Question 1

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Question # 1

Question # 1

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Question 2

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

Options:

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Question 3

Which of the following is a potential challenge that may arise from language barriers among a project team?

Options:

A.

A project team is unable to communicate effectively due to a lack of common technical terminology and jargon.

B.

A project team refuses to learn foreign languages to cater to remote colleagues.

C.

A project team cannot use communication tools due to a lack of IT knowledge.

D.

A project team member located in a different time zone fails to access project resources.

Question 4

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

Options:

A.

Build

B.

Subscription

C.

Lease

D.

Buy

Question 5

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Options:

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.

Question 6

During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?

Options:

A.

Communicate the change status.

B.

Ask for a change request submission

C.

Escalate to the change control board

D.

Reject the change to prevent scope creep.

Question 7

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

Options:

A.

Reassess the resource pool.

B.

Review the QA plan from a similar project.

C.

Check on available resources for additional team members.

D.

Escalate the issue to the project sponsor.

Question 8

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

Options:

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Question 9

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

Options:

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Question 10

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Options:

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

Question 11

Which of the following items must be protected as Pll? (Select TWO).

Options:

A.

Job title

B.

Home address

C.

Work phone number

D.

Time zone

E.

Date of birth

F.

Blood type

Question 12

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Question 13

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Options:

A.

Compromising

B.

Forcing

C.

Smoothing

D.

Collaborating

Question 14

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

Options:

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Question 15

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

Options:

A.

SWOT

B.

Risk register

C.

Project schedule

D.

RAC

Question 16

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

Options:

A.

RFP

B.

RFQ

C.

RFB

D.

RFI

Question 17

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Question 18

A lessons-learned meeting took more than two hours and ended without defining a standardized process. The project manager decides to move forward without allowing changes to the existing process. Which of the following techniques is the project manager using?

Options:

A.

Forcing

B.

Avoiding

C.

Compromising

D.

Smoothing

Question 19

Which of the following PRINCE2 processes includes creating the project plan?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Managing product delivery

D.

Directing a project

Question 20

An enhancement is set to be released into production, and availability issues need to be avoided. Before the release, which of the following should be the most important consideration?

Options:

A.

System downtime

B.

Risk assessment

C.

Cost

D.

Customer experience

Question 21

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Options:

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Question 22

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.

Escalate directly to the project sponsor

B.

Push the kickoff meeting out by one week

C.

Proceed with the kickoff as planned

D.

Identity replacements for project stakeholders

Question 23

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

Options:

A.

Regression testing

B.

Smoke testing

C.

Stress testing

D.

Automation testing

Question 24

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Options:

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

Question 25

Which of the following activities should a project manager perform during the closing phase? (Select three).

Options:

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Question 26

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Question 27

Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?

Options:

A.

Start-to-start

B.

Start-to-finish

C.

Finish-to-finish

D.

Finish-to-start

Question 28

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

Options:

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Question 29

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Question 30

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Options:

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Question 31

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

Options:

A.

Forming, storming, performing, norming, adjourning

B.

Forming, performing, storming, norming, adjourning

C.

Forming, norming, storming, performing, adjourning

D.

Forming, storming, norming, performing, adjourning

Question 32

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

Options:

A.

Quote

B.

Information

C.

Proposal

D.

Bid

Question 33

Which of the following are primary features provided by a standard laaS solution? (Select two).

Options:

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Question 34

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Question 35

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Question 36

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

Options:

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Question 37

During the planning phase, a team agreed on the tasks, durations, predecessors, and resources needed to complete a project. Which of the following should be developed to formalize this agreement?

Options:

A.

Baseline

B.

RBS

C.

WBS

D.

Milestones

Question 38

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Options:

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

Question 39

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

Options:

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Question 40

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

Options:

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Question 41

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

Options:

A.

Grant the client access to the project repository.

B.

Create a chat to communicate in real time.

C.

Schedule a weekly status meeting.

D.

Send a weekly status report by email.

Question 42

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Options:

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

Question 43

Which of the following statements best describes zero-based budgeting?

Options:

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

Question 44

Which of the following should a product manager choose in order to enable collaboration between team members located in different regions? (Select two).

Options:

A.

Real-time surveys/polling

B.

Wiki knowledge base

C.

Spreadsheets

D.

Meetings/face-to-face

E.

Real-time, multi-authoring editing software

F.

Charting/diagramming

Question 45

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Question # 45

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Question 46

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.

B.

Work with the functional managers to create a work-around.

C.

Submit a change request to the change control board.

D.

Transfer the risk by hiring a new vendor who was successful on a previous project.

E.

Set up an escalation meeting with the sponsor.

Question 47

Which of the following best represents an intellectual property breach?

Options:

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Question 48

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

Options:

A.

Consult with the legal department.

B.

Update the issue log.

C.

Start a new RFP immediately.

D.

Perform a PERT analysis.

Question 49

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

Options:

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Question 50

During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

Options:

A.

Project dashboard

B.

Gap analysis

C.

Risk register

D.

Communication plan

Question 51

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Options:

A.

Social engineering

B.

Phishing

C.

Spoofing

D.

Hacking

Question 52

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?

Options:

A.

Change log

B.

Issue log

C.

Risk register

D.

