Summer Sale Limited Time Flat 70% Discount offer - Ends in 0d 00h 00m 00s - Coupon code: 70spcl

Autodesk BIM_MGT_101 Autodesk Certified Professional in BIM Management for Building Design Exam Practice Test

Page: 1 / 6
Total 57 questions

Autodesk Certified Professional in BIM Management for Building Design Questions and Answers

Question 1

The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.

What fix needs to happen to resolve this misalignment?

Options:

A.

The BIM manager needs to go to a 3D view and move the model to align with the architectural geometry.

B.

The Lighting team needs to fix its shared coordinates to match those of the Architectural model and reissue the file.

C.

The BIM manager needs to acquire the shared coordinates of the CAD file.

D.

The Lighting team needs to add gridlines so the BIM manager can align its CAD file to the architectural gridlines.

Question 2

An AEC company has received a design model from the Architect of Record to begin creating construction documentation. The BIM Execution Plan identifies a fast-track delivery schedule, and the project team includes new consultants with limited exposure to the client’s preferred toolset and workflows. The BIM manager must determine how best to prepare the delivery team and assess the model’s compatibility with internal systems.

As the BIM manager prepares for the Project Kickoff meeting, which two pieces of information are most critical to avoid issues related to digital compatibility? (Select two.)

Options:

A.

Any add-ins required.

B.

Project units.

C.

Software version and build.

D.

Shared Coordinates.

E.

Graphic standards.

Question 3

Refer to the exhibit.

Question # 3

A designer cannot see a 2x4 tile ceiling in the hallway area of their Reflected Ceiling Plan, but that same ceiling is visible in a 3D view. The 2x2 ceilings in the other rooms are visible in both views.

What are two possible reasons for this? (Select two.)

Options:

A.

The ceiling was inadvertently deleted.

B.

A View Filter has been applied for that ceiling type.

C.

A View Template has been assigned with ceilings category visibility off.

D.

A Plan Region with a higher cut level has been applied to that area.

E.

Hide in View by Category was applied to that ceiling.

Question 4

During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high-impact clashes between structural, MEP, and architecture in specific zones.

For the BIM manager, what is the most appropriate next step to align clash reporting with the project’s coordination strategy?

Options:

A.

Share the full clash report with all project teams and instruct them to determine and resolve the issues they consider most important.

B.

Export the entire clash list into spreadsheet format so project managers can manually sort, review, and prioritize the items by trade.

C.

Disable or relax selected non-critical clash rules within the detection software to temporarily reduce the total number of reported issues.

D.

Apply the clash matrix to filter out low-priority clashes, adjust detection tolerances where appropriate, and produce reports for each discipline’s scope.

Question 5

The BIM manager is working in an Architectural model that uses the phases Existing and New Construction . They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.

Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?

Options:

A.

Apply a phase-filter override to the linked model using Visibility/Graphics settings.

B.

Open the linked model and manually change its phase names to match the host model.

C.

Map the linked model’s phases to the host model’s phases in the Revit Link properties.

D.

Override the linked view’s phase settings using view templates in the host model.

Question 6

During a project onboarding meeting, the client provides their current BIM standards and templates to the BIM manager. The project will involve multiple consultants across different regions and is being delivered under a fast-track schedule with a high volume of design iterations. The client has also indicated that they plan to use a new collaboration platform not previously piloted on similar project types.

The BIM manager must evaluate whether the client’s materials are sufficient and aligned with digital-delivery expectations, collaboration goals, and coordination requirements.

Given these factors, which two of the client’s BIM resources must be prioritized for review to evaluate their ability to support digital delivery and coordination across regions, teams, and time constraints? (Select two.)

Options:

A.

Confirm that shared-parameter files and naming conventions are consistent across provided templates and documentation to support data consistency.

B.

Review the provided project templates to confirm whether units, naming conventions, and view organization are consistent and support coordination.

C.

Prioritize identifying which users from the client’s team will need Revit training or software access before the project begins.

D.

Review previous projects’ sample sheets and title blocks to assess the visual style preferred by the client.

E.

Confirm whether the templates allow full customization by each discipline so teams can adapt the setup to their own preferences.

Question 7

The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.

What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?

Options:

A.

Facilitate a project-specific BIM kickoff session to align all contributors on workflows, deliverables, and data-handover protocols.

B.

Accept each firm’s standard BIM workflows and distribute them to the team to promote consistency across consultants.

C.

Focus on setting the Common Data Environment permissions first and allow teams to organize their workflows independently.

D.

Establish a baseline BIM Execution Plan, then adjust it incrementally based on coordination issues as they arise.

Question 8

A client has provided a resource model with many custom shared parameters required to meet the project data-management requirements across all of its projects with the firm. The BIM manager has extracted those parameters to the Parameters Service for wider firm access.

