APMG-International AgilePM-Practitioner Agile Project Management (AgilePM) Practitioner Exam Exam Practice Test
Total 184 questions
Agile Project Management (AgilePM) Practitioner Exam Questions and Answers
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following question
about assigning the Agile Project Management team roles within this
project.
Lines 1 to 5 in the table below consist of an assertion statement and a
reason statement. For each line identify the appropriate option, from options
A to E. that applies. Each option can be used once, more than once or not
at all.

Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager

Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification ' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Xan Insurance Company is a friendly company with no separate private offices
for individual managers. Staff members prefer to wander around the office
space and have one-to-one chats rather than use email or have lots of
meetings.
What action should the Project Manager take when planning for effective
communication throughout the Web project?
Which 2 actions should the Team Leader take to implement the new Must
Have requirement?
A difference of opinion on the outcome of an earlier project has created a
' them and us ' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
Time is running short and the Must Have requirements for the data entry screen
of the web page, as recorded in the Prioritised Requirements List, are not going
to be completed on time.
What action should the Project Manager take?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk-
rounds of the new bedroom and en-suite bathroom facilities throughout the project.
Is this an appropriate application of Agile Project Management for this project?
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the
agreement of the team.
Which Agile principle MOST influences this course of action?
The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in
the gardens could be enjoyed.
Which Agile principle MOST influences this course of action?
Which 2 individuals would be suitable for the role of Workshop Facilitator?
A three-month timeframe has been specified to catch the seasonal sales window.
Which Agile principle MOST influences this course of action?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The ' Hoy for Hoy Hall ' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the ' Hoy for Hoy Hall ' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.

What action should the Project Manager take to plan the deployment activities?
Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.


Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the
project in the Prioritised Requirements List?
What action should the Project Manager take regarding the remaining windows?
When preparing for the workshop, which 2 items should the Workshop Facilitator be provided with?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Within Sales, which 2 people would be the BEST candidates to use as change agents, based on the descriptions given?
One member of the Customer Services team has been chatting informally to some Sales co-workers. They felt that the Sales process changes are causing more work for Customer Services and that the whole customer experience has now been compromised.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
For cognitive learning, which is the BEST example of providing ' learning feedback ' ?
Which 2 actions demonstrate transparency?
Which 2 actions demonstrate connectivity?
Answer the following questions about applying the principles for building
engagement to the Change Programme, defined by Hodges.
Which 2 actions demonstrate inclusivity?
The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.
Which preference does this behavior BEST display?
Answer the following question about different language style preferences
identified by Pashler et. al. using VARK preferences.
As part of the Capability and skills development workstream, the Human
Resources (HR) Manager is considering the training needs of staff
managers undertaking staff appraisals. The HR Manager is designing the
learning activities so that they will appeal to differing ways for receiving
and processing information.
Column 1 is a list of learning activities that could be used to develop the staff.
For each learning activity in Column 1, select from Column 2 the VARK
preference to which it relates. Each selection from Column 2 can be used
once, more than once or not at all.


Answer the following question about Schein ' s concept of survival and learning
anxieties.
Column 1 is a list of messages about the change given to Sales staff. For each
message in Column 1, select from Column 2 the appropriate element of
Schein ' s concept of survival and learning anxieties. Each selection from
Column 2 can be used once, more than once or not at all.


Which ' event ' BEST offers the opportunity to connect learning to the wider change initiative?
Sales staff are unhappy that they have been told that they will lose the Sales relaxation area completely to make space for the new Selco staff. The Sales staff are considering consulting their Union about escalating their discontent.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
Awareness of the new processes in the Customer Services department is good, but so far there has been little progress on implementation with the majority of staff.
Which approach is LEAST likely to build momentum for the changes?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the CEO is appropriate for the role of Sponsor for the Change Programme?
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock’s SCARF framework to increase the motivation for change.
One aim of the relocation is to develop a less hierarchical culture. The relocation team hear that staff believe managers are still getting special treatment in the allocation of desks. To mitigate this concern, they have planned for groups to move separately over a few weeks and have communicated details with each group independently.
Is this an appropriate approach to reward the brain in the need for ‘fairness,’ and why?
(Brinda Vyas has been absent for two weeks, leaving Mira Bachar and the Delivery Teams to make decisions. Recent strategic adjustments haven ' t been communicated to the Delivery Teams causing frustration and risk of rework.
Which 2 statements describe how this risk should be handled within the AgilePM framework?)
Mira Bachar has spoken with a guest who wanted an aromatherapy scent to remember their holiday. Inspired by this, Mira suggested creating a unique aromatherapy oil for spa treatments and guest sales, which could also serve as a marketing tool.
Brinda Vyas supports exploring the idea, but Sukra Aroon notes that selling products is not in scope and could introduce complexities.

(Selling aromatherapy oils to guests was not previously in scope.
Which 2 of the following actions align with AgilePM ' s guidance for handling Mira Bachar ' s suggestion?)
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Having provided some sample estimates for Hira to review, a number of stakeholders have challenged their accuracy—some suggesting that the work has been significantly over-estimated, while others believe it has been significantly under-estimated.
What should the Developers do?)
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote
deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush
and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(A treatment plant intended to add chlorine to the natural, pristine, river-sourced mineral water has been proposed as a Must Have requirement for hygiene reasons.
Is this aligned with the business vision?)
(New food hygiene laws take effect in six months. Sukra Aroon and Wanida Anong are assessing if kitchen remodeling is needed, which may divert Infrastructure Team resources.)
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(Which of the following describes AgilePM ' s approach to estimation?)
(Brinda believes that a meditation garden is essential for the holistic wellness experience, but Sukra, the Solution Architect, warns of risk associated with cultivating and maintaining the required plants.
How should Hira resolve this?)
(To keep Business Sponsor, Sarah, informed, Hira has set up a real-time dashboard displaying project progress, risks, and actions from planning events.
Will this meet Sarah ' s needs?)
As Sprint 5 comes to an end, the Infrastructure Delivery Team is facing delays due to:
. Heavy rainfall affecting the Wellness Garden.
. Local supplier issues causing material delivery delays.
· Dependency on external contractors for hydrotherapy equipment.
The Operations Delivery Team is unable to finalize details of the hydrotherapy treatments without testing them in the
context of the facilities being constructed. The marketing materials cannot be generated until this work is complete.
In addition to the Developers, the teams include:

(It is appropriate that the Delivery Team Leaders attend this Project Sprint Planning Event?)
(Hira is considering splitting the Developers into two Delivery Teams: one focused on Spa infrastructure and the other on guest experience. Mira Bachar, the Guest Services Manager, will be the Product Owner for both teams.

Which one of the following statements support Hira ' s proposed Delivery Team structure?)


(Which 2 statements describe appropriate team behaviour for effective risk management?)
(Lee Tan, General Manager of EPR Southeast Asia, is serving as a Business Advisor during Project Increment 4. He has not attended any Sprint Reviews, calling them " project meetings " and " a waste of time. " He later complains to Sarah about the lack of project awareness.
Which of the following actions reflects an AgilePM approach?)
Total 184 questions








