat – SectionFormat is the internal three-part structure of a specification section (Parts 1, 2, and 3) and is not the format used for cost classification and data organization; that role is assigned to UniFormat.
Relevant CSI references (paraphrased):
CSI Project Delivery Practice Guide – descriptions of UniFormat use for system-based project descriptions and cost planning, and MasterFormat use for work result organization.
CSI Construction Specifications Practice Guide – chapters on MasterFormat, UniFormat, and their roles in specifications and estimating.
Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?
Warranty of title
Implied warranty of merchantability
Purchase warranty
Extended warranty
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI’s treatment of warranties in construction distinguishes among several types, including:
Warranty of title – assures that the seller/contractor has good title to goods and that they are free of liens or claims.
Implied warranties – such as merchantability and fitness for a particular purpose, arising under applicable law for goods.
Express warranties – explicitly stated in the contract documents or manufacturer literature, which may include extended warranties.
In the construction context, CSI’s project delivery and specification guidance emphasizes that extended warranties (often called special warranties in specifications):
Survive completion and acceptance of the project.
Provide remedies to the owner for defects in materials and/or workmanship that appear after substantial completion, often beyond the standard one-year correction period.
Are commonly used for critical building components (e.g., roofing systems, waterproofing, major equipment) and may run for 5, 10, or more years.
This directly matches the question’s language: a warranty “used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction.” That is precisely the purpose of an extended warranty in CSI-style contract documents and specifications, making Option D correct.
Why the other options are incorrect:
A. Warranty of titleThis deals with ownership and freedom from liens, not performance of materials or systems after completion. It does not address post-completion material defects.
B. Implied warranty of merchantabilityThis is a legal concept for goods: that they are fit for ordinary purposes. While it may apply in background law, it is not the specific contractual tool that owners rely on in construction documents to secure long-term remedies for material defects.
C. Purchase warranty“Purchase warranty” is not a standard CSI-defined category of construction warranty. Product or manufacturer warranties may be obtained at purchase, but the CSI terminology used in specifications and project delivery guidance is typically standard warranty, special warranty, or extended warranty, not “purchase warranty.”
Key CSI References (titles only):
CSI Project Delivery Practice Guide – sections on Warranties, Guarantees, and the Correction Period.
CSI Construction Specifications Practice Guide – guidance on specifying warranties (including extended warranties) in Division 01 and technical sections.
CSI CDT Body of Knowledge – “Contract Provisions: Warranties and Guarantees.”
Which of the following is a scaled view?
Perspective
Foundation plan
Riser diagram
Isometric
In CSI-based drawing conventions, a scaled view is one drawn at a stated scale so that actual dimensions can be measured directly from the drawing (e.g., 1:100, 1/4" = 1'-0"). CSI’s Uniform Drawing System (UDS) treats floor plans, roof plans, and foundation plans as primary orthographic views prepared at a defined scale for dimensioning and coordination between disciplines. These are the standard “working drawings” for construction.
Foundation plan (Option B)A foundation plan is an orthographic plan view drawn to a specific scale showing footings, slabs, and foundations with dimensions and notes. It is intended for measurement and layout, and CSI references it as one of the basic scaled plan views of the project drawings.
Why the other options are not correct:
A. Perspective – Perspectives are pictorial views used for visualization and presentation. CSI notes that such views are typically not used for taking dimensions and may not be drawn to a true working scale.
C. Riser diagram – Riser diagrams (for plumbing, fire protection, electrical, etc.) are diagrammatic, showing relationships and routing, not physical locations at scale. They are expressly identified as “not to scale” in most construction document standards.
D. Isometric – Isometric drawings are a type of pictorial/axonometric view used to show three-dimensional relationships. While they can sometimes be constructed proportionally, CSI’s guidance treats them as diagrammatic/pictorial views rather than the primary scaled working views used for dimensioning work in the field.
CSI References (no links):
CSI Uniform Drawing System (UDS) modules on drawing types and views (plan, elevation, section, diagrammatic views).
CSI Project Delivery Practice Guide – discussion of scaled plan views as part of the construction documents set.
Which of the following ensure that all systems work together effectively to meet the overall project performance goals?
Total project commissioning
Inspection by architect
Safety testing
Field testing
CSI describes commissioning as a quality-focused, systematic process for verifying and documenting that the facility and its systems meet the Owner’s Project Requirements (OPR). Within commissioning types, Total Project Commissioning (also called whole-building or total building commissioning) is defined as:
Encompassing the entire facility, including building envelope, systems, and interfaces.
Ensuring that all systems and assemblies operate together as an integrated whole to achieve performance targets (energy, comfort, safety, functionality, etc.).
Involving activities from design through occupancy: reviews, tests, training, and performance verification.
Because the question specifically asks for the process that ensures all systems work together effectively to meet overall project performance goals, that description matches Total Project Commissioning (Option A).
Why the others are incorrect:
B. Inspection by architect – A/E inspections or observations confirm general conformance with the contract documents but are not a comprehensive performance verification process for all systems.
C. Safety testing – Focuses only on safety-related aspects, not on full integration and performance of all systems.
D. Field testing – Typically refers to testing of specific components or systems in the field; it is one tool within commissioning, not the overall coordinating process.
Relevant CSI references (no links):
CSI Project Delivery Practice Guide – commissioning chapter (systems & equipment, building envelope, and total project commissioning).
CSI CDT Body of Knowledge – sections on commissioning scope, objectives, and responsibilities across project phases.