Which tool should a team member use to load the new shared parameters into a project model? (Select the correct tool on the image.)

Question # 8

Options:

Question 9

Refer to the exhibits.

Question # 9

Question # 9

Question # 9

Question # 9

A BIM manager is preparing a site model that includes three separate buildings. Which exhibit shows the correct way to assemble and position the individual building models on the site while maintaining proper coordinates and orientation?

Question # 9

Question # 9

Question # 9

Question # 9

Options:

A.

Exhibit 4

B.

Exhibit 3

C.

Exhibit 2

D.

Exhibit 1

Question 10

The BIM manager received a subcontractor’s 3D model containing specialty equipment to be integrated into the federated model. Upon review, they observe that:

    Many elements lack consistent object styles and category assignments.

    Some components are modelled with excessive detail, affecting performance.

    Embedded data does not follow the project’s naming conventions outlined in the BEP.

What is the most appropriate next step when evaluating this geometry and content?

Options:

A.

Instruct the subcontractor to simplify geometry and reduce file size, even if some metadata and classifications are lost.

B.

Approve the model as-is to avoid delaying coordination and document the issues for review at the next quality-control milestone.

C.

Review the model against content standards, document noncompliance, and request revisions aligned with agreed deliverable requirements.

D.

Import the model into the coordination environment and apply view filters to hide excessive detail and inconsistencies.

Question 11

During a model review, several linked files appear missing or unloadable in the federated coordination file. The files were present and working the day before, and no changes were made to the Revit host model itself.

As the BIM manager, what is the most appropriate step to troubleshoot the issue?

Options:

A.

Check that file paths to linked models were set as relative and validate that the folder structure remains unchanged.

B.

Ask the modelling team to rebind all linked models using absolute file paths.

C.

Remove the missing links and advise each team to reinsert their models before the next coordination meeting.

D.

Recreate the host model using a previous backup and manually reload each link.

Question 12

A design team requests a focused coordination review between the Architectural and Structural published design models. They want to exclude all other trades from the clash matrix.

What should the BIM manager do to ensure only the Architectural and Structural models are included in clash detection?

Options:

A.

Request each non-relevant discipline to temporarily remove its views from the coordination environment.

B.

Merge all models into a single federated model and manually hide non-relevant elements.

C.

Run clash detection on all models but only review the issues between Architectural and Structural.

D.

Assign only the Architectural and Structural models to a dedicated coordination group before running clash detection.

Question 13

Which of the following would typically be included in an AECO BIM data handover package at project closeout?

Options:

A.

Internal meeting notes from model coordination sessions.

B.

Federated design models used during clash detection.

C.

3D views used for clash detection during model coordination.

D.

Record models with the required asset data embedded.

Question 14

The BIM manager oversees both design coordination and post-handover data requirements and is asked to ensure the digital deliverables align with the owner’s long-term asset-management system.

To minimize information gaps, inconsistencies in file formats, and unclear responsibilities throughout delivery, which tool should the BIM manager rely on to define who provides what information, when, and in what format, from design through facilities handover?

Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

Options:

A.

The file-naming protocol and model-authoring standards.

B.

The Quantity Takeoff Checklist and/or the BIM Execution Plan.

C.

The Model Element Table and Level of Development (LOD) matrix.

D.

The Master Information Delivery Plan (MIDP) and/or the BIM Execution Plan.

Question 15

A BIM manager is running clash detection for the first time on a large retail project during the Design Development phase. After copying all the models to the coordination space on Autodesk Forma, the matrix shows no clashes among any of the models.

How should the BIM manager proceed?

Options:

A.

Add sheets to the publish settings and rerun the clash.

B.

Verify the shared coordinates for each model and republish.

C.

Continue forward on the project because there are no coordination issues.

D.

Use the project as a case study for a firm-wide presentation.

Question 16

The BIM Execution Plan (BEP) has just been completed for a new project. To ensure all multidisciplinary team members review and understand their roles and responsibilities, what is the most effective way to distribute the BEP before the project starts and ensure it remains accessible to everyone throughout the project?

Options:

A.

Include the BEP as part of the project contract and distribute it at project kickoff.

B.

Conduct a mandatory training session to review the BEP and archive it as official once approved by all disciplines.

C.

Upload the BEP to Autodesk Forma in a shared folder location to serve as a live copy.

D.

Email the BEP to all team members and request that they sign and return it as confirmation of review and agreement.

Question 17

What is included in a BIM Execution Plan?

Options:

A.

Project schedule and design playbook.

B.

Modeling standards and technology ecosystem.

C.

LOD Matrix and project specifications.

D.

Collaboration protocols and project playbook.

Page: 1 / 6
Total 57 questions