Defect log

Question 53

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

Options:

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Question 54

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

Options:

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Question 55

Which of the following is a capital expense?

Options:

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Question 56

Which of the following is a consideration when determining a project's ESG factors?

Options:

A.

Project management methodology

B.

IT infrastructure security

C.

Proper accounting practices

D.

Corporate values compliance

Question 57

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

Options:

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Question 58

Which of the following software programs would be best to use to store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Question 59

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Options:

A.

Decline because it is not included in the project scope.

B.

Assess the impact of the request and create a change request

C.

Create new functional and non-functional requirements for mobile devices.

D.

Revise the baseline of the project plan by adding the new requirements.

Question 60

Which of the following best represents the project impact to a company's brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.The project meets the expected milestones and finishes on time and within budget.

Question 61

When assigning access, classifying information based on sensitivity is referred to as:

Options:

A.

Digital security

B.

Physical security

C.

Data security

D.

Operational security

Question 62

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

Options:

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Question 63

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

Question # 63

Part 2:

Question # 63

Options:

Question 64

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Question 65

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Question 66

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Question # 66

Select the Appropriate Tool:

Question # 66

Question # 66

Question # 66

Question # 66

Question # 66

Select the new critical path.

Option A

Question # 66

Option B

Question # 66

Option C

Question # 66

Question # 66

Options:

Question 67

Which of the following should occur first when planning maintenance windows?

Options:

A.

Diagnose potential areas for concern.

B.

Notify the customer base.

C.

Determine a rollback plan.

D.

Understand the organization's production cycle.

Question 68

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Question 69

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Question 70

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Question 71

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

Options:

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Question 72

Which of the following is a quantitative key performance indicator?

Options:

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Question 73

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

Options:

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Question 74

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?

Options:

A.

Agile

B.

Waterfall

C.

Standard

D.

Hybrid

Question 75

A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to

identify the level of engagement among project team members. Which of the following would be the best tool for the project manager to use?

Options:

A.

Meeting chat

B.

Email

C.

Real-time survey

D.

Whiteboard

Question 76

Which of the following provides the best justification for undertaking a project?

Options:

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

Question 77

Which of the following describes three-tier architecture?

Options:

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Question 78

During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?

Options:

A.

Preliminary scope statement

B.

Procurement needs assessment

C.

Project success criteria

D.

Work breakdown structure

Question 79

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

Options:

A.

Smoke testing

B.

Regression testing

C.

Unit testing

D.

User acceptance testing

Question 80

A project manager does not have the power to reward team members when they accomplish something or penalize them when they fail to perform well. As a result, the project manager is having issues with team members. Which of the following describes this organizational structure?

Options:

A.

Flat

B.

Projectized

C.

Weak matrix

D.

Functional

Question 81

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG

B.

PHI

C.

Pll

D.

ROI

Question 82

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Options:

A.

Implement the change.

B.

Approve the test plan.

C.

Notify customers.

D.

Develop a rollback plan.

Question 83

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Question 84

Which of the following aspects are true of agile as compared to waterfall? (Select two).

Options:

A.

Agile works through larger integrated teams.

B.

Agile promotes project manager ownership over deliverables.

C.

Agile reinforces the importance of comprehensive documentation.

D.

Agile has more customer involvement throughout development.

E.

Agile is more flexible to allow for changes in scope.

F.

Agile is comprised of well-defined phases.

Question 85

A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:

Options:

A.

the preferred sponsor's communication channel.

B.

the preferred project manager's communication channel.

C.

the preferred reported communication channel.

D.

email communication as the preferred communication channel.

Question 86

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

Options:

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

Question 87

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Question 88

How does data discovery assist with data classification'?

Options:

A.

It shows where specific data is stored

B.

It automatically classifies data by keywords

C.

It helps to identify the data owner

D.

It provides assurance of data integrity

Question 89

Which of the following software programs would be BEST to use lo store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Question 90

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Question 91

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

Options:

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Question 92

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Options:

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

Question 93

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Question 94

Question # 94

Given the following network diagram:

Which of the following is the critical path?

Options:

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

Question 95

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

Options:

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Question 96

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Options:

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Question 97

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Options:

A.

Assemble a new project with existing resources.

B.

Obtain the final report from release management.

C.

Notify the functional manager that resources are released.

D.

Allocate resources in a different project

Question 98

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

Options:

A.

Obtain details from the owner of the project.

B.

Update the critical path for the project.

C.

Apply contingency reserves.

D.

Reestimate epic user stories.

Question 99

Government projects require that personnel submit to background screenings for certain clearance requirements. Which of the following best describes this process?

Options:

A.

Data security

B.

Operational security

C.

Physical security

D.

Digital security

Question 100

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Options:

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Question 101

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Options:

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

Question 102

Which of the following best describes the difference between the current state and the desired future state in project management?

Options:

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.

B.

The current state is where the business is now, and the desired state is where the project is going to take the business.

C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.

D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.

Question 103

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps

Question 104

A company wants to move its data from on premises to off premises. Which of the following cloud models should be pursued?

Options:

A.

XaaS

B.

SaaS

C.

PaaS

D.

laaS

Question 105

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

Options:

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Question 106

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

Options:

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

Question 107

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

Options:

